Financier | Commitments |
---|---|
IDA Grant | 120.00 |
Japan Social Development Fund | 14.40 |
Afghanistan Resilience Trust Fund | 449.50 |
P102288
Closed
Ladisy Komba Chengula
N/A
September 25, 2006
(as of board presentation)
December 7, 2006
May 15, 2007
US$ 583.90 million
N/A
2007
US$ 583.90 million
B
Not Applicable
June 30, 2014
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
IDA Grant | 120.00 |
Japan Social Development Fund | 14.40 |
Afghanistan Resilience Trust Fund | 449.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 120.00 |
IBRD + IDA Commitment | 120.00 |
Lending Instrument | |
---|---|
Grant Amount | 463.90 |
Total Project Cost** | 583.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 7, 2006 | IDA-H2610 | Loan Commitment | 120,000,000.00 |
May 12, 2009 | IDA-H4760 | Loan Commitment | 75,000,000.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Unsatisfactory | 2011-01-15 |
Counterpart Funding | Satisfactory | 2011-01-15 |
Overall Implementation Progress (IP) | Satisfactory | 2011-01-15 |
Financial Management | Moderately Satisfactory | 2011-01-15 |
Monitoring and Evaluation | Moderately Satisfactory | 2011-01-15 |
Progress towards achievement of PDO | Satisfactory | 2011-01-15 |
Project Management | Satisfactory | 2011-01-15 |
Overall | High | 2011-01-15 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-31-2012 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Substantial |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 03-13-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percent of CDCs functioning beyond NSP block grants to address critical development needs as identified by villagers. | Value | 0 | Data will be available after the second and third | At least 60% |
Date | September 30, 2006 | December 5, 2010 | June 30, 2011 | |
Comment |
Percentage of sampled community members confirming that CDCs are respresentative, following NSP principles. | Value | 0 | Interim findings from the first follow up survey i | 60% of sampled community members |
Date | September 30, 2006 | December 5, 2010 | September 30, 2011 | |
Comment |
ERR of the community subprojects | Value | N/A | 18.9% of sampled subprojects | Greater than 15% |
Date | September 30, 2006 | December 5, 2010 | September 30, 2011 | |
Comment |
Percentage of CDCs functioning to address critical development needs as identified by villagers | Value | 0 | 87% of male and 60% of female CDC/subcommittee mem | At least 60% |
Date | September 30, 2006 | December 5, 2010 | September 30, 2011 | |
Comment |
Number of communities across the country availing basic social and productive infrastructure and other services. | Value | 9,156 (at end of NSPI) | 19,451 communities have finished at least 1 subpro | At least 23,700 communities |
Date | September 30, 2006 | December 5, 2010 | September 30, 2011 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of CDC members nationally that are women | Value | According to the Implementation Monitoring (IM) Re | Minimum of 35% | |
Date | December 5, 2010 | September 30, 2010 | ||
Comment |
Percent of CDCs with community development plans developed in accordance with NSP principles | Value | 0 | Accrording to IM report, 98% of CDCs prepared the | Minimum of 80% |
Date | September 30, 2006 | December 5, 2010 | September 30, 2011 | |
Comment |
Percent of NSP-financed projects that are completed | Value | 6,913 (At closing of NSP 1) | 87% of financed subprojects have been completed | At least 70% |
Date | September 30, 2006 | December 5, 2010 | September 30, 2011 | |
Comment |
Percent of sampled infrastructure projects that are functional one year after date of completion | Value | According to Post Implementation Monitoring report | At least 80% of sampled infrastructure projects | |
Date | December 5, 2010 | September 30, 2011 | ||
Comment |
Number of labour days created | Value | Approximately 24 million labour days created | At least 21 million labour days | |
Date | December 5, 2010 | September 30, 2010 | ||
Comment |