Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 29.67 |
Borrower/Recipient | 14.30 |
P098538
Closed
Neeta Hooda , Gayatri Kanungo
Republic of Ghana
April 1, 2010
(as of board presentation)
November 30, 2010
March 9, 2010
US$ 43.97 million
Ministry of Environment, Science, Technology and Innovation (MESTI)
2011
US$ 29.67 million
B
October 16, 2023
May 31, 2021
BANK APPROVED
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 29.67 |
Borrower/Recipient | 14.30 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 29.67 |
Total Project Cost** | 43.97 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2020-12-17 |
Procurement | Satisfactory | 2020-12-17 |
Financial Management | Moderately Satisfactory | 2020-12-17 |
Overall Implementation Progress (IP) | Satisfactory | 2020-12-17 |
Summary Global Objective Rating | Satisfactory | 2020-12-17 |
Counterpart Funding | Highly Satisfactory | 2020-12-17 |
Project Management | Satisfactory | 2020-12-17 |
Monitoring and Evaluation | Satisfactory | 2020-12-17 |
Overall Safeguards Rating | Satisfactory | 2020-12-17 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-24-2021 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Highly Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | High | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Land area where sustainable land mgt. practices were adopted as a result of proj | Value | 0.00 | 15861.85 | 15000.00 |
Date | January 20, 2011 | May 31, 2021 | May 20, 2016 | |
Comment |
Land users adopting sustainable land mgt. practices as a result of the project | Value | 0.00 | 42230.00 | 30000.00 |
Date | January 20, 2011 | May 31, 2021 | May 20, 2016 | |
Comment |
Management Effectiveness Tracking Tool score: Gbele Resource Reserve and Sanyiga Kasena Gavara Kara (SKGK), Moagduri Wuntanluri Kuwesaasi, Bulsa Yening, Wahabu Wiasi, and Gbele-Mole corridor sites | Value | 0.00 | 0.00 | 0.00 |
Date | July 1, 2010 | May 31, 2021 | May 20, 2016 | |
Comment |
Gbele Resource Reserve | Value | 45.00 | 70.00 | 0.00 |
Date | July 1, 2010 | |||
Comment |
Sanyiga Kasena Gavara Kara Corridor Site (CREMA Site 1) | Value | 28.00 | 29.00 | 0.00 |
Date | July 1, 2010 | |||
Comment |
Sissala Kasena Fraah Corridor Site (CREMA Site 2a) | Value | 21.00 | 24.00 | 0.00 |
Date | July 1, 2010 | |||
Comment |
Bulkawe Corridor Site (CREMA Site 2b) | Value | 21.00 | 24.00 | 0.00 |
Date | July 1, 2010 | |||
Comment |
Moagduri Wuntanluri Kuwesaasi Corridor Site (CREMA Site 3a) | Value | 21.00 | 24.00 | 0.00 |
Date | July 1, 2010 | |||
Comment |
Bulsa Yening Corridor Site (CREMA Site 3b) | Value | 21.00 | 24.00 | 0.00 |
Date | July 1, 2010 | |||
Comment |
Chakali Sungmaaluu Corridor (CREMA Site 4) | Value | 21.00 | 23.00 | 0.00 |
Date | July 1, 2010 | |||
Comment |
Direct project beneficiaries | Value | 0.00 | 63544.00 | 60000.00 |
Date | January 20, 2011 | May 31, 2021 | May 20, 2016 | |
Comment |
Female beneficiaries | Value | 0.00 | 55.50 | 0.00 |
Date | July 1, 2010 | May 9, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Integrated spatial development framework produced for Northern Savannah zone | Value | No | Yes | Yes |
Date | November 1, 2010 | May 31, 2021 | May 20, 2016 | |
Comment |
Project M&E system providing required reports and data in a timely manner | Value | No | Yes | Yes |
Date | January 20, 2011 | May 31, 2021 | May 20, 2016 | |
