Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IDA Fund | 3.50 |
Borrower/Recipient | 10.00 |
NETHERLANDS: Min. of Foreign Affairs / Min. of Dev. Coop. | 6.00 |
IDA Grant | 3.50 |
P099321
Closed
Peter Johansen
N/A
July 20, 2006
(as of board presentation)
December 19, 2006
May 4, 2007
US$ 23.00 million
N/A
2007
US$ 9.50 million
C
January 15, 2013
June 30, 2012
BANK APPROVED
Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IDA Fund | 3.50 |
Borrower/Recipient | 10.00 |
NETHERLANDS: Min. of Foreign Affairs / Min. of Dev. Coop. | 6.00 |
IDA Grant | 3.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 3.50 |
IBRD + IDA Commitment | 3.50 |
Lending Instrument | |
---|---|
Grant Amount | 6.00 |
Total Project Cost** | 23.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 19, 2006 | IDA-H2630 | Loan Commitment | 3,500,000.00 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Satisfactory | 2012-01-18 |
Overall Implementation Progress (IP) | Highly Satisfactory | 2012-01-18 |
Project Management | Satisfactory | 2012-01-18 |
Progress towards achievement of PDO | Highly Satisfactory | 2012-01-18 |
Procurement | Satisfactory | 2012-01-18 |
Counterpart Funding | Highly Satisfactory | 2012-01-18 |
Financial Management | Satisfactory | 2012-01-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-17-2012 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 10-03-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: 06-15-2018 |
---|---|---|
Outcome Rating | Moderately Satisfactory | Moderately Satisfactory |
Risk To Development Outcome | Moderate | Substantial |
Bank Performance | Moderately Satisfactory | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory | Moderately Satisfactory |
Government Performance | Satisfactory | Not Rated |
Implementing Agency | Moderately Satisfactory | Moderately Satisfactory |
Icr Quality | Satisfactory | Not Rated |
M&e Quality | Substantial | Modest |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% of herders served by SHS and WTS | Value | 15% | 54.4% | 50% |
Date | December 31, 2006 | December 1, 2011 | June 30, 2012 | |
Comment | Total of 32,922 pieces SHSs were delivered to the herders under the 100,000 solar ger national program. | Total of 54,841 herder families have received SHSs under the project for a total of 87,763 systems. (Mongolia has approximately160,000 herder families.) |
Number of people in off-grid soums with renewable electricity | Value | negligible | 18,410 | 16,000 |
Date | December 31, 2006 | November 8, 2011 | June 30, 2012 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of RET Information Centers established | Value | 0 | 50 | 50 |
Date | December 31, 2006 | December 1, 2011 | June 30, 2012 | |
Comment |
Total sale of SHS systems under project | Value | 0 | 54,841 | 50,000 |
Date | December 31, 2006 | December 1, 2011 | June 30, 2012 | |
Comment | The project is on track to reach 67,224 by closing. |
Establishment of Soum User Associations | Value | 0 | 15 | 30 |
Date | December 31, 2006 | December 1, 2011 | June 30, 2012 | |
Comment |
Establishment of Soum Utilities | Value | 0 | 15 | 30 |
Date | December 31, 2006 | November 8, 2011 | June 30, 2012 | |
Comment | The soum utilities are administered by the Aimag level utilities. Since the remaining 15 soums are connected to the grid, thereisno need for separate utilities. |
Soum grids that are rehabilitated | Value | 0 | 30 | 30 |
Date | December 31, 2006 | November 8, 2011 | June 30, 2012 | |
Comment | 15 rehabilitated by the project and 15 by Government funds |
Number of renewable hybrid systems (RET) built | Value | 0 | 15 (+5 connected to grid) | 20 |
Date | December 31, 2006 | November 8, 2011 | June 30, 2012 | |
Comment |
Estimated GHG emissions reduced as a result of project | Value | 0 | unknown | 9,000 t per year |
Date | December 31, 2006 | November 8, 2011 | June 30, 2012 | |
Comment | Estimate based on projection at design. Will be calculated at conclusion of project when systems have been in operation. |