Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 4.00 |
Borrower/Recipient | 5.00 |
P099757
Closed
Nguyet Anh Pham
N/A
November 8, 2007
(as of board presentation)
May 29, 2008
June 23, 2008
US$ 9.00 million
N/A
2008
US$ 4.00 million
C
February 13, 2013
June 30, 2013
BANK APPROVED
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 4.00 |
Borrower/Recipient | 5.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 4.00 |
Total Project Cost** | 9.00 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Moderately Satisfactory | 2013-06-25 |
Summary Global Objective Rating | Unsatisfactory | 2013-06-25 |
Procurement | Moderately Unsatisfactory | 2013-06-25 |
Counterpart Funding | Satisfactory | 2013-06-25 |
Overall Implementation Progress (IP) | Unsatisfactory | 2013-06-25 |
Project Management | Unsatisfactory | 2013-06-25 |
Financial Management | Moderately Unsatisfactory | 2013-06-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-30-2013 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 10-14-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Relevant agencies for undertaking geothermal transactions trained through on-the-job programs as well as 5-10 workshops and seminars | Value | N/A | Achieved | 7 workshops held |
Date | May 29, 2008 | June 10, 2013 | June 30, 2013 | |
Comment | Several workshops were organized on pricing isues | Achieved |
Awareness raising and information dissemination activities about sector policies and business opportunities conducted through promotional campaigns including 5-10 stakeholder dialogue seminars | Value | N/A | Canceled | 7 workshops held |
Date | May 29, 2008 | June 10, 2013 | June 30, 2013 | |
Comment | MEMR uses its own resources for the awareness program |
Strategy for domestic geothermal technology development formulated | Value | N/A | Partially achieved. | Strategy drafted |
Date | May 29, 2008 | June 10, 2013 | June 30, 2013 | |
Comment | Alternate approach whereby World Bank has assisted PGE, largest public geothermal developer, with separate capacity building grantto enhance its efficiency and reduce costs by meeting industry and international standards. This has been successfully completedwith the preparation of three projects. Private developers are not expected to need such assistance. |
Installed geothermal power capacity (including financial closure) resulting from the investment transactions assisted by the Project | Value | 0.00 | 0.00 | 350.00 |
Date | June 10, 2013 | June 30, 2013 | ||
Comment | No investment transactions supported by the project. The previous values were deleted as it was not supported by the project.Thetarget is unlikely to be achieved. |
Reduction CO2 emissions by off-setting fossil fuel based power generation (i.e. coal) with geothermal power | Value | 0.00 | 0.00 | 2000000.00 |
Date | June 10, 2013 | June 30, 2013 | ||
Comment | No reduction of CO2 emission is expected as no investment transactions supported by the project. The target is unlilkely to beachieved. |
Pricing mechanism to provide adequate economic incentive developed | Value | N/A | FIT mechanism issued in August 2012, but not appl | Pricing mechanism applied in transactions |
Date | May 29, 2008 | June 10, 2013 | June 30, 2013 | |
Comment | The regulation is under revision by MEMR. It is not clear whether the new pricing mechanism will provide adequate incentives |
Upstream resource risk mitigation mechanism developed | Value | N/A | Achieved | Implementation arrangement developed |
Date | May 29, 2008 | June 10, 2013 | June 30, 2013 | |
Comment | MOF established Geothermal Funds to support upstream exploration activities using its own funds. Likely to be achieved |
Implementation regulations of the Geothermal Law issued | Value | N/A | Achieved | |
Date | May 29, 2008 | June 10, 2013 | June 30, 2013 | |
Comment | Regulation GR59 is already issued.Promulgated |
Model procedures and standardized documentation for competitive bidding of geothermal power transactions developed | Value | N/A | Completed | Applied |
Date | May 29, 2008 | June 10, 2013 | June 30, 2013 | |
Comment | Documentation developed, but no transaction has been conducted to apply it. | Potential change in regulation may require revision of the documents. |
Structure offers to mobilize investments for additional geothermal power in fields that are controlled by existing operators | Value | N/A | Not applicable | Target Achieved |
Date | May 29, 2008 | June 10, 2013 | June 30, 2013 | |
Comment | Await revision of pricing decision |
Develop and implement a pilot transaction for one power project in a new geothermal field competitively tendered based on the Geothermal Law | Value | N/A | Not applicable | Target achieved |
Date | May 29, 2008 | June 10, 2013 | June 30, 2013 | |
Comment | No transactions have taken place as the revision of the geothermal law is still pending to allow any new geothermal tendering. |