Development Objective

The objective of this project is to increase access to safe water and sanitation facilities in all states throughout Southern Sudan and to build capacity for sustainable management, regulation and expansion of the rural water and sanitation sector.

Key Details

Project Details

  • P100835

  • Closed

  • Tesfaye Wondem

  • N/A

  • South Sudan

  • October 27, 2006

  • (as of board presentation)

    October 27, 2006

  • February 20, 2007

  • US$ 19.00 million

  • B

  • Not Applicable

  • June 30, 2011

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Multi-donor Trust Fund for South Sudan 19.00
Borrower/Recipient 11.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 19.00
Total Project Cost** 30.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2011-05-01
Monitoring and Evaluation Moderately Satisfactory 2011-05-01
Counterpart Funding Satisfactory 2011-05-01
Progress towards achievement of PDO Satisfactory 2011-05-01
Project Management Satisfactory 2011-05-01
Financial Management Satisfactory 2011-05-01
Overall Implementation Progress (IP) Satisfactory 2011-05-01
Overall Safeguards Rating Satisfactory 2011-05-01

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-21-2011
Outcomes
Risk to Development OutcomeSubstantial
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-26-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Additional households with improved sanitation facilities Value01011 FUTURE CORE SANITATION (# of people)1,000
    DateJune 30, 2006April 3, 2011March 31, 2011
    CommentA total of 1011 Household latrines, more than the targeted value were constructed.
  • Number of people in rural areas provided with access to Improved Water Sources under the projectValue0.00608000.00700000.00
    DateJune 30, 2006April 3, 2011March 31, 2011
    CommentA total of 608,000 people in rural south Sudan get access to safe water due to the construction of 616 new Boreholes andrehabilitation of 528 Boreholes. This is about 86.85% of the target population. When the remaining works are completed it is likelythat the target population would be reached.
  • Number of other water service providers that the project is supportingValue0.00528.00925.00
    DateJune 30, 2006April 3, 2011March 31, 2011
    CommentWater committees trained and organized on management and maintenance for new schemes and few rehabilitated schemes. Forrehabilitated schemes the existing committee members were trained.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved community water points constructed or rehabilitated under the projectValue0.001144.001325.00
    DateJune 30, 2006April 3, 2011March 31, 2011
    CommentWork is on progress to complete the drilling of the remaining Boreholes.
  • Piped water systems (small) constructedValue0.0012.0020.00
    DateJune 30, 2006April 3, 2011March 31, 2011
    CommentThe remaining 8 water systems are under construction
  • Latrines (public) constructedValue0.0058.0075.00
    DateJune 30, 2006November 6, 2010March 31, 2011
    Comment
  • Water Committee members trained to maintain water systems (incl. provision of tools)Value0.005720.009275.00
    DateJune 30, 2006April 3, 2011March 31, 2011
    CommentA total of 5,720 committee members for 1144 water points (New and rehabilitated ones) were trained
  • Number of improved latrines constructed under the projectValue0.00103.0075.00
    DateApril 3, 2011March 31, 2011
    Comment
  • Number of people trained to improve hygiene behavior or sanitation practices under the projectValue0.00121334.00331250.00
    DateApril 3, 2011March 31, 2011
    CommentFUTURE SANITATION CORE PLEASE provide data
  • rehabilitatedValue0.00528.00400.00
    DateJune 30, 2006April 3, 2011March 31, 2011
    CommentSame applies as above
  • newly constructedValue0.00616.00925.00
    DateJune 30, 2006April 3, 2011March 31, 2011
    Comment
  • Schools and health centersValue0.0056.0050.00
    DateJune 30, 2006November 6, 2010March 31, 2011
    CommentRevised plan 75
  • Markets, bus stops, other public placesValue0.006.0025.00
    DateJune 30, 2006April 3, 2011March 31, 2011
    Comment