Financier | Commitments |
---|---|
Indonesia - Multi-donor TF for Aceh and North Sumatra | 100.00 |
Borrower/Recipient | 191.00 |
P101785
Closed
Khairy Al-Jamal
N/A
December 11, 2006
(as of board presentation)
December 11, 2006
March 14, 2007
US$ 291.00 million
N/A
2007
US$ 100.00 million
A
January 15, 2013
December 31, 2012
BANK APPROVED
Financier | Commitments |
---|---|
Indonesia - Multi-donor TF for Aceh and North Sumatra | 100.00 |
Borrower/Recipient | 191.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 100.00 |
Total Project Cost** | 291.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2012-12-03 |
Monitoring and Evaluation | Moderately Satisfactory | 2012-12-03 |
Financial Management | Moderately Unsatisfactory | 2012-12-03 |
Counterpart Funding | Satisfactory | 2012-12-03 |
Project Management | Moderately Satisfactory | 2012-12-03 |
Procurement | Satisfactory | 2012-12-03 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2012-12-03 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-29-2013 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 04-30-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Unsatisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Sustainable post-tsunami infrastructure reconstruction and development in Aceh and Nias. | Value | NA | 52 of good quality sub-projects are complet and ha | Good quality outcomes of reconstruction. A final s |
Date | June 29, 2007 | October 1, 2012 | December 31, 2012 | |
Comment | The appropriate designs, proper construction supervision for each subproject are closely monitored by the consultant and the MoPW.Also all completed subproject are handed over to the relevant authorities. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Proposals submitted to IDA for proposed subprojects include a set of quality indicators. | Value | NA | Achieved | Design Specifications are well defined and met, 10 |
Date | December 20, 2006 | October 1, 2012 | December 31, 2012 | |
Comment | All sub-projects meet the targeted objective with high quality of design and supervision. |
Approved subprojects after the Recipient's infrastructure development strategy developed under IREP is drafted to reflect the priorities laid out therein | Value | NA | Achived | Prioritized projects from local governments, 100% |
Date | December 20, 2006 | October 1, 2012 | December 31, 2012 | |
Comment | All sub-projects meet the targeted objective with high quality of design and supervision. |
Technical designs of approved subprojects are sound and appropriate | Value | NA | Achieved | Sub-project appraisal checklists/DED |
Date | December 20, 2006 | October 1, 2012 | December 31, 2012 | |
Comment | All designs are sound and carried out by international qualified design firms. |
Proper financial and safeguards measures are integrated into the preparation of approved subprojects. | Value | Initial sub-projects were reviewed by Bank Safegua | Achieved | Sub-project appraisal checklists would ensure stat |
Date | December 20, 2006 | October 1, 2012 | December 31, 2012 | |
Comment | All sub-projects had provisions to implement the adequate EMP and LARAPs. More over appropriate financial measures applied to allsub-projects. |
Implementation of approved subprojects is adequately supervised. | Value | NA | Achieved | Adequately staffed supervision, QA safeguards cons |
Date | December 20, 2006 | October 1, 2012 | December 31, 2012 | |
Comment | All sub-projects had been continuously supervised by qualified consultants and personnel. |
Performance and financial audit reports (in addition to external audits financed under IREP) are prepared. | Value | NA | In general, Complied with | FM reports to be prepared and submitted on time, 1 |
Date | December 20, 2006 | October 1, 2012 | December 31, 2012 | |
Comment | All required audits and FM reports were prepared and submitted to the Bank. However, the 2011 audit for TF057657 is still underpreparation and has been due since June 30, 2012. It is expected to be submitted to the Bank in November 2012. Also |
Restoration of the destroyed environment of the wetlands across the West Coast Road and around the Kuala Bubon Bridge | Value | Impacted environment at many sections along the w | Completed as Provisions are integrated with the co | Plantation of local species to restore the devasta |
Date | August 13, 2010 | October 31, 2011 | December 31, 2012 | |
Comment |
Improved Access from Calang to Meulaboh across the Kuala Bubon Bridge | Value | 2.0 hours | In progress | < 1.0 hour |
Date | August 13, 2010 | October 1, 2012 | December 31, 2012 | |
Comment | Construction works are ongoing. The bridge is around 70% completed. |
Efficient travel between Calang to Meulaboh across the Kuala Bubon Bridge. The bridge will eliminate the lee way between Km216 and Km 234 | Value | 38 km travel distance | In progress | 18 km travel distance |
Date | August 13, 2010 | October 1, 2012 | December 31, 2012 | |
Comment | Construction works are ongoing. The bridge is around 70% completed. |
A comprehensive survey designed to assess the state of infrastructure service delivery in the 12 districts of Aceh and Nias benefiting from IRFF and AF financing of individual subprojects | Value | NA | Achieved | Comprehensive assessment survey at the end of the |
Date | December 20, 2006 | October 1, 2012 | March 31, 2007 | |
Comment | this survey was conducted by the IPM to assist in prioritizing construction sub-projects. |