Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 10.00 |
GLOBAL ENVIRONMENT - Associated IBRD Fund | 30.00 |
P098838
Closed
Christian Peter
N/A
Costa Rica
June 8, 2006
(as of board presentation)
June 8, 2006
July 31, 2008
US$ 40.00 million
N/A
2006
US$ 10.00 million
B
March 15, 2022
March 31, 2014
BANK APPROVED
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 10.00 |
GLOBAL ENVIRONMENT - Associated IBRD Fund | 30.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 10.00 |
Total Project Cost** | 40.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2014-03-26 |
Financial Management | Moderately Satisfactory | 2014-03-26 |
Overall Safeguards Rating | Moderately Satisfactory | 2014-03-26 |
Summary Global Objective Rating | Moderately Satisfactory | 2014-03-26 |
Procurement | Satisfactory | 2014-03-26 |
Project Management | Satisfactory | 2014-03-26 |
Monitoring and Evaluation | Satisfactory | 2014-03-26 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2014-03-26 |
Overall Safeguards Rating | Moderately Satisfactory | 2014-03-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
By the end of the project, at least 288,000 hectares of land with environmental service contracts generating environmental servicesof local, national and/or global importance. | Value | 250,000 ha | 282,989 ha | 288,000 ha |
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment | Comments: 612 new environmental service contracts were signed under different PSA modalities. The first payment of 302 of the 612contracts was paid with the 50 % of the first disbursement from the loan (USD$1.5 million) |
By the end of the project, at least half of the newly-contracted area is financed by funding from service users. | Value | 0% | 0% TOR for contracts to identify funding from serv | 50% |
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment | Comments: The expected level of funds coming from watersheds users has not been reached. A consultant has been hired by FONAFIFO toevaluate the situation. This indicator will be measured on the last year of theproject implementation. |
Improved efficiency of the environmental services program, as measured by indices of services generated per dollar spent.(Index under preparation) | Value | Index under preparation. | ||
Date | February 15, 2010 | |||
Comment | Comments: FONAFIFO is preparing an index on PSA participant#s costs and benefits. Administrative costs should be reduced, inparticular regarding the simplifica tion process of contract renewal. |
By the end of the project 50% increase (from current 1,900 to 2,850) of the number of small- and medium-sized landholders (less than 100-hectare farms) participating in the PSA Program. | Value | 1,900 landholders (small- and medium-sized) | Index under preparation | 2,850 landholders |
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment | Comments: Index under preparation on number of contracts paid from July 2008 until now, including information about how many ofthose contracts include less th an 100 ha per land. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Effective biodiversity conservation in globally significant areas measured by vegetation cover and indicator species of conservation interest (method under preparation, baseline to be ready by 12/07). | Value | Indicator under preparation. | ||
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment | Comments: Importance of signing a contract with the National Institute of Biodiversity for the development of this indicator. |
3.5% from fuel-tax revenues and 25% water-resource-usage tariffs to finance PSA. | Value | 3.5% | In 2010, approximately USD$ 20 Million will be tra | 3.5% |
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment |
FBS with capital participation of at least US$15 million, of which US$7.5 million contributed by GEF. | Value | US$0 | FBS was created. | US$15 total of which US$7.5 from GEF. |
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment | Comments: FONAFIFO is on the process of reviewing five different proposals for the Fiduciary Bank. |
At least 75% of PSA Program resources are placed in PSA contracts. | Value | Present percentage to be evaluated during year 1 o | 20% of the disbursed funds are being committed to | 75% |
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment |
Contract system for payments of environmental services with differentiated payments applied. | Value | Does not exist | Three different kind of PSA contracts are being de | Differentiated system is approved and under implem |
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment |
PSA activities are integrated through participatory planning on land use in at least 3 (micro-watershed) communities. | Value | 0 micro-watersheds | TORs for 1 watershed were approved (Watershed Rive | 3 micro-watersheds |
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment |
Female landholders and Indigenous community owned lands in the program will be maintained at least to the current level. | Value | 10% of contracted area is held by female-led famil | 10% of the new contracts have been signed by femal | 10% of contracted area each |
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment |
3.5% from fuel-tax revenues and 25% water-resource-usage tariffs to finance PSA. | Value | 3.5% | 3.5% | 3.5% |
Date | June 8, 2006 | May 29, 2009 | July 31, 2012 | |
Comment |
FBS with capital participation of at least US$15 million, of which US$7.5 million contributed by GEF. | Value | US$0 | US$0 | US$15 total of which US$7.5 from GEF. |
Date | June 8, 2006 | May 29, 2009 | July 31, 2012 | |
Comment |
At least 75% of PSA Program resources are placed in PSA contracts. | Value | Present percentage to be evaluated during year 1 o | N/A | 75% |
Date | June 8, 2006 | May 29, 2009 | July 31, 2012 | |
Comment |
Contract system for payments of environmental services with differentiated payments applied. | Value | Does not exist | Does not exist | Differentiated system is approved and under implem |
Date | June 8, 2006 | May 29, 2009 | July 31, 2012 | |
Comment |
PSA activities are integrated through participatory planning on land use in at least 3 (micro-watershed) communities. | Value | 0 micro-watersheds | 0 micro-watersheds | 3 micro-watersheds |
Date | June 8, 2006 | May 29, 2009 | July 31, 2012 | |
Comment |
Female landholders and Indigenous community owned lands in the program will be maintained at least to the current level. | Value | 10% of contracted area is held by female-led famil | 10% of contracted area each | 10% of contracted area each |
Date | June 8, 2006 | May 29, 2009 | July 31, 2012 | |
Comment |
At least 190,000 ha (2,000 contracts) in productive landscapes in the buffer zones of protected areas and biological corridors in the MBC are maintained annually under PSA contracts of 20 years. | Value | Contracts signed represent less than 10% of the co | ||
Date | June 8, 2006 | February 15, 2010 | July 31, 2012 | |
Comment | Comments: Importance of simplification of contract renewal every five years |