Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 1437.00 |
P101324
Closed
Roland N. Clarke
Goverment of minas Gerais
December 11, 2007
(as of board presentation)
May 1, 2008
September 23, 2008
US$ 1437.00 million
State Secretariat of Planning and Management (Secretaria de Estado do Planejamento e Gestão -SEPLAG)
2008
US$ 1437.00 million
B
Not Applicable
October 31, 2014
BANK APPROVED
July 18, 2014
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 1437.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 1437.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 1437.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 1437.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 15, 2013 | IBRD-75470 | Int Charges | 2,421,100.20 |
Dec 12, 2013 | IBRD-75470 | Loan Disb | 127,031.05 |
Sep 15, 2016 | IBRD-78710 | Int Charges | 4,603,795.00 |
Sep 15, 2016 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Oct 15, 2016 | IBRD-75470 | Int Charges | 4,306,729.50 |
Oct 15, 2016 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Apr 30, 2015 | IBRD-75470 | Loan Cancel | 1,119,873.00 |
Apr 30, 2015 | IBRD-75470 | Loan Disb | -433,803.10 |
Apr 15, 2015 | IBRD-75470 | Int Charges | 415.40 |
Apr 15, 2015 | IBRD-75470 | Int Charges | 1,785,547.00 |
Apr 15, 2015 | IBRD-75470 | Loan Repay | 20,774,530.00 |
Oct 15, 2015 | IBRD-75470 | Int Charges | 2,182,557.20 |
Oct 15, 2015 | IBRD-75470 | Loan Repay | 18,582,322.00 |
Oct 15, 2015 | IBRD-75470 | Loan Repay | 2,182,557.20 |
Sep 15, 2015 | IBRD-78710 | Int Charges | 3,405,868.80 |
Apr 15, 2014 | IBRD-75470 | Int Charges | 630.10 |
Apr 15, 2014 | IBRD-75470 | Int Charges | 2,019,377.50 |
Mar 15, 2014 | IBRD-78710 | Int Charges | 3,304,126.80 |
Aug 18, 2014 | IBRD-75470 | Loan Disb | 152,808.98 |
Aug 15, 2014 | IBRD-75470 | Loan Disb | 476,698.16 |
Mar 18, 2015 | IBRD-78710 | Int Charges | 3,188,597.80 |
Jul 23, 2014 | IBRD-75470 | Loan Disb | 315,980.16 |
Sep 15, 2014 | IBRD-78710 | Int Charges | 3,241,447.50 |
Sep 2, 2014 | IBRD-75470 | Loan Disb | 57,550.93 |
Nov 12, 2014 | IBRD-75470 | Int Charges | 51.00 |
Oct 15, 2014 | IBRD-75470 | Int Charges | 1,832,789.20 |
Oct 15, 2014 | IBRD-75470 | Loan Repay | 20,759,552.00 |
Jul 31, 2013 | IBRD-78710 | Loan Cancel | 1,437,500.00 |
Jul 22, 2013 | IBRD-75470 | Loan Disb | 551,616.90 |
Sep 15, 2013 | IBRD-78710 | Int Charges | 3,499,823.80 |
Sep 10, 2013 | IBRD-75470 | Loan Disb | 1,215,607.40 |
Oct 18, 2013 | IBRD-75470 | Loan Disb | 512,318.84 |
Apr 1, 2019 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Apr 1, 2019 | IBRD-78710 | Int Charges | 7,473,443.50 |
Mar 18, 2019 | IBRD-78710 | Loan Repay | 52.00 |
Mar 18, 2019 | IBRD-78710 | Int Charges | 52.00 |
Sep 15, 2019 | IBRD-78710 | Int Charges | 104.00 |
Sep 15, 2018 | IBRD-78710 | Loan Repay | 9,788,629.00 |
Sep 15, 2018 | IBRD-78710 | Int Charges | 7,198,315.50 |
Oct 15, 2018 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Oct 15, 2018 | IBRD-75470 | Int Charges | 10,401,286.00 |
Mar 15, 2017 | IBRD-78710 | Loan Repay | 4,587,547.00 |
Sep 15, 2017 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Mar 15, 2018 | IBRD-78710 | Int Charges | 5,428,960.00 |
Mar 15, 2018 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Sep 15, 2017 | IBRD-78710 | Int Charges | 5,577,056.00 |
Apr 15, 2018 | IBRD-75470 | Int Charges | 43,222.90 |
Apr 15, 2018 | IBRD-75470 | Int Charges | 6,626,034.50 |
Apr 15, 2018 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Mar 15, 2017 | IBRD-78710 | Loan Repay | 5,201,134.50 |
Apr 15, 2017 | IBRD-75470 | Loan Repay | 5,768,780.00 |
Apr 15, 2017 | IBRD-75470 | Int Charges | 5,768,780.00 |
Apr 15, 2017 | IBRD-75470 | Loan Repay | 14,996,099.00 |
Oct 15, 2017 | IBRD-75470 | Int Charges | 6,267,320.50 |
Oct 15, 2017 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Mar 15, 2017 | IBRD-78710 | Int Charges | 5,201,134.50 |
Mar 15, 2016 | IBRD-78710 | Int Charges | 3,694,116.50 |
Apr 15, 2016 | IBRD-75470 | Int Charges | 2,644,204.00 |
Apr 15, 2016 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Mar 30, 2022 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Mar 29, 2021 | IBRD-78710 | Int Charges | 3,254.74 |
Mar 29, 2021 | IBRD-78710 | Int Charges | 2,483,961.50 |
Mar 29, 2021 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Apr 28, 2021 | IBRD-75470 | Int Charges | 1,903.45 |
Apr 28, 2021 | IBRD-75470 | Int Charges | 1,069,147.40 |
