The objectives of the Municipal Infrastructure Development Project for Bulgaria are to: (a) improve the reliability and quality of water provision to the communities in selected settlements in the project area; and (b) assist municipalities to improve investment-planning capacity. There are three components to the project: (1) project implementation support to carry out activities under component three of the project and consultant services associated...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project objectives are to: (a) improve bulk potable water provision in target areas, and (b) assist municipalities to improve investment-planning capacity. These objectives are in line with Bulgaria's National Strategy on Environment (2005-2014) which has a goal to provide good quality and sufficient quantity of water for various purposes.

Key Details

Project Details

  • P099895

  • Closed

  • Toma Yanakiev

  • Republic of Bulgaria

  • Bulgaria

  • July 19, 2006

  • (as of board presentation)

    November 24, 2009

  • April 30, 2010

  • US$ 148.30 million

  • Ministry of Regional Development and Public Works

  • Europe and Central Asia

  • 2010

  • US$ 118.70 million

  • A

  • October 12, 2023

  • December 31, 2019

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 29.60
International Bank for Reconstruction and Development 118.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 118.70
IDA Commitment N/A
IBRD + IDA Commitment 118.70
Lending Instrument
Grant Amount N/A
Total Project Cost** 148.30

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 9, 2018 IBRD-78340 Loan Disb 2,454,600.00
Apr 15, 2018 IBRD-78340 Loan Repay 1,908,979.60
Dec 18, 2019 IBRD-78340 Loan Disb 2,926,532.50
Oct 15, 2019 IBRD-78340 Loan Repay 2,551,984.00
Apr 15, 2019 IBRD-78340 Loan Repay 2,382,514.20
Mar 21, 2019 IBRD-78340 Loan Disb 4,543,442.00
Apr 15, 2016 IBRD-78340 Int Charges 17,761.30
Dec 1, 2017 IBRD-78340 Loan Disb 3,689,155.00
Sep 14, 2017 IBRD-78340 Loan Disb 1,904,160.00
Oct 15, 2017 IBRD-78340 Loan Repay 1,579,089.40
Apr 15, 2017 IBRD-78340 Loan Repay 1,238,179.00
Apr 15, 2017 IBRD-78340 Int Charges 10.03
Jun 23, 2017 IBRD-78340 Loan Disb 2,680,200.00
May 10, 2017 IBRD-78340 Loan Disb 1,630,275.00
Dec 18, 2018 IBRD-78340 Loan Disb 2,136,281.20
Sep 17, 2018 IBRD-78340 Loan Disb 583,100.00
Aug 24, 2018 IBRD-78340 Loan Disb 1,737,075.00
Jun 22, 2018 IBRD-78340 Loan Disb 3,492,750.00
Oct 24, 2018 IBRD-78340 Loan Disb 2,853,250.00
Oct 15, 2018 IBRD-78340 Loan Repay 2,073,280.80
Oct 15, 2020 IBRD-78340 Int Charges 36,981.34
Oct 15, 2020 IBRD-78340 Loan Repay 2,785,234.20
Jul 21, 2020 IBRD-78340 Loan Cancel 18,731,778.00
Jul 21, 2020 IBRD-78340 Loan Disb -1,056,637.00
Oct 15, 2020 IBRD-78340 Loan Repay 36,981.34
Apr 15, 2020 IBRD-78340 Loan Repay 2,686,470.20
Apr 15, 2022 IBRD-78340 Loan Repay 2,603,288.00
Oct 15, 2021 IBRD-78340 Loan Repay 2,796,565.80
Apr 15, 2021 IBRD-78340 Loan Repay 2,881,583.80
Oct 15, 2022 IBRD-78340 Loan Repay 2,344,621.00
Oct 15, 2023 IBRD-78340 Int Charges 527,474.10
Oct 15, 2023 IBRD-78340 Loan Repay 2,005,728.10
Oct 15, 2023 IBRD-78340 Loan Repay 527,474.10
Apr 15, 2023 IBRD-78340 Loan Repay 2,663,378.80
Apr 15, 2023 IBRD-78340 Int Charges 369,453.44
Nov 24, 2009 IBRD-78340 Loan Commitment 118,700,000.00
Apr 15, 2024 IBRD-78340 Loan Repay 566,524.56
Apr 15, 2024 IBRD-78340 Int Charges 566,524.56
Apr 15, 2024 IBRD-78340 Loan Repay 2,000,155.00
Dec 19, 2014 IBRD-78340 Loan Disb 1,778,207.50
Oct 15, 2014 IBRD-78340 Int Charges 39,087.02
May 15, 2014 IBRD-78340 Loan Cancel 15,023,250.00
Oct 15, 2013 IBRD-78340 Int Charges 12,772.83
Jan 24, 2014 IBRD-78340 Loan Disb 2,469,510.00
Jul 1, 2014 IBRD-78340 Loan Disb 2,053,425.00
Apr 15, 2014 IBRD-78340 Int Charges 25,091.60
Nov 20, 2013 IBRD-78340 Loan Disb 5,275,140.00
Jun 26, 2015 IBRD-78340 Loan Disb 1,680,450.00
Dec 7, 2015 IBRD-78340 Loan Disb 2,161,300.00
Oct 15, 2015 IBRD-78340 Int Charges 18,845.31
Apr 15, 2015 IBRD-78340 Int Charges 19,775.54
Oct 31, 2016 IBRD-78340 Loan Disb 4,217,482.50
Dec 8, 2016 IBRD-78340 Loan Disb 3,990,080.00
Oct 15, 2016 IBRD-78340 Int Charges 2,144.13
Sep 28, 2016 IBRD-78340 Loan Disb 1,121,750.00
Jun 30, 2016 IBRD-78340 Loan Disb 668,760.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Moderately Satisfactory 2019-06-03
Financial Management Satisfactory 2019-06-03
Monitoring and Evaluation Satisfactory 2019-06-03
Progress towards achievement of PDO Moderately Unsatisfactory 2019-06-03
Project Management Moderately Satisfactory 2019-06-03
Procurement Moderately Satisfactory 2019-06-03
Overall Implementation Progress (IP) Moderately Unsatisfactory 2019-06-03

