Financier | Commitments |
---|---|
IDA Credit | 300.00 |
Borrower/Recipient | 200.00 |
P102549
Closed
Tara Beteille , Francisco Marmolejo
Republic of India
December 24, 2008
(as of board presentation)
March 18, 2010
August 6, 2010
US$ 500.00 million
Ministry of Human Resource Development
2010
US$ 300.00 million
B
Not Applicable
March 31, 2017
BANK APPROVED
September 6, 2022
Financier | Commitments |
---|---|
IDA Credit | 300.00 |
Borrower/Recipient | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 300.00 |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 500.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 15, 2021 | IDA-46850 | Int Charges | 42,166.13 |
Jul 15, 2021 | IDA-46850 | Int Charges | 42,166.13 |
Jul 15, 2021 | IDA-46850 | Int Charges | 514,903.70 |
Jul 15, 2021 | IDA-46850 | Int Charges | 514,903.70 |
Jul 15, 2022 | IDA-46850 | Int Charges | 5,561.31 |
Jul 15, 2022 | IDA-46850 | Int Charges | 5,561.31 |
Jul 15, 2022 | IDA-46850 | Loan Repay | 4,351,325.50 |
Jul 15, 2022 | IDA-46850 | Int Charges | 456,956.28 |
Jul 15, 2022 | IDA-46850 | Int Charges | 456,956.28 |
Jan 15, 2022 | IDA-46850 | Loan Repay | 2,305,741.50 |
Jan 15, 2022 | IDA-46850 | Int Charges | 494,139.72 |
Jan 15, 2022 | IDA-46850 | Int Charges | 494,139.72 |
Jan 15, 2022 | IDA-46850 | Loan Repay | 28,936.27 |
Jan 15, 2023 | IDA-46850 | Loan Repay | 78,900.39 |
Jan 15, 2023 | IDA-46850 | Int Charges | 335,069.97 |
Jan 15, 2023 | IDA-46850 | Int Charges | 335,069.97 |
Jan 15, 2020 | IDA-46850 | Int Charges | 507,888.16 |
Jan 15, 2020 | IDA-46850 | Int Charges | 507,888.16 |
Jan 15, 2020 | IDA-46850 | Int Charges | 9,037.04 |
Jan 15, 2020 | IDA-46850 | Int Charges | 9,037.04 |
Jan 15, 2020 | IDA-46850 | Loan Repay | 4,591,106.50 |
Jul 15, 2020 | IDA-46850 | Int Charges | 456,278.80 |
Jul 15, 2020 | IDA-46850 | Int Charges | 456,278.80 |
Jul 15, 2020 | IDA-46850 | Int Charges | 25,994.75 |
Jul 15, 2020 | IDA-46850 | Int Charges | 25,994.75 |
Jul 15, 2020 | IDA-46850 | Loan Repay | 2,305,624.80 |
Jan 15, 2021 | IDA-46850 | Int Charges | 65,842.15 |
Jan 15, 2021 | IDA-46850 | Int Charges | 65,842.15 |
Jan 15, 2021 | IDA-46850 | Loan Repay | 2,388,571.50 |
Jan 15, 2021 | IDA-46850 | Int Charges | 486,944.40 |
Jan 15, 2021 | IDA-46850 | Int Charges | 486,944.40 |
Jul 15, 2018 | IDA-46850 | Int Charges | 74,823.18 |
Jul 15, 2018 | IDA-46850 | Int Charges | 74,823.18 |
Jul 15, 2018 | IDA-46850 | Loan Repay | 4,659,335.50 |
Jul 15, 2018 | IDA-46850 | Int Charges | 594,065.25 |
Jul 15, 2018 | IDA-46850 | Int Charges | 594,065.25 |
Jan 15, 2019 | IDA-46850 | Int Charges | 522,871.78 |
Jan 15, 2019 | IDA-46850 | Int Charges | 522,871.78 |
Jan 15, 2019 | IDA-46850 | Loan Repay | 99,686.39 |
Jan 15, 2019 | IDA-46850 | Loan Repay | 4,537,482.50 |
Jul 15, 2019 | IDA-46850 | Int Charges | 50,591.30 |
Jul 15, 2019 | IDA-46850 | Int Charges | 50,591.30 |
Jul 15, 2019 | IDA-46850 | Loan Repay | 4,602,007.50 |
Jul 15, 2019 | IDA-46850 | Int Charges | 543,182.44 |
Jul 15, 2019 | IDA-46850 | Int Charges | 543,182.44 |
Jul 15, 2016 | IDA-46850 | Loan Repay | 1,921.55 |
Jul 15, 2016 | IDA-46850 | Loan Repay | 4,689,664.50 |
Jul 15, 2016 | IDA-46850 | Int Charges | 389,623.34 |
Jul 15, 2016 | IDA-46850 | Int Charges | 389,623.34 |
Feb 16, 2017 | IDA-46850 | Loan Disb | 11,366,849.00 |
Jun 23, 2016 | IDA-46850 | Loan Disb | 9,337,583.00 |
Jan 15, 2017 | IDA-46850 | Int Charges | 429,523.94 |
Jan 15, 2017 | IDA-46850 | Int Charges | 429,523.94 |
Jan 15, 2017 | IDA-46850 | Loan Repay | 57,904.81 |
Jan 15, 2017 | IDA-46850 | Loan Repay | 4,490,065.00 |
Mar 20, 2017 | IDA-46850 | Loan Disb | 10,699,763.00 |
Jun 29, 2017 | IDA-46850 | Loan Disb | 4,902,342.00 |
Jun 16, 2017 | IDA-46850 | Loan Disb | 18,215,970.00 |
Jul 15, 2017 | IDA-46850 | Loan Repay | 45,308.53 |
Aug 1, 2017 | IDA-46850 | Loan Disb | 3,194,793.50 |
Jul 15, 2017 | IDA-46850 | Loan Repay | 4,634,666.00 |
Jul 15, 2017 | IDA-46850 | Int Charges | 427,766.78 |
Jul 15, 2017 | IDA-46850 | Int Charges | 427,766.78 |
Aug 1, 2017 | IDA-46850 | Loan Cancel | 2,094,157.40 |
Jan 15, 2018 | IDA-46850 | Int Charges | 90,350.25 |
Jan 15, 2018 | IDA-46850 | Int Charges | 90,350.25 |
Jan 15, 2018 | IDA-46850 | Loan Repay | 4,762,227.00 |
Jan 15, 2018 | IDA-46850 | Int Charges | 547,486.00 |
Jan 15, 2018 | IDA-46850 | Int Charges | 547,486.00 |
Jul 15, 2014 | IDA-46850 | Int Charges | 209,352.44 |
Jul 15, 2014 | IDA-46850 | Int Charges | 209,352.44 |
Mar 30, 2015 | IDA-46850 | Loan Disb | 9,790,735.00 |
Aug 27, 2015 | IDA-46850 | Loan Disb | 7,568,861.50 |
Jul 15, 2015 | IDA-46850 | Int Charges | 5,553.19 |
Jul 15, 2015 | IDA-46850 | Int Charges | 5,553.19 |
Jul 15, 2015 | IDA-46850 | Loan Repay | 4,704,039.50 |
Jul 15, 2015 | IDA-46850 | Int Charges | 304,025.10 |
Jul 15, 2015 | IDA-46850 | Int Charges | 304,025.10 |
Jan 15, 2016 | IDA-46850 | Loan Repay | 57,817.03 |
Jan 15, 2016 | IDA-46850 | Loan Repay | 4,598,866.50 |
Jan 15, 2016 | IDA-46850 | Int Charges | 359,462.60 |
Jan 15, 2016 | IDA-46850 | Int Charges | 359,462.60 |
Jun 15, 2015 | IDA-46850 | Loan Disb | 12,766,659.00 |
Mar 30, 2016 | IDA-46850 | Loan Disb | 7,087,521.00 |
Mar 2, 2016 | IDA-46850 | Loan Disb | 6,741,880.50 |
Sep 28, 2016 | IDA-46850 | Loan Disb | 10,456,356.00 |
Nov 6, 2014 | IDA-46850 | Loan Disb | 766,037.44 |
Nov 21, 2014 | IDA-46850 | Loan Disb | 10,749,618.00 |
Jan 15, 2015 | IDA-46850 | Int Charges | 342.35 |
Jan 15, 2015 | IDA-46850 | Int Charges | 342.35 |
Jan 15, 2015 | IDA-46850 | Int Charges | 245,382.05 |
Jan 15, 2015 | IDA-46850 | Int Charges | 245,382.05 |
Jul 15, 2013 | IDA-46850 | Int Charges | 1,452.78 |
Jul 15, 2013 | IDA-46850 | Int Charges | 1,452.78 |
Jul 15, 2013 | IDA-46850 | Int Charges | 170,656.83 |
Jul 15, 2013 | IDA-46850 | Int Charges | 170,656.83 |
Dec 27, 2013 | IDA-46850 | Loan Cancel | 79,995,520.00 |
Jan 15, 2014 | IDA-46850 | Int Charges | 1,004.87 |
Jan 15, 2014 | IDA-46850 | Int Charges | 1,004.87 |
Jan 15, 2014 | IDA-46850 | Int Charges | 174,958.52 |
Jan 15, 2014 | IDA-46850 | Int Charges | 174,958.52 |
May 2, 2014 | IDA-46850 | Loan Disb | 9,838,936.00 |
May 2, 2014 | IDA-46850 | Loan Disb | 11,812,477.00 |
Jul 15, 2014 | IDA-46850 | Int Charges | 751.51 |
Jul 15, 2014 | IDA-46850 | Int Charges | 751.51 |
Jul 15, 2024 | IDA-46850 | Loan Repay | 4,410,980.00 |
Mar 18, 2010 | IDA-46850 | Loan Commitment | 300,000,000.00 |
Jan 15, 2023 | IDA-46850 | Loan Repay | 4,402,369.00 |
Jul 15, 2023 | IDA-46850 | Int Charges | 119,264.77 |
Jul 15, 2023 | IDA-46850 | Loan Repay | 4,501,542.00 |
Jul 15, 2023 | IDA-46850 | Int Charges | 394,704.03 |
Jul 15, 2023 | IDA-46850 | Int Charges | 394,704.03 |
Jul 15, 2023 | IDA-46850 | Int Charges | 119,264.77 |
Jan 15, 2024 | IDA-46850 | Int Charges | 43,662.43 |
Jan 15, 2024 | IDA-46850 | Int Charges | 43,662.43 |
Jan 15, 2024 | IDA-46850 | Loan Repay | 4,440,192.50 |
Jan 15, 2024 | IDA-46850 | Int Charges | 380,760.06 |
Jan 15, 2024 | IDA-46850 | Int Charges | 380,760.06 |
Jul 15, 2024 | IDA-46850 | Int Charges | 382,678.60 |
Jul 15, 2024 | IDA-46850 | Int Charges | 382,678.60 |
Jul 15, 2024 | IDA-46850 | Int Charges | 35,342.35 |
Jul 15, 2024 | IDA-46850 | Int Charges | 35,342.35 |
Jul 15, 2021 | IDA-46850 | Loan Repay | 2,362,337.50 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2017-03-31 |
Procurement | Satisfactory | 2017-03-31 |
Progress towards achievement of PDO | Satisfactory | 2017-03-31 |
Counterpart Funding | Moderately Satisfactory | 2017-03-31 |
Project Management | Satisfactory | 2017-03-31 |
Financial Management | Satisfactory | 2017-03-31 |
Monitoring and Evaluation | Satisfactory | 2017-03-31 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-28-2017 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-05-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of supported programs that are accredited or applied for | Value | 30.00 | 55.00 | 65.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Percentage of institutions with academic autonomy | Value | 30.00 | 70.00 | 70.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Percentage Faculty with at least an M. Tech (regular and contract) | Value | 45.00 | 88.00 | 92.35 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Total number of Master and PhD students | Value | 30000.00 | 41000.00 | 45658.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of publications in refereed journals (within the field of Engineering) | Value | 7032.00 | 18000.00 | 18163.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Percentage of Faculty with or pursuing M. Tech and PhD (regular and contract) | Value | 63.00 | 90.00 | 93.45 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Increase in the satisfaction index of student and faculty | Value | 3.90 | 4.30 | 4.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Number of faculty members that have benefitted from the teaching effectiveness training (under sub-component 1.3) | Value | 0.00 | 2900.00 | 3750.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Percentage of externally funded research and development projects and consultancies in total revenue | Value | 6.00 | 12.00 | 14.04 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Transition rate of students from disadvantaged backgrounds from the first year to second year of undergraduate study | Value | 45.00 | 60.00 | 61.45 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Share of TEQIP Supported Institutions from states in lagging in technical education | Value | 14.00 | 20.00 | 23.50 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Direct project beneficiaries | Value | 300000.00 | 405000.00 | 443970.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Number of governance self reviews received | Value | 0.00 | 190.00 | 186.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Number of Governance Development plans received | Value | 0.00 | 180.00 | 186.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Fully functional MIS -Number of institutions reporting at least 70% of the indicators | Value | 0.00 | 180.00 | 181.00 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |
Female beneficiaries | Value | 26.00 | 30.00 | 29.40 |
Date | November 30, 2009 | March 31, 2017 | March 10, 2017 | |
Comment |