Apr 28, 2021 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Oct 26, 2021 | IBRD-75470 | Int Charges | 2,024.58 |
Oct 26, 2021 | IBRD-75470 | Int Charges | 939,019.90 |
Oct 26, 2021 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Oct 26, 2020 | IBRD-75470 | Int Charges | 6,644.76 |
Oct 26, 2020 | IBRD-75470 | Int Charges | 4,721,870.00 |
Oct 26, 2020 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Sep 24, 2020 | IBRD-78710 | Int Charges | 3,488,041.80 |
Sep 24, 2020 | IBRD-78710 | Int Charges | 7,300.72 |
Sep 24, 2020 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Sep 30, 2019 | IBRD-78710 | Int Charges | 7,641,609.00 |
Oct 28, 2019 | IBRD-75470 | Int Charges | 21,641.62 |
Oct 28, 2019 | IBRD-75470 | Int Charges | 10,452,189.00 |
Oct 28, 2019 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Sep 30, 2019 | IBRD-78710 | Int Charges | 17,137.69 |
Sep 30, 2019 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Mar 30, 2020 | IBRD-78710 | Int Charges | 12,643.71 |
Mar 30, 2020 | IBRD-78710 | Int Charges | 6,128,493.00 |
Mar 30, 2020 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Apr 24, 2020 | IBRD-75470 | Int Charges | 15,221.81 |
Apr 24, 2020 | IBRD-75470 | Int Charges | 7,702,867.00 |
Apr 24, 2020 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Apr 29, 2019 | IBRD-75470 | Int Charges | 10,716,252.00 |
Apr 29, 2019 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Apr 15, 2024 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Apr 15, 2024 | IBRD-75470 | Int Charges | 17,208,416.00 |
Mar 15, 2024 | IBRD-78710 | Int Charges | 10,813,185.00 |
Mar 15, 2024 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Apr 6, 2010 | IBRD-78710 | Loan Commitment | 461,000,000.00 |
May 1, 2008 | IBRD-75470 | Loan Commitment | 976,000,000.00 |
Mar 15, 2023 | IBRD-78710 | Int Charges | 8,170,109.50 |
Mar 15, 2023 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Sep 15, 2023 | IBRD-78710 | Int Charges | 10,055,487.00 |
Sep 15, 2023 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Oct 15, 2023 | IBRD-75470 | Int Charges | 16,378,189.00 |
Oct 15, 2023 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Oct 15, 2022 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Oct 15, 2022 | IBRD-75470 | Int Charges | 11,074.60 |
Oct 15, 2022 | IBRD-75470 | Int Charges | 5,226,787.00 |
Sep 15, 2022 | IBRD-78710 | Int Charges | 8,891.39 |
Sep 15, 2022 | IBRD-78710 | Int Charges | 3,811,735.50 |
Sep 15, 2022 | IBRD-78710 | Loan Repay | 3,820,627.00 |
Sep 15, 2022 | IBRD-78710 | Loan Repay | 5,968,054.50 |
Apr 15, 2023 | IBRD-75470 | Int Charges | 14,430,560.00 |
Apr 15, 2023 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Sep 27, 2021 | IBRD-78710 | Int Charges | 4,720.32 |
Sep 27, 2021 | IBRD-78710 | Int Charges | 2,292,220.00 |
Sep 27, 2021 | IBRD-78710 | Loan Repay | 9,788,681.00 |
Apr 27, 2022 | IBRD-75470 | Int Charges | 1,332.41 |
Apr 27, 2022 | IBRD-75470 | Int Charges | 704,312.44 |
Apr 27, 2022 | IBRD-75470 | Loan Repay | 20,764,880.00 |
Mar 30, 2022 | IBRD-78710 | Int Charges | 3,915.47 |
Mar 30, 2022 | IBRD-78710 | Int Charges | 2,123,051.50 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2014-06-27 |
Monitoring and Evaluation | Satisfactory | 2014-06-27 |
Overall Implementation Progress (IP) | Satisfactory | 2014-06-27 |
Procurement | Satisfactory | 2014-06-27 |
Financial Management | Satisfactory | 2014-06-27 |
Progress towards achievement of PDO | Highly Satisfactory | 2014-06-27 |
Project Management | Highly Satisfactory | 2014-06-27 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 04-28-2015 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 02-16-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of personnel expenditure as a share of net current revenues of the MG government. | Value | 59.43% | 65.1% | Consistent with PAF (60 percent or under) |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | This DLI was not achieved. |
Existence of cost data in hospitals with time series that indicate trends in costs at organizational level (hospital level) and at the departmental level | Value | No cost system in place. | Cost system developed and piloted in two hospitals | |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Target achieved and no longer monitored. |
Cost per Student Informational System (SICA) implemented and cost data posted on the web | Value | System exists with information updated once a year | System is being updated due to a change in the for | Regular reports and analysis produced on evolution |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Achieved in previous year and not longer monitored. |
Investment expenditure as a share of net current revenue | Value | 12.99% | 10.44% | 9.47% |
Date | December 31, 2007 | May 7, 2012 | December 31, 2010 | |
Comment | target for 2011 was 9.47% |
Expenditure on strategic projects as a share of total expenditure | Value | 8.35% (Despesa Empenhada) 6.97% (Despesa Liquidada | 16.62% | 9.5% |
Date | December 31, 2007 | October 1, 2014 | December 31, 2010 | |
Comment | Last established target was 9.5% for 2010. |
Successful implementation of results agreements (RAs considered for this indicator: SEF, SEPLAG, SEMAD, SECTES, SEE and SES) | Value | 4 RAs with results over 70 percent satisfactory. | All 28 secretariats with results over 70 percent s | 7 RAs with results over 70 percent. |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Indicator data not yet available for 2013 |
percent of state paved roads network under results-based maintenance and rehabilitation contracts | Value | 11% | 32.88% | 42% |
Date | December 31, 2007 | October 1, 2014 | December 31, 2010 | |
Comment | Target not achieved. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of certified job categories and/or re-certification processes | Value | 2 | - | |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Target met and no longer monitored. |
Primary surplus | Value | R$ 1,704 million | R$ 683 million in 2013 | Targets described in PAF for the 2010 fiscal year |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Target met in 2009 but continued to be monitored. |
System of management of civil construction contracts developed and implemented, integrated with SIAD and SIAFI. | Value | No system of electronic invoicing, management of c | System of management of civil construction contrac | |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Target achieved, indicator no longer monitored. |
Support systems of monitoring and evaluation | Value | Incipient monitoring and evaluation systems. | Report discussing the use of the evidence provided | |
Date | September 30, 2008 | October 1, 2014 | December 31, 2011 | |
Comment | Target met and no longer monitored. |
Time (in days) to start a business at Minas Facil in Belo Horizonte (one-stop shop) | Value | 26 days | 6 | 9 days |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Target met, but indicator is continued to be tracked. |
Number of Technological Innovation Centers | Value | 4 | 18 | 15 |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Target was met, but indicator is continued to be measured. |
Percentage of hospitals of PROHOSP program formally assessed for accreditation by the National Accreditation Organization | Value | 0% (123 hospitals in 2007) | 75.71% (140 hospitals in 2013) | 75% |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Target met. |
Percentage of students registered in state schools with expected reading level in the 3rd year of elementary school | Value | 65% | 92.30% | 78-80% |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment |
Implement system of measurement and feedback - standardized student assessments for Portuguese and Mathematics | Value | PROALFA and PROEB conducted at classes of 3rd, 5th | ||
Date | October 1, 2014 | December 31, 2010 | ||
Comment | Dropped with AF. |
% of municipalities in the state with paved access | Value | 83% | 98.24% | 96% |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Target achieved but continued to be monitored. |
Development of new highway PPPs | Value | 6 | Expression of Interest Notices published for 5 add | |
Date | October 1, 2014 | December 31, 2010 | ||
Comment | Target already achieved. This indicator continues to measure other PPPs. |
Average time for the concession of environmental licenses for activities with environmental impact in the state for classes 3 and 4 | Value | 180 days | 92.63 days | 90 days |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Target achieved in 2010 but continued to be monitored. |
Number of certified teachers in the Curso de Magisterio Indigena | Value | 137 | 110 | 212 |
Date | December 31, 2007 | October 1, 2014 | December 31, 2009 | |
Comment | Target already achieved and indicator no longer monitored. |
(i) Total Number of Test Items (cumulative) / (ii) Participation rate total number of schools that apply the test for the 9th gradeclassrooms in five subjects) (cumulative) | Value | (i) 24,633 (2008) / (ii) 500 State secondary schoo | (i) 97,911 / (ii) 8,236 | (i) 35,000 / (ii) 1000 State secondary schools |
Date | December 31, 2008 | October 1, 2014 | December 31, 2011 | |
Comment | Target already achieved in 2010, but indicator is continued to be measured. |
Number of eletronic speed control equipments in operation | Value | 16 (2009) | 240 | 90 |
Date | December 31, 2009 | October 1, 2014 | December 31, 2011 | |
Comment | Target already met but continued to be monitored. |
Number of families benefited by the Rural Poverty Reduction Program starting in 2010 | Value | 0.00 | 2400.00 | 16800.00 |
Date | December 31, 2009 | October 1, 2014 | December 31, 2011 | |
Comment | Numbers from the previous ISR contain a typo. The correct information for the previous ISR is 3100.00 families benefited by theProgram. |
Improve poverty monitoring: completion of PAD-MG in 2009. | Value | Analytical report on poverty in the "Great North" | ||
Date | October 1, 2014 | December 31, 2011 | ||
Comment | Target achieved and no longer monitored. |
Implementation of 2nd stage Results Agreements | Value | 10 of these 12 agreements evaluated by March 31, 2 | All agreements evaluated in time. | At least 11 of these agreemnts evaluated fro compl |
Date | March 31, 2009 | October 1, 2014 | April 30, 2011 | |
Comment | This indicator was added to the ISR in March 2013. Before it had been tracked but not reported through the ISR. |
Gross operating Balance | Value | 11.00 | 7.91 | 14.00 |
Date | December 31, 2009 | October 1, 2014 | December 31, 2011 | |
Comment | This indicator was added to the ISR in March 2013. Before it had been tracked but not reported through the ISR. | The target for 2010 was 13% and the actual 14.95%; the Operation balance for 2011 was 13.12; |
Output-Outcome Reports | Value | Strategic projoects under implementation and ongoi | A report outlining the Government's priorities, st | |
Date | December 31, 2009 | October 1, 2014 | December 31, 2011 | |
Comment | Target achieved in 2011. |
Minas Facil physical units | Value | 21.00 | 111.00 | 29.00 |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | This indicator was added to the ISR only in March 2013, but has been tracked before. |
Impact evaluation for the Vida Vida Centers | Value | No impact evaluation system | This target was excluded from the project in 2011. | Methodology for using DATASUS panel data with moni |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment |
Registration in the Vocational Education Program (PEP) | Value | 0.00 | 42626.00 | 25000.00 |
Date | December 31, 2007 | December 31, 2009 | December 31, 2009 | |
Comment | This indicator was added to the ISR in early 2013, but has been monitored before. | This indicator was achieved in 2009. |
Number of new students enrolled in PEP courses in secondary vocational schools (non-cumulative) | Value | 0.00 | 30073.00 | 30000.00 |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | The target was achieved in 2010; in 2013, 30.073 new students were enrolled. |
Intensive Monitoring of the Rural Poverty Reduxction Project | Value | 0 | 3 | 6 |
Date | December 31, 2009 | October 1, 2014 | December 31, 2011 | |
Comment | Target achieved in 2010. 12 monitoring meetings held in 2012. |
Average percantage delay of Pro-Acesso paving works concluded in the current year | Value | 37.90 | 0.00 | 20.00 |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | Measured in weighted average | This target was not met, but due to a difference in the measurement of the indicator, it has not been tracked since 2010. |
Secondary schools in the Great North offering computer maintenance courses | Value | 59.00 | 0.00 | 0.00 |
Date | December 31, 2009 | October 1, 2014 | ||
Comment | Target achieved in 2010. In subsequent years, the course was no longer offered, as per resolution published in 2011 extinguishingthe FIT (Formação Inicial para o Trabalho) project. |
Proportion of live births from mothers with 7 or more pre-natal consultations | Value | 46.10 | 66.60 | 48.00 |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment | This is 2013 data. Data for 2012: 65.10; 2010: 57.8%, 2009: 51.2%; 2008: 49.8% |
Interdisciplinary teams of indigenous health | Value | 12.00 | 19.00 | 16.00 |
Date | December 31, 2007 | October 1, 2014 | December 31, 2011 | |
Comment |