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-22-2020
OutcomesModerately Unsatisfactory
Risk to Development Outcome
Bank PerformanceModerately Unsatisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-30-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • (Revised June2016) Percentage of samples from the water produced by the dams and WTPs, completed under the project, meeting nationalstandardsValue0.00100.000.00
    DateNovember 2, 2009December 13, 2019
    Comment
  • (Revised Feb2014) Number of regional master plans for water supply and sewerage systems, of satisfactory quality for acceptance byBulgaria and EC, to support investments in service deliveryValue0.0051.000.00
    DateNovember 2, 2009December 13, 2019
    Comment
  • Volume of additional potable water (number of cubic meters/year) produced by the dams and WTPs, completed under the project.Value0.002022560.000.00
    DateNovember 2, 2009December 13, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • (Revised June 2014) Component 2: Diagnosis of the present situation and investment needs completed, as part of Master Plans preparation, and submitted to the MRD and Water AssociationsValue0.00100.000.00
    DateNovember 2, 2009June 4, 2018
    Comment
  • Number of water utilities that the project is supportingValue0.0051.000.00
    DateDecember 8, 2012December 6, 2018
    Comment
  • (Revised May2011) Component 3: Preparatory works for dams and water treatment plants completed (% progress)Value0.00100.000.00
    DateNovember 2, 2009December 13, 2019
    Comment
  • (Revised June2016) Component 3: Construction works for water treatment plants completed and equipment installed (% progress)Value0.0052.800.00
    DateNovember 2, 2009December 13, 2019
    Comment
  • (Revised June2016) Component 3: Construction works for dams completed (% progress)Value0.0075.600.00
    DateNovember 2, 2009December 13, 2019
    Comment
  • Direct project beneficiariesValue0.0019616.000.00
    DateNovember 2, 2009May 27, 2019
    Comment
  • Female beneficiariesValue0.000.000.00
    DateNovember 2, 2009June 4, 2018
    Comment