Morocco Urban WS&S Access Pilots

Abstract*

The objective of the Improved Access to Water and Sewerage Services Project in Morocco is to provide sustainable access to combined water and sewerage services to peri-urban 'quartiers' with high levels of 'vulnerable' households. The project will be coordinated and administered by the Ministry of Interior, and implemented by the three incumbent providers of water supply and sewerage services in the three selected urban centers, namely Casablanca...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Objective of the project is to provide sustainable access to combined water and sewerage services to peri-urban #quartiers# with high levels of #vulnerable# households, ie with household incomes falling under 295 US$/month (150% of the poverty line of Dh 1687) or about US$60/cap/month.

Key Details

Project Details

  • P102527

  • Closed

  • Xavier Chauvot De Beauchene

  • N/A

  • Morocco

  • January 29, 2007

  • (as of board presentation)

    January 29, 2007

  • January 29, 2007

  • US$ 7.00 million

  • C

  • Not Applicable

  • December 31, 2011

  • BANK APPROVED

  • February 24, 2016

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Partnership on Output-based Aid 7.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 7.00
Total Project Cost** 7.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2012-01-10
Financial Management Moderately Satisfactory 2012-01-10
Monitoring and Evaluation Moderately Satisfactory 2012-01-10
Progress towards achievement of PDO Satisfactory 2012-01-10
Project Management Satisfactory 2012-01-10
Counterpart Funding Satisfactory 2012-01-10
Overall Implementation Progress (IP) Satisfactory 2012-01-10

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2012
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-21-2013PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • New piped household water connections that are resulting from the project interventionValue0.0011147.0011230.00
    DateJune 1, 2006March 31, 2011December 31, 2011
    CommentCasablanca: 0;Meknes Urban: 0; Meknes Rural: 0;Tangier: 0Casablanca: 5,622;Meknes Urban: 705;Meknes Rural: 1,444;Tangier: 3,376Casablanca: 5,782;Meknes Urban: 603;Meknes Rural: 1,134; Tangier: 2,902
  • Number of people in urban areas provided with access to Improved Sanitation under the projectValue0.0045825.0047390.00
    DateJune 1, 2006March 31, 2011December 31, 2010
    CommentCasablanca: 0;Meknes Urban: 0;Meknes Rural: N/A;Tangier: 0Casablanca: 28,110;Meknes Urban: 2,905; Tangier: 16,880Casablanca: 28,910;Meknes Urban: 3,970;Tangier: 14,510
  • Number of water and sewerage connections made (Total number of beneficiary households)Value0Casablanca: 5,622 simultaneous connections Meknes Casablanca: 5,782 simultaneous connections Meknes
    DateJune 1, 2006March 31, 2011December 31, 2010
    Comment
  • New piped household water connections that are resulting from the project intervention in Meknès Rural AreasValue0.001444.001134.00
    DateJune 1, 2006September 30, 2010December 31, 2011
    CommentThe remaining subsidy amount allows subsidizing a total of 1,315 connections in Meknes rural areas.
  • New piped household water connections that are resulting from the project intervention in TangierValue0.003376.002902.00
    DateJune 1, 2006June 30, 2010December 31, 2010
    CommentThe remaining subsidy amount allows subsidizing only 727 of the 1201 additional simultaneous connection made by Amendis-Tangier,making the total connection subsidized 2,909.
  • New piped household water connections that are resulting from the project intervention in Meknès Urban AreasValue0.00705.00603.00
    DateJune 1, 2006September 30, 2010December 31, 2010
    CommentThe remaining subsidy amount allows subsidizing a total of 687 connections in Meknes urban areas.
  • New piped household water connections that are resulting from the project intervention in CasablancaValue0.005622.005782.00
    DateJune 1, 2006March 31, 2011December 31, 2011
    CommentThe remaining subsidy amount allows subsidizing only 444 of the 493 additional simultaneous connection made by LYDEC inCasablanca,making the total connection subsidized 5,573.
  • Number of people in urban areas provided with access to Improved Sanitation under the project in TangierValue0.0016880.0014510.00
    DateJune 1, 2006June 30, 2010December 31, 2010
    Comment
  • Number of people in urban areas provided with access to Improved Sanitation under the project in Meknès Urban AreasValue0.002905.003970.00
    DateJune 1, 2006September 30, 2010December 31, 2010
    Comment
  • Number of people in urban areas provided with access to Improved Sanitation under the project in CasablancaValue0.0016880.0028910.00
    DateJune 1, 2006March 31, 2011December 31, 2010
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Uptake by Beneficiary households per operator and eligible areaValue0% uptakeunchangedCasablanca: 80% Meknes: 90% Tangiers: 85%
    DateJune 1, 2006June 30, 2010December 31, 2010
    Comment
  • Average monthly consumption per Beneficiary householdValueNo piped service provided.unchangedIndicative target is for 40 l/day/person, translat
    DateJune 1, 2006June 30, 2010December 31, 2010
    Comment
  • Average consumption bill per Beneficiary householdsValueNo service, hence no consumptionunchangedInformation, no target value
    DateJune 1, 2006June 30, 2010December 31, 2010
    Comment
  • Collection ratio for consumption bills per operator, and to the extend possible collection ratio of connection feesValue0% (no service)unchangedCollection ratio in project areas equal or superio
    DateJune 1, 2006June 30, 2010December 31, 2010
    Comment