Skip to Main Navigation

Compensatory Education

Abstract*

The development objective of the Compensatory Education Project is to improve access to Early Childhood Education (ECD) services and learning outcomes of children in the most marginalized municipalities of Mexico. There are three components to the project. The first component of the project is early childhood development intervention. This component will finance training of parents, relatives, and caregivers of children aged 0-4 to improve their competencies...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objective of the Compensatory Education Project is to improve access to Early Childhood Education (ECD) services and learning outcomes of children in the most marginalized municipalities of Mexico. This objective would be achieved through innovative interventions at the early childhood and basic education levels that strengthen the involvement of members of the school community and municipalities.

Key Details

Project Details

  • P101369

  • Closed

  • Ciro Avitabile

  • N/A

  • Mexico

  • October 1, 2009

  • (as of board presentation)

    March 25, 2010

  • August 26, 2011

  • US$ 100.00 million

  • C

  • Not Applicable

  • June 30, 2014

  • BANK APPROVED

  • September 28, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 100.00
Borrower/Recipient 66.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 166.70

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 2023 IBRD-78590 Int Charges 1,030,981.44
Jun 15, 2022 IBRD-78590 Int Charges 419,611.10
Dec 15, 2022 IBRD-78590 Int Charges 0.01
Dec 15, 2022 IBRD-78590 Int Charges 1,753,229.80
Dec 15, 2021 IBRD-78590 Int Charges 345,666.66
Jun 15, 2021 IBRD-78590 Int Charges 0.01
Jun 15, 2021 IBRD-78590 Int Charges 379,166.66
Jun 15, 2020 IBRD-78590 Int Charges 1,209,833.40
Dec 15, 2020 IBRD-78590 Int Charges 462,583.30
Dec 15, 2019 IBRD-78590 Int Charges 1,433,500.00
Jun 15, 2019 IBRD-78590 Int Charges 61,169.39
Jun 15, 2019 IBRD-78590 Int Charges 1,652,664.00
Dec 15, 2018 IBRD-78590 Int Charges 1,509,750.00
Dec 15, 2017 IBRD-78590 Int Charges 950,583.30
Jun 15, 2018 IBRD-78590 Int Charges 1,122,333.40
Dec 15, 2016 IBRD-78590 Int Charges 665,916.70
Jun 15, 2017 IBRD-78590 Int Charges 864,500.00
Jun 15, 2016 IBRD-78590 Int Charges 559,166.70
Jun 15, 2015 IBRD-78590 Int Charges 323,555.56
Dec 15, 2015 IBRD-78590 Int Charges 391,416.66
Apr 7, 2014 IBRD-78590 Loan Disb 1,230,314.10
Dec 15, 2014 IBRD-78590 Int Charges 299,212.94
Jun 15, 2014 IBRD-78590 Int Charges 25.52
Jun 15, 2014 IBRD-78590 Int Charges 293,991.62
Jun 26, 2014 IBRD-78590 Loan Disb 3,903,638.00
Oct 10, 2013 IBRD-78590 Loan Disb 11,562,134.00
Jan 30, 2014 IBRD-78590 Loan Disb 4,060.38
Dec 15, 2013 IBRD-78590 Int Charges 7,231.18
Dec 15, 2013 IBRD-78590 Int Charges 294,998.28
Dec 13, 2013 IBRD-78590 Loan Disb 642,452.56
Jun 15, 2024 IBRD-78590 Int Charges 1,124,384.80
Jun 15, 2024 IBRD-78590 Int Charges 2,075,093.00
Dec 13, 2013 IBRD-78590 Loan Disb 43,386.12
Jun 15, 2024 IBRD-78590 Int Charges 19,883.36
Mar 25, 2010 IBRD-78590 Loan Commitment 100,000,000.00
Jun 15, 2023 IBRD-78590 Int Charges 127,941.24
Jun 15, 2023 IBRD-78590 Int Charges 1,833,053.60
Jun 15, 2023 IBRD-78590 Int Charges 781,184.00
Dec 15, 2023 IBRD-78590 Int Charges 1,980,408.20
Dec 15, 2023 IBRD-78590 Int Charges 53,180.10

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2014-07-12
Counterpart Funding Satisfactory 2014-07-12
Overall Implementation Progress (IP) Satisfactory 2014-07-12
Procurement Moderately Satisfactory 2014-07-12
Monitoring and Evaluation Moderately Satisfactory 2014-07-12
Project Management Satisfactory 2014-07-12
Financial Management Satisfactory 2014-07-12

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-29-2015
Outcomes
Risk to Development OutcomeSubstantial
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-01-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of children 0 to 4 years who attend at least 80 percent of the sessions of the Early Childhood Development intervention in the 172 target municipalitiesValue43241.0057983.0058685.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Gap in test scores between the 172 target municipalities and the national levelValue5.801223.009.40
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of ECD service points that are established and complete the minimum number of sessions provided for by the model, in the target municipalitiesValue2885.003498.003821.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Number of fathers and mothers trained, i.e. who attended at least 80 percent of the total number of sessions of the ECD model, in the target municipalitiesValue38620.0048640.0052670.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Number of pregnant women trained, i.e. who attended at least 80 percent of the total number of sessions of the ECD model specific to pregnant womenValue0.001317.001761.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Number of fathers trained, i.e. who attended at least 80 % of the sessions of the ECD model specific to fathers, in the target municipalitiesValue0.001714.0011737.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Application of an instrument that measures the competencies of parents and children age 0-4 years oldValueNoYesYes
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Longitudinal StudyValueDoes not applyBasic measurement
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Number of Parent Associations (Asociaciones de Padres de Familia or APF) trained yearly in the AGE intervention, nationallyValue67714.0047408.0046462.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Number of FORTALECE entities with a Work Program developed and approved by FORTALECE, in the target municipalitiesValue0.001373.001338.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Total amount of financial support transferred to and received by the FORTALECE entitiesValue0.001234153.001213056.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Grade failure rate in community schools in the target municipalities, primary and secondary education levelValue26.202.0017.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Number of school establishments supported by Mobile tutors (Asesores Pedagógicos Itinerantes or APIs)Value0.001942.002000.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Grade failure rate in non-community schools, primary and secondary education level, in 172 target municipalitiesValue9.301.905.90
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Student scores in the ENLACE test in non-community schools, primary and secondary education level, in 172 target municipalitiesValue432.00510.99452.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Number of municipalities that have a strategic plan for the education sector, approved and validated by CONAFEValue0.004.005.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Percent of strategic plan executed against municipal budget in municipalities with planValue0.000.000.00
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Learning results on ENLACE test in 5 pilot municipalitiesValue469.15519.95489.15
    DateSeptember 1, 2009January 31, 2014June 30, 2014
    Comment
  • Implementation of a management and monitoring module for the ECD, AGEs, FORTALECE and API programsValueYes
    DateJanuary 31, 2014June 30, 2014
    Comment
  • Number and percentage of families in the 172 municipalities, that have beneficiaries from both Oportunidades and Educación InicialValue0.000.000.00
    DateJanuary 31, 2014June 30, 2014
    Comment
  • Number and percentage of AGEs schools in the 172 municipalities, that have at least 75 percent of students participating in OportunidadesValue0.000.000.00
    DateJanuary 31, 2014June 30, 2014
    Comment