Comment |
Communities with Community Watershed Development Plans consistent with the Watershed Development Planning Manual | Value | 0.00 | 247.00 | 244.00 |
Date | July 30, 2010 | May 31, 2021 | May 20, 2016 | |
Comment |
Pre-feasibility studies conducted for new large-scale multi-purpose water storage investments | Value | 0.00 | 10.00 | 10.00 |
Date | July 30, 2010 | May 31, 2021 | November 30, 2020 | |
Comment |
Demonstration plots established in the target watersheds | Value | 0.00 | 344.00 | 282.00 |
Date | July 30, 2010 | May 31, 2021 | May 20, 2016 | |
Comment |
Targeted CREMA communities adopting management plans according to criteria defined in CREMA agreements | Value | 0.00 | 88.00 | 98.00 |
Date | July 30, 2010 | May 31, 2021 | May 20, 2016 | |
Comment |
A study on feasibility of sustaining SLWM activities through PES market mechanism | Value | No | Yes | Yes |
Date | July 30, 2010 | May 31, 2021 | May 20, 2016 | |
Comment |
Area reforested [within target forest reserves] | Value | 0.00 | 1060.00 | 1060.00 |
Date | January 20, 2011 | May 31, 2021 | May 20, 2016 | |
Comment |
Forest area brought under management plans | Value | 0.00 | 72716.00 | 72716.00 |
Date | January 20, 2011 | May 31, 2021 | May 20, 2016 | |
Comment |
Normalized Difference Vegetation Index (NDVI) in target areas | Value | -0.13 | 0.01 | 0.13 |
Date | June 2, 2014 | May 31, 2021 | May 20, 2016 | |
Comment |
Community governance structures established, trained and operational | Value | 115.00 | 340.00 | 347.00 |
Date | January 26, 2016 | May 31, 2021 | May 20, 2016 | |
Comment |
- CREMA Executive Committees | Value | 3.00 | 6.00 | 5.00 |
Date | January 26, 2016 | May 31, 2021 | May 20, 2016 | |
Comment |
-Community Watershed Management Teams | Value | 72.00 | 246.00 | 244.00 |
Date | January 26, 2016 | May 31, 2021 | May 20, 2016 | |
Comment |
- CREMA Resource Management Committees | Value | 40.00 | 88.00 | 98.00 |
Date | January 26, 2016 | May 31, 2021 | May 20, 2016 | |
Comment |
Forest users trained | Value | 0.00 | 821.00 | 660.00 |
Date | February 15, 2016 | May 31, 2021 | May 20, 2016 | |
Comment |
Forest users trained - Female | Value | 0.00 | 262.00 | 330.00 |
Date | February 15, 2016 | May 31, 2021 | May 20, 2016 | |
Comment |
Beneficiaries that feel project investments reflected their needs (percentage) | Value | 0.00 | 92.29 | 70.00 |
Date | February 15, 2016 | May 31, 2021 | May 20, 2016 | |
Comment |
Beneficiaries that feel project inv. reflected their needs - female (number) | Value | 0.00 | 0.00 | 0.00 |
Date | February 21, 2016 | |||
Comment |
Total beneficiaries - female (number) | Value | 0.00 | 0.00 | 0.00 |
Date | February 21, 2016 | |||
Comment |
Total beneficiaries - male (number) | Value | 0.00 | 0.00 | 0.00 |
Date | February 21, 2016 | |||
Comment |
Beneficiaries that feel project inv. reflected their needs - male (number) | Value | 0.00 | 0.00 | 0.00 |
Date | February 21, 2016 | |||
Comment |
New areas outside protected areas managed as biodiversity-friendly (ha) | Value | 39107.00 | 600995.71 | 417299.00 |
Date | February 15, 2016 | May 31, 2021 | May 20, 2016 | |
Comment |
Smallholder households supported in coping with the effects of climate change [in 76 communities under AF2] | Value | 0.00 | 3045.00 | 3000.00 |
Date | January 26, 2016 | May 31, 2021 | May 20, 2016 | |
Comment |