Financier | Commitments |
---|---|
Carbon Fund | 37.54 |
International Bank for Reconstruction and Development | 395.00 |
Borrower/Recipient | 244.46 |
P101274
Closed
Rohit Mittal
N/A
October 6, 2011
(as of board presentation)
October 6, 2011
October 6, 2011
US$ 677.00 million
N/A
2012
US$ 432.54 million
N/A
December 19, 2024
February 27, 2017
BANK APPROVED
Financier | Commitments |
---|---|
Carbon Fund | 37.54 |
International Bank for Reconstruction and Development | 395.00 |
Borrower/Recipient | 244.46 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 395.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 395.00 |
Lending Instrument | |
---|---|
Grant Amount | 37.54 |
Total Project Cost** | 677.00 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2015-01-08 |
Progress towards achievement of PDO | Satisfactory | 2015-01-08 |
Financial Management | Satisfactory | 2015-01-08 |
Monitoring and Evaluation | Satisfactory | 2015-01-08 |
Counterpart Funding | Highly Satisfactory | 2015-01-08 |
Procurement | Satisfactory | 2015-01-08 |
Project Management | Satisfactory | 2015-01-08 |
Overall | Moderable | 2015-01-08 |