UA - ALCHEVSK STEEL MILL REVAMPING AND MODERNIZATION

Development Objective

(i) generate and sell greenhouse gas (GHG) emission reductions (ERs) and transfer ERs as Emission Reduction Units (ERUs) to buyers under Joint Implementation (JI) mechanism by modernization of the steel making capacity in OJSC “Alchevsk Iron and Steel Works” (AISW); (ii) support investment in technology modernization that improves process, energy efficiency and environmental performancethrough significant reductions in local air emissions, wastewater discharges and solid waste generation/disposal.

Key Details

Project Details

  • P101615

  • Closed

  • Alexei Slenzak

  • N/A

  • Ukraine

  • March 15, 2007

  • (as of board presentation)

    May 6, 2008

  • May 21, 2009

  • US$ 7.50 million

  • N/A

  • Not Applicable

  • June 30, 2013

  • BANK APPROVED

  • December 19, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Carbon Fund 7.50
Borrower/Recipient 936.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 7.50
Total Project Cost** 944.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2013-12-23
Progress towards achievement of PDO Satisfactory 2013-12-23
Monitoring and Evaluation Satisfactory 2013-12-23
Overall Implementation Progress (IP) Satisfactory 2013-12-23
Counterpart Funding Satisfactory 2013-12-23

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • generate and sell greenhouse gas (GHG) emission reductions (ERs) and transfer ERs as Emission Reduction Units (ERUs) to buyers under Joint Implementation (JI) mechanismValue0.001336254.001336254.00
    DateDecember 31, 2011December 31, 2012
    CommentThis data are considered as confidential and could not be publicly disclosed.This data are considered as confidential and could not be publicly disclosed.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • ERs transferred as early creditsValue0.00736254.00736254.00
    DateJanuary 1, 2005December 31, 2007December 31, 2008
    CommentThis data are considered as confidential and could not be publicly disclosed.
  • 2008 ERs transferredValue0.00643006.00600000.00
    DateJanuary 1, 2008December 31, 2008December 31, 2009
    Comment5590727 t of CO2 eqThis data are considered as confidential and could not be publicly disclosed.