Financier | Commitments |
---|---|
IDA Credit | 10.00 |
P100807
Closed
Maria Manuela Do Rosario Francisco
N/A
February 7, 2007
(as of board presentation)
March 27, 2007
July 5, 2007
US$ 10.00 million
N/A
2007
US$ 10.00 million
N/A
Not Applicable
December 31, 2007
BANK APPROVED
March 6, 2024
Financier | Commitments |
---|---|
IDA Credit | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 10.00 |
IBRD + IDA Commitment | 10.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 10.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2024 | IDA-42800 | Loan Repay | 89,744.54 |
Feb 15, 2024 | IDA-42800 | Int Charges | 29,346.76 |
Feb 15, 2024 | IDA-42800 | Int Charges | 29,346.76 |
Mar 27, 2007 | IDA-42800 | Loan Commitment | 10,000,000.00 |
Feb 16, 2022 | IDA-42800 | Loan Repay | 93,801.97 |
Feb 16, 2022 | IDA-42800 | Int Charges | 3.97 |
Feb 16, 2022 | IDA-42800 | Int Charges | 3.97 |
Feb 16, 2022 | IDA-42800 | Int Charges | 31,985.92 |
Feb 16, 2022 | IDA-42800 | Int Charges | 31,985.92 |
Feb 15, 2022 | IDA-42800 | Loan Repay | 1,583.54 |
Aug 16, 2022 | IDA-42800 | Int Charges | 530.10 |
Aug 16, 2022 | IDA-42800 | Int Charges | 530.10 |
Aug 16, 2022 | IDA-42800 | Loan Repay | 89,474.40 |
Aug 16, 2022 | IDA-42800 | Int Charges | 1.84 |
Aug 16, 2022 | IDA-42800 | Int Charges | 1.84 |
Aug 16, 2022 | IDA-42800 | Int Charges | 30,197.61 |
Aug 16, 2022 | IDA-42800 | Int Charges | 30,197.61 |
Feb 15, 2023 | IDA-42800 | Loan Repay | 1,463.49 |
Feb 15, 2023 | IDA-42800 | Loan Repay | 89,478.35 |
Feb 15, 2023 | IDA-42800 | Int Charges | 1.89 |
Feb 15, 2023 | IDA-42800 | Int Charges | 1.89 |
Feb 15, 2023 | IDA-42800 | Int Charges | 29,755.96 |
Feb 15, 2023 | IDA-42800 | Int Charges | 29,755.96 |
Aug 15, 2023 | IDA-42800 | Int Charges | 593.64 |
Aug 15, 2023 | IDA-42800 | Int Charges | 593.64 |
Aug 15, 2023 | IDA-42800 | Loan Repay | 90,599.80 |
Aug 15, 2023 | IDA-42800 | Int Charges | 29,897.93 |
Aug 15, 2019 | IDA-42800 | Loan Repay | 93,458.52 |
Aug 15, 2019 | IDA-42800 | Int Charges | 33,645.07 |
Aug 15, 2019 | IDA-42800 | Int Charges | 33,645.07 |
Feb 15, 2020 | IDA-42800 | Loan Repay | 831.30 |
Feb 15, 2020 | IDA-42800 | Loan Repay | 92,159.38 |
Feb 15, 2020 | IDA-42800 | Int Charges | 33,127.93 |
Feb 15, 2020 | IDA-42800 | Int Charges | 33,127.93 |
Aug 15, 2020 | IDA-42800 | Loan Repay | 1,529.09 |
Aug 15, 2020 | IDA-42800 | Loan Repay | 94,329.15 |
Aug 15, 2020 | IDA-42800 | Int Charges | 31,000.58 |
Aug 15, 2020 | IDA-42800 | Int Charges | 31,000.58 |
Feb 15, 2021 | IDA-42800 | Loan Repay | 97,971.00 |
Feb 15, 2021 | IDA-42800 | Int Charges | 33,907.85 |
Feb 15, 2021 | IDA-42800 | Int Charges | 33,907.85 |
Feb 15, 2021 | IDA-42800 | Int Charges | 2,850.93 |
Feb 15, 2021 | IDA-42800 | Int Charges | 2,850.93 |
Aug 17, 2021 | IDA-42800 | Int Charges | 256.14 |
Aug 17, 2021 | IDA-42800 | Int Charges | 33,357.54 |
Aug 17, 2021 | IDA-42800 | Int Charges | 33,357.54 |
Aug 17, 2021 | IDA-42800 | Loan Repay | 96,688.52 |
Aug 17, 2021 | IDA-42800 | Int Charges | 256.14 |
Aug 16, 2017 | IDA-42800 | Int Charges | 33,704.97 |
Feb 16, 2018 | IDA-42800 | Int Charges | 2,200.30 |
Feb 16, 2018 | IDA-42800 | Int Charges | 2,200.30 |
Feb 16, 2018 | IDA-42800 | Loan Repay | 99,265.04 |
Feb 16, 2018 | IDA-42800 | Int Charges | 2.07 |
Feb 16, 2018 | IDA-42800 | Int Charges | 2.07 |
Feb 16, 2018 | IDA-42800 | Int Charges | 32,520.02 |
