Skip to Main Navigation

Lao PDR Customs and Trade Facilitation Project

Abstract*

The objective of the Customs and Trade Facilitation Project for Laos is to facilitate trade by improving the efficiency and effectiveness of customs administration. The project will simplify customs procedures, eliminate duplication and redundancy, and reduce transaction costs and time to clear goods, and increase transparency and accountability. There are two components to the project. The first component is the implementation of Automated Systems...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the project is to facilitate trade by improving the efficiency and effectiveness of customs administration and simplifying customs procedures to eliminate duplication and redundancy, reduce transactions costs and time to clear goods, and increasetransparencyand accountability.

Key Details

Project Details

  • P101750

  • Closed

  • Konesawang Nghardsaysone

  • Ministry of Finance

  • US$ 12.50 million

  • Customs Department, Ministry of Finance

  • East Asia and Pacific

  • 2008

  • US$ 12.50 million

  • C

  • February 27, 2020

  • June 30, 2017

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 12.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 12.50
IBRD + IDA Commitment 12.50
Lending Instrument
Grant Amount N/A
Total Project Cost** 12.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 18, 2014 IDA-H8430 Loan Disb 103,359.09
May 21, 2014 IDA-H4030 Loan Disb -5,836.25
Oct 29, 2014 IDA-H8430 Loan Disb 70,805.00
Jan 9, 2015 IDA-H8430 Loan Disb 125,365.92
Aug 2, 2013 IDA-H4030 Loan Disb 35,296.10
Jul 9, 2013 IDA-H4030 Loan Disb 486,490.00
Sep 12, 2013 IDA-H4030 Loan Disb 17,323.00
Aug 14, 2013 IDA-H8430 Loan Disb 150,000.02
Dec 26, 2013 IDA-H8430 Loan Disb 64,981.02
Oct 9, 2013 IDA-H4030 Loan Disb 12,168.10
May 28, 2013 IDA-H8430 Loan Commitment 6,500,000.00
Jun 17, 2008 IDA-H4030 Loan Commitment 6,000,000.00
Dec 21, 2017 IDA-H8430 Loan Disb 23,855.12
Dec 29, 2017 IDA-H8430 Loan Disb 21,443.55
May 8, 2018 IDA-H8430 Loan Disb -930.29
May 8, 2018 IDA-H8430 Loan Disb -3,135.96
May 8, 2018 IDA-H8430 Loan Cancel 309,075.38
Jun 30, 2017 IDA-H8430 Loan Disb 41,164.86
May 24, 2017 IDA-H8430 Loan Disb 95,958.33
May 24, 2017 IDA-H8430 Loan Disb 143,937.52
Mar 30, 2017 IDA-H8430 Loan Disb 95,958.34
Jun 27, 2017 IDA-H8430 Loan Disb 110,619.49
Mar 30, 2017 IDA-H8430 Loan Disb -95,958.34
Nov 6, 2017 IDA-H8430 Loan Disb 228,434.88
Aug 28, 2017 IDA-H8430 Loan Disb 95,958.33
Aug 28, 2017 IDA-H8430 Loan Disb 191,916.67
Aug 28, 2017 IDA-H8430 Loan Disb 143,937.52
Dec 15, 2017 IDA-H8430 Loan Disb -20,483.34
Sep 14, 2016 IDA-H8430 Loan Disb 118,198.68
Dec 6, 2016 IDA-H8430 Loan Disb 105,103.99
Aug 10, 2016 IDA-H8430 Loan Disb 128,671.68
Feb 1, 2017 IDA-H8430 Loan Disb 108,686.79
Sep 15, 2016 IDA-H8430 Loan Disb 41,352.39
Jun 8, 2016 IDA-H8430 Loan Disb 50,661.66
Oct 4, 2016 IDA-H8430 Loan Disb 129,669.92
Jun 28, 2017 IDA-H8430 Loan Disb 143,937.52
May 10, 2017 IDA-H8430 Loan Disb 66,513.49
Jun 28, 2017 IDA-H8430 Loan Disb 219,782.12
May 12, 2017 IDA-H8430 Loan Disb 107,390.02
Mar 30, 2017 IDA-H8430 Loan Disb 201,979.00
May 12, 2017 IDA-H8430 Loan Disb 41,346.37
Mar 30, 2017 IDA-H8430 Loan Disb 58,500.01
Mar 31, 2015 IDA-H8430 Loan Disb 115,319.00
May 20, 2015 IDA-H8430 Loan Disb 88,549.01
May 26, 2015 IDA-H8430 Loan Disb 103,925.61
Aug 3, 2015 IDA-H8430 Loan Disb 63,668.27
Jan 19, 2016 IDA-H8430 Loan Disb 33,759.00
Oct 16, 2015 IDA-H8430 Loan Disb 39,423.42
Sep 3, 2015 IDA-H8430 Loan Disb 82,453.64
Dec 17, 2015 IDA-H8430 Loan Disb 56,314.50
Oct 27, 2015 IDA-H8430 Loan Disb 84,318.99
Jan 29, 2016 IDA-H8430 Loan Disb 58,388.00
Jan 29, 2016 IDA-H8430 Loan Disb 86,033.88
Dec 23, 2015 IDA-H8430 Loan Disb 239,130.00
Feb 10, 2016 IDA-H8430 Loan Disb 78,000.00
Mar 30, 2016 IDA-H8430 Loan Disb 39,300.00
Mar 8, 2016 IDA-H8430 Loan Disb 34,711.00
Apr 25, 2016 IDA-H8430 Loan Disb 128,989.49
Apr 25, 2016 IDA-H8430 Loan Disb 142,204.78
Mar 4, 2016 IDA-H8430 Loan Disb 51,188.68
Mar 9, 2016 IDA-H8430 Loan Disb 101,720.78
Jul 26, 2016 IDA-H8430 Loan Disb 72,867.44
May 21, 2014 IDA-H4030 Loan Cancel 24,405.11
Feb 17, 2015 IDA-H8430 Loan Disb 77,316.69
Dec 18, 2014 IDA-H8430 Loan Disb 62,616.27
Aug 19, 2014 IDA-H8430 Loan Disb 131,012.05
Apr 1, 2015 IDA-H8430 Loan Disb 78,542.07
Mar 17, 2015 IDA-H8430 Loan Disb 237,287.44
May 4, 2015 IDA-H8430 Loan Disb 87,203.55
Jun 16, 2015 IDA-H8430 Loan Disb 101,880.92
May 4, 2015 IDA-H8430 Loan Disb 133,027.00
Aug 26, 2015 IDA-H8430 Loan Disb 98,915.01
Mar 18, 2014 IDA-H8430 Loan Disb 60,254.15
May 21, 2014 IDA-H4030 Loan Disb -18,568.87

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2017-06-26
Progress towards achievement of PDO Satisfactory 2017-06-26
Procurement Satisfactory 2017-06-26
Financial Management Moderately Satisfactory 2017-06-26
Monitoring and Evaluation Moderately Satisfactory 2017-06-26
Overall Implementation Progress (IP) Moderately Satisfactory 2017-06-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-28-2017
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-15-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Customs Efficiency: Reduction in mean import, export, and transit clearance times.Value17.97.46.5
    DateMarch 22, 2010June 30, 2017June 30, 2017
    Comment
  • Customs Effectiveness: Increase in the ratio of detections / inspections by customs.ValueNot initiated2.9NA
    DateApril 26, 2013June 30, 2017June 30, 2017
    Comment
  • Customs Efficiency: Reduction in number of steps to clear commercial shipments (import / export).Value9/74/34/3
    DateMarch 22, 2010June 30, 2017June 30, 2017
    Comment
  • Customs Effectiveness: Increase in the perceptions of customs performance and integrity by clients.Value2.08 (LPI 2007)2.82.07
    DateJune 30, 2007June 30, 2017June 30, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Integrated IT system is in place by 2011, pilot completed and reviewed by 2012, and fully operational in all implementation sites by 2014ValueNot initiated2324
    DateJune 30, 2009June 30, 2017June 30, 2017
    Comment
  • Prototype developed and accepted by governmentValueNot initiatedCompletedCompleted
    DateJune 30, 2009December 31, 2010December 31, 2011
    Comment
  • Accepted prototype validated at the pilot siteValueNot initiatedCompletedCompleted.
    DateJune 30, 2009December 30, 2011April 30, 2012
    Comment
  • Prototype replicated at the remaining checkpoint sitesValueNot initiated2324
    DateJune 30, 2009June 30, 2017June 30, 2017
    Comment
  • Full acceptance of electronic data submission for customs declaration procedures by the end of 2013ValueNot initiated2324
    DateJune 30, 2009June 30, 2017April 19, 2017
    Comment
  • Appropriate front line staff and affected traders trained in advance of pilot testing and pre nationwide rolloutValueNot initiated25003500
    DateJune 30, 2009June 30, 2017June 30, 2017
    Comment