Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 5.50 |
P099528
Closed
Cesar Niculescu
Ministry of Finance
Romania
February 28, 2006
(as of board presentation)
October 30, 2007
December 8, 2008
US$ 5.50 million
Ministry of Environment, Waters and Forests
2008
US$ 5.50 million
B
N/A
December 31, 2023
BANK APPROVED
March 21, 2024
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 5.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 5.50 |
Total Project Cost** | 5.50 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2023-12-19 |
Procurement | Satisfactory | 2023-12-19 |
Financial Management | Satisfactory | 2023-12-19 |
Project Management | Satisfactory | 2023-12-19 |
Monitoring and Evaluation | Moderately Satisfactory | 2023-12-19 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-09-2016 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |