Financier | Commitments |
---|---|
Local Communities | 3.70 |
IDA Grant | 30.00 |
Borrower/Recipient | 6.60 |
P102354
Closed
Amadou Alassane
N/A
June 17, 2008
(as of board presentation)
August 29, 2008
December 24, 2008
US$ 40.30 million
N/A
2009
US$ 30.00 million
B
Not Applicable
June 30, 2020
No
BANK APPROVED
July 16, 2013
Financier | Commitments |
---|---|
Local Communities | 3.70 |
IDA Grant | 30.00 |
Borrower/Recipient | 6.60 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 30.00 |
IBRD + IDA Commitment | 30.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.30 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 29, 2008 | IDA-H4230 | Loan Commitment | 30,000,000.00 |
Oct 22, 2013 | IDA-H4230 | Loan Cancel | 39,686.63 |
Oct 18, 2013 | IDA-H4230 | Loan Disb | -1,085.30 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2013-01-19 |
Financial Management | Satisfactory | 2013-01-19 |
Monitoring and Evaluation | Satisfactory | 2013-01-19 |
Overall Implementation Progress (IP) | Satisfactory | 2013-01-19 |
Counterpart Funding | Satisfactory | 2013-01-19 |
Procurement | Satisfactory | 2013-01-19 |
Project Management | Satisfactory | 2013-01-19 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-30-2013 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-30-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: 01-20-2021 |
---|---|---|
Outcome Rating | Moderately Satisfactory | Moderately Satisfactory |
Risk To Development Outcome | Significant | Substantial |
Bank Performance | Moderately Satisfactory | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory | Satisfactory |
Government Performance | Moderately Satisfactory | Not Rated |
Implementing Agency | Moderately Satisfactory | Satisfactory |
Icr Quality | Satisfactory | Not Rated |
M&e Quality | Substantial | Substantial |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Targeted communes for which more than 50% of the population are satisfied with the CDP through the Annual Investment Plan (AIP) | Value | 13.00 | 92.00 | 63.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | Total number of communes is 164 (IDA 108 and IFAD 52) | 13% is the baseline. No result recorded for the moment |
Targeted communes that increase the rate of coverage of social services by more than 2% in one of the following three sectors: education, health, potable water | Value | 0.00 | 65.60 | 50.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | No result recorded for the moment |
Beneficiaries of income generating activities in targeted communes who increase their revenue | Value | 0.00 | 75.00 | 60.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | No result recorded for the moment |
Targeted communes that increase the rate of coverage of education services by more than 2% | Value | 25.00 | 66.00 | 50.00 |
Date | December 24, 2008 | September 30, 2012 | April 4, 2013 | |
Comment |
Targeted communes that increase the rate of coverage of health services by more than 2% | Value | 20.00 | 55.55 | 50.00 |
Date | December 24, 2008 | September 30, 2012 | April 4, 2013 | |
Comment |
Targeted communes that increase the rate of coverage of potable water services by more than 2% | Value | 41.00 | 83.00 | 50.00 |
Date | December 24, 2008 | September 30, 2012 | April 4, 2013 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% of targeted communes using the RDS methodological guide to plan SLM activities. | Value | 2 | See above | 62 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | There is no updated data for this specific indicator.e updated indicators come from assessment made by the PAC2 M&E beforeDecember 2010 |
% of targeted communes that design/update their CDP according to the National Communal Planning Guide. | Value | 32 | See above | 92 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | No updated value is available for this specific indicator |
% of targeted communies for which more than 50% of the population are satisfied with the design of the Communal Development Plan (CDP). | Value | 13 | See above | 63 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | However this indicator was not been maintained by the MTR |
% of targeted communes that adjust their CDP and AIP based on feed back from communities. | Value | 30 | See above | 90 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | Current value on the basis of annual assessment made at the end of each CY year. | The target which was 60 % has been raised to 90 % from the MTR |
%of performance-based contracts with public service providers satisfactorily implemented at communal level. | Value | 0 | 80 | |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | This indicator is not maintained by the MTR. |
% of targeted communes that set up adequate measures to ensure sustainability of micro-projects (management committee, maintenance fund and technical assistance contracts). | Value | 65 | See above | 90 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | this target was initially 25% ; then raised to 90% from the MTR |
% targeted communes where 100% of micro-projects include environmental and social safeguards. | Value | 15 | See above | 75 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | The MTR mentioned % of targeted communes where 80% of MP include env. & social safeguards | Th eprevious target was 60% but has now been raised to 75%. |
% communes in which more than 50% of the population are aware of commune budget and resource management. | Value | 6 | 64 | 66 |
Date | December 24, 2008 | October 31, 2011 | April 30, 2013 | |
Comment |
% communes in which technical audits are satisfactory and financial audits are unqualified. | Value | 6 | See above | 86 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | Value resulting from an annual assessment |
Percentage of targeted communes mobilizing more than 30% of internal and other resources to co-finance the AIP. | Value | 48 | See above | 88 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment |
Hectares of lanc reclamation and protection. | Value | 5591 | See above | 15,472 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | The initial baseline and end target have been revised to take into account massive planting losses due insufficiency of rainfall. | End target has been downsized from 17, 472 to 15,472 accordingly initially foreseen for acacia plantation. |
Hectares of Acacia Senegalensis under the Biocarbon fund transaction. | Value | 3591 | See above | 8,472 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | 3591 | This is the actual value of covered areas. Worth to be kept in the records | During the MTR Target was downsized from 15,472 to 8, 472 |
% communes that submit quarterly M&E reports on time. | Value | 20 | See above | 80 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment |
Number of collaboration agreements signed with other projects at the regional level satisfactorily implemented. | Value | 2 | See above | S |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | collaboration Agreements signed with WFP, PUSADR, PAC-RC, the WAAPP1-C Niger and the BEEEI. | S means satisfactory at each step. |
Project annual audit opinion has been qualified. | Value | S | S | |
Date | December 24, 2008 | April 30, 2013 | April 30, 2013 | |
Comment | Please as follows the correct formulation of this indicator:The Project annual audit opinion has not been qualified. | S means satisfactory for the Audit Report |
Health facilities constructed, renovated, and/or equipped (number) | Value | 0.00 | 26.00 | 40.00 |
Date | August 12, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | Baseline figure not currently available because local development plans are not ready. | One additional health facility has been constructed from the last SPN mission. By April 30, 2012 , 24 additional healthfacilities since the last supervision | Target will be confirmed once local development plans are ready. |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 72.00 | 300.00 |
Date | August 19, 2009 | September 30, 2012 | April 30, 2013 | |
Comment | 17 new water points have been realized from the last SPN to May 15, 2011. By April 30, 2012, 55 additional water points sincethelast mission |
Roads rehabilitated, Rural | Value | 0.00 | 0.72 | 100.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | Baseline figure not currently available because local development plans are not ready. | 1 road facility of 0.720 meters has been constructed in Tillaberi region during the period under review. No additional rural roadon IDA and/GEF financing since the first case. |
People with access to improved sanitation in the areas served by the project | Value | 0.00 | 0.00 | 0.00 |
Date | August 19, 2009 | September 30, 2012 | April 30, 2013 | |
Comment | Baseline figure not currently available because local development plans are not ready. | See above Health facilities.Number of people yet to be determined by the M&E Unit of the PAC2. Consider the same previous comment. | Target yet to be determined by the M&E of the PAC2.Not in schedule of the Project. |
Targeted communes in which more than 200 additional hectares of land are protected and reclaimed | Value | 0.00 | 72.00 | 60.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | The previous baseline was 4% but has been corrected and kept at 0. Further progress continues to be noted so far in this regard |
Targeted communes setting up land tenure commissions that start delivering land titles. | Value | 36.00 | 96.00 | 100.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | The baseline value has been corrected from 13 to 36 following an updating assessment. | 13% was the initial baseline with is corrected to be at 0. Some progress has been noted so far in this regard | The target previously mentioned is corrected and becomes 100 instead of 60 as stated in the previous ISR. |
Targeted communes that design/ update their CDP acc to the national Communal Planning Guide | Value | 32.00 | 100.00 | 92.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | 32 is the baseline. This indicator has yet to be updated | The target value has been corrected from 100 in the previous ISR to 92 currently |
Targeted communes using the RDS methodological guide to plan SLM activities | Value | 2.00 | 100.00 | 62.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | 2 is the baseline. This indicator has yet to be updated |
Targeted communies for which more than 50% of the population are satisfied with the design of the Communal Development Plan (CDP) | Value | 13.00 | 92.00 | 63.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment |
Targeted communes that adjust their CDP and AIP based on feed back from communities | Value | 30.00 | 93.30 | 90.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment |
Performance-based contracts with public service providers satisfactorily implemented at communal level | Value | 0.00 | 99.00 | 80.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | already recorded in this ISR for both target and actual values. |
Targeted communes that set up adequate measures to ensure sustainability of micro-projects | Value | 65.00 | 93.00 | 90.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | This indicator looks redundant since already updated. |
Targeted communes where 100% of micro-projects include environmental and social safeguards | Value | 15.00 | 100.00 | 90.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | Baseline and target values of this indicator has been revised. It becomes redundant since already updated above. |
Communes in which more than 50% of the population are aware of commune budget and resource management | Value | 6.00 | 88.00 | 66.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | The current value, target value are also redundant since already recorded above |
Communes in which technical audits are satisfactory and financial audits are unqualified | Value | 6.00 | 100.00 | 86.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | This indicator has yet to be updated as of the 6th supervision time. |
Targeted communes mobilizing more than 30% of internal and other resources to co-finance the AIP | Value | 48.00 | 90.00 | 86.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | The previous target was 88% |
Hectares of land reclamation and protection | Value | 5591.00 | 32202.00 | 15472.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | This value translates progress since the MTR although redundant since already recorded above. |
Hectares of Acacia Senegalensis under the Biocarbon fund transaction | Value | 3591.00 | 8133.00 | 8472.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2012 | |
Comment | This area is related to the achievement of the PAC1 | The values have been revised by the MTR. THis indicator is redundant since already updated above. | The target value has been revised down from 2100 ha |
Communes that submit quarterly M&E reports on time | Value | 20.00 | 81.25 | 80.00 |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | It is a percentage i.e 30% | This is a cumulative value |
Project bi-annual implementation progress reports are disseminated to public services donors and other relevant stakeholders | Value | 0 | S | S |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment |
Project annual audit opinion has been qualified | Value | S | S | S |
Date | December 24, 2008 | September 30, 2012 | April 30, 2013 | |
Comment | It is all about qualitative appreciation | This is an end of phase cumulative value |
&% pf targeted Communes which have elaborated their CDP according to the Natural Management (NRM) methodological guide | Value | 2.00 | 0.00 | 0.00 |
Date | September 30, 2012 | April 30, 2013 | ||
Comment | N/A. This indicator was not maintained since the MTR. |
Percentage of communes-civil services implemented in a satisfacory manner. | Value | 0.00 | 97.00 | 80.00 |
Date | September 30, 2012 | April 30, 2013 | ||
Comment | Previous values modified by the PIU both for actual and target |
Percentage of communes taking appropriate measures for microprojects sustainability (managing committees, technical assistance, recurrent charges, ..) | Value | 65.00 | 93.00 | 90.00 |
Date | September 30, 2012 | April 30, 2013 | ||
Comment |
Percentage of Communes in which 80% of microprojects take into account environmental and social safeguards measures | Value | 15.00 | 100.00 | 75.00 |
Date | September 30, 2012 | April 30, 2013 | ||
Comment |
Percentage of communes in which at least 50% of the population knows pririty activities, budget and management modialities | Value | 6.00 | 87.00 | 66.00 |
Date | September 30, 2012 | April 30, 2013 | ||
Comment |