Feb 16, 2018 | IDA-42800 | Int Charges | 32,520.02 |
Aug 17, 2018 | IDA-42800 | Int Charges | 1.97 |
Aug 17, 2018 | IDA-42800 | Int Charges | 1.97 |
Aug 17, 2018 | IDA-42800 | Int Charges | 34,686.37 |
Aug 17, 2018 | IDA-42800 | Int Charges | 34,686.37 |
Aug 17, 2018 | IDA-42800 | Int Charges | 4,119.14 |
Aug 17, 2018 | IDA-42800 | Int Charges | 4,119.14 |
Aug 17, 2018 | IDA-42800 | Loan Repay | 94,384.68 |
Feb 15, 2019 | IDA-42800 | Loan Repay | 2,210.90 |
Feb 15, 2019 | IDA-42800 | Int Charges | 33,593.87 |
Feb 15, 2019 | IDA-42800 | Int Charges | 33,593.87 |
Feb 15, 2019 | IDA-42800 | Loan Repay | 92,075.86 |
Feb 15, 2019 | IDA-42800 | Int Charges | 3.92 |
Feb 15, 2019 | IDA-42800 | Int Charges | 3.92 |
Feb 15, 2017 | IDA-42800 | Int Charges | 271.59 |
Feb 15, 2017 | IDA-42800 | Int Charges | 271.59 |
Aug 16, 2017 | IDA-42800 | Int Charges | 268.82 |
Aug 16, 2017 | IDA-42800 | Int Charges | 268.82 |
Aug 16, 2017 | IDA-42800 | Loan Repay | 95,526.40 |
Aug 16, 2017 | IDA-42800 | Int Charges | 33,704.97 |
Feb 15, 2015 | IDA-42800 | Int Charges | 268.05 |
Feb 15, 2015 | IDA-42800 | Int Charges | 268.05 |
Aug 15, 2015 | IDA-42800 | Int Charges | 1,170.19 |
Aug 15, 2015 | IDA-42800 | Int Charges | 1,170.19 |
Aug 15, 2015 | IDA-42800 | Int Charges | 34,622.63 |
Aug 15, 2015 | IDA-42800 | Int Charges | 34,622.63 |
Feb 15, 2016 | IDA-42800 | Int Charges | 19.40 |
Feb 15, 2016 | IDA-42800 | Int Charges | 19.40 |
Aug 15, 2013 | IDA-42800 | Int Charges | 267.76 |
Aug 15, 2013 | IDA-42800 | Int Charges | 267.76 |
Aug 16, 2013 | IDA-42800 | Int Charges | 38,542.56 |
Aug 16, 2013 | IDA-42800 | Int Charges | 38,542.56 |
Feb 15, 2014 | IDA-42800 | Int Charges | 62.40 |
Feb 15, 2014 | IDA-42800 | Int Charges | 62.40 |
Feb 15, 2014 | IDA-42800 | Int Charges | 39,153.29 |
Feb 15, 2014 | IDA-42800 | Int Charges | 39,153.29 |
Feb 15, 2015 | IDA-42800 | Int Charges | 35,827.20 |
Feb 15, 2015 | IDA-42800 | Int Charges | 35,827.20 |
Aug 15, 2014 | IDA-42800 | Int Charges | 157.57 |
Aug 15, 2014 | IDA-42800 | Int Charges | 157.57 |
Aug 15, 2014 | IDA-42800 | Int Charges | 38,990.78 |
Aug 15, 2014 | IDA-42800 | Int Charges | 38,990.78 |
Aug 15, 2023 | IDA-42800 | Int Charges | 29,897.93 |
Aug 15, 2024 | IDA-42800 | Loan Repay | 89,402.13 |
Aug 15, 2024 | IDA-42800 | Int Charges | 27,470.80 |
Aug 15, 2024 | IDA-42800 | Int Charges | 27,470.80 |
Aug 15, 2024 | IDA-42800 | Loan Repay | 1,620.63 |
Feb 15, 2024 | IDA-42800 | Loan Repay | 207.22 |
Aug 15, 2019 | IDA-42800 | Int Charges | 696.76 |
Aug 15, 2019 | IDA-42800 | Int Charges | 696.76 |
Feb 18, 2016 | IDA-42800 | Int Charges | 35,523.26 |
Feb 18, 2016 | IDA-42800 | Int Charges | 35,523.26 |
Aug 15, 2016 | IDA-42800 | Int Charges | 35,587.04 |
Aug 15, 2016 | IDA-42800 | Int Charges | 35,587.04 |
Aug 15, 2016 | IDA-42800 | Int Charges | 35.60 |
Aug 15, 2016 | IDA-42800 | Int Charges | 35.60 |
Feb 15, 2017 | IDA-42800 | Int Charges | 33,892.80 |
Feb 15, 2017 | IDA-42800 | Int Charges | 33,892.80 |
Name | Review | Date |
---|---|---|
Program Management | Satisfactory | 2007-08-13 |
Progress towards achievement of PDO | Satisfactory | 2007-08-13 |
Monitoring and Evaluation | Satisfactory | 2007-08-13 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-22-2008 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 10-08-2008 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |