Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 66.70 |
P101369
Closed
Ciro Avitabile
N/A
October 1, 2009
(as of board presentation)
March 25, 2010
August 26, 2011
US$ 166.70 million
N/A
2010
US$ 100.00 million
C
Not Applicable
June 30, 2014
BANK APPROVED
September 28, 2021
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 66.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 166.70 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2023 | IBRD-78590 | Int Charges | 1,030,981.44 |
Jun 15, 2022 | IBRD-78590 | Int Charges | 419,611.10 |
Dec 15, 2022 | IBRD-78590 | Int Charges | 0.01 |
Dec 15, 2022 | IBRD-78590 | Int Charges | 1,753,229.80 |
Dec 15, 2021 | IBRD-78590 | Int Charges | 345,666.66 |
Jun 15, 2021 | IBRD-78590 | Int Charges | 0.01 |
Jun 15, 2021 | IBRD-78590 | Int Charges | 379,166.66 |
Jun 15, 2020 | IBRD-78590 | Int Charges | 1,209,833.40 |
Dec 15, 2020 | IBRD-78590 | Int Charges | 462,583.30 |
Dec 15, 2019 | IBRD-78590 | Int Charges | 1,433,500.00 |
Jun 15, 2019 | IBRD-78590 | Int Charges | 61,169.39 |
Jun 15, 2019 | IBRD-78590 | Int Charges | 1,652,664.00 |
Dec 15, 2018 | IBRD-78590 | Int Charges | 1,509,750.00 |
Dec 15, 2017 | IBRD-78590 | Int Charges | 950,583.30 |
Jun 15, 2018 | IBRD-78590 | Int Charges | 1,122,333.40 |
Dec 15, 2016 | IBRD-78590 | Int Charges | 665,916.70 |
Jun 15, 2017 | IBRD-78590 | Int Charges | 864,500.00 |
Jun 15, 2016 | IBRD-78590 | Int Charges | 559,166.70 |
Jun 15, 2015 | IBRD-78590 | Int Charges | 323,555.56 |
Dec 15, 2015 | IBRD-78590 | Int Charges | 391,416.66 |
Apr 7, 2014 | IBRD-78590 | Loan Disb | 1,230,314.10 |
Dec 15, 2014 | IBRD-78590 | Int Charges | 299,212.94 |
Jun 15, 2014 | IBRD-78590 | Int Charges | 25.52 |
Jun 15, 2014 | IBRD-78590 | Int Charges | 293,991.62 |
Jun 26, 2014 | IBRD-78590 | Loan Disb | 3,903,638.00 |
Oct 10, 2013 | IBRD-78590 | Loan Disb | 11,562,134.00 |
Jan 30, 2014 | IBRD-78590 | Loan Disb | 4,060.38 |
Dec 15, 2013 | IBRD-78590 | Int Charges | 7,231.18 |
Dec 15, 2013 | IBRD-78590 | Int Charges | 294,998.28 |
Dec 13, 2013 | IBRD-78590 | Loan Disb | 642,452.56 |
Jun 15, 2024 | IBRD-78590 | Int Charges | 1,124,384.80 |
Jun 15, 2024 | IBRD-78590 | Int Charges | 2,075,093.00 |
Dec 13, 2013 | IBRD-78590 | Loan Disb | 43,386.12 |
Jun 15, 2024 | IBRD-78590 | Int Charges | 19,883.36 |
Mar 25, 2010 | IBRD-78590 | Loan Commitment | 100,000,000.00 |
Jun 15, 2023 | IBRD-78590 | Int Charges | 127,941.24 |
Jun 15, 2023 | IBRD-78590 | Int Charges | 1,833,053.60 |
Jun 15, 2023 | IBRD-78590 | Int Charges | 781,184.00 |
Dec 15, 2023 | IBRD-78590 | Int Charges | 1,980,408.20 |
Dec 15, 2023 | IBRD-78590 | Int Charges | 53,180.10 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2014-07-12 |
Counterpart Funding | Satisfactory | 2014-07-12 |
Overall Implementation Progress (IP) | Satisfactory | 2014-07-12 |
Procurement | Moderately Satisfactory | 2014-07-12 |
Monitoring and Evaluation | Moderately Satisfactory | 2014-07-12 |
Project Management | Satisfactory | 2014-07-12 |
Financial Management | Satisfactory | 2014-07-12 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-29-2015 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-01-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of children 0 to 4 years who attend at least 80 percent of the sessions of the Early Childhood Development intervention in the 172 target municipalities | Value | 43241.00 | 57983.00 | 58685.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Gap in test scores between the 172 target municipalities and the national level | Value | 5.80 | 1223.00 | 9.40 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of ECD service points that are established and complete the minimum number of sessions provided for by the model, in the target municipalities | Value | 2885.00 | 3498.00 | 3821.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Number of fathers and mothers trained, i.e. who attended at least 80 percent of the total number of sessions of the ECD model, in the target municipalities | Value | 38620.00 | 48640.00 | 52670.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Number of pregnant women trained, i.e. who attended at least 80 percent of the total number of sessions of the ECD model specific to pregnant women | Value | 0.00 | 1317.00 | 1761.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Number of fathers trained, i.e. who attended at least 80 % of the sessions of the ECD model specific to fathers, in the target municipalities | Value | 0.00 | 1714.00 | 11737.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Application of an instrument that measures the competencies of parents and children age 0-4 years old | Value | No | Yes | Yes |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Longitudinal Study | Value | Does not apply | Basic measurement | |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Number of Parent Associations (Asociaciones de Padres de Familia or APF) trained yearly in the AGE intervention, nationally | Value | 67714.00 | 47408.00 | 46462.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Number of FORTALECE entities with a Work Program developed and approved by FORTALECE, in the target municipalities | Value | 0.00 | 1373.00 | 1338.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Total amount of financial support transferred to and received by the FORTALECE entities | Value | 0.00 | 1234153.00 | 1213056.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Grade failure rate in community schools in the target municipalities, primary and secondary education level | Value | 26.20 | 2.00 | 17.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Number of school establishments supported by Mobile tutors (Asesores Pedagógicos Itinerantes or APIs) | Value | 0.00 | 1942.00 | 2000.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Grade failure rate in non-community schools, primary and secondary education level, in 172 target municipalities | Value | 9.30 | 1.90 | 5.90 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Student scores in the ENLACE test in non-community schools, primary and secondary education level, in 172 target municipalities | Value | 432.00 | 510.99 | 452.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Number of municipalities that have a strategic plan for the education sector, approved and validated by CONAFE | Value | 0.00 | 4.00 | 5.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Percent of strategic plan executed against municipal budget in municipalities with plan | Value | 0.00 | 0.00 | 0.00 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Learning results on ENLACE test in 5 pilot municipalities | Value | 469.15 | 519.95 | 489.15 |
Date | September 1, 2009 | January 31, 2014 | June 30, 2014 | |
Comment |
Implementation of a management and monitoring module for the ECD, AGEs, FORTALECE and API programs | Value | Yes | ||
Date | January 31, 2014 | June 30, 2014 | ||
Comment |
Number and percentage of families in the 172 municipalities, that have beneficiaries from both Oportunidades and Educación Inicial | Value | 0.00 | 0.00 | 0.00 |
Date | January 31, 2014 | June 30, 2014 | ||
Comment |
Number and percentage of AGEs schools in the 172 municipalities, that have at least 75 percent of students participating in Oportunidades | Value | 0.00 | 0.00 | 0.00 |
Date | January 31, 2014 | June 30, 2014 | ||
Comment |