Skip to Main Navigation

Sustainable Financing & Management of Eastern Caribbean Marine Ecosystem Project

Abstract*

The objective of the Sustainable Financing and Management of Eastern Caribbean Marine Ecosystem Project is to contribute to enhancing the long-term sustainability of protected area networks in the Eastern Caribbean sub-region by: 1) establishing sustainable financing mechanisms; 2) strengthening of the marine protected area networks; and 3) deploying a regional monitoring and information system for the protected area networks. There are four components...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To contribute to enhancing the long-term sustainability of Protected Area networks in the Participating Countries by: (i) establishing sustainable financing mechanisms; (ii) strengthening of the Marine Protected Area networks; and (iii) deploying a regional monitoring and information system for the Protected Area networks.

Key Details

Project Details

  • P103470

  • Closed

  • Nyaneba Nkrumah

  • The Nature Conservancy

  • OECS Countries

  • August 4, 2009

  • (as of board presentation)

    August 4, 2011

  • November 18, 2011

  • US$ 13.25 million

  • B

  • Not Applicable

  • December 31, 2016

  • BANK APPROVED

  • March 15, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 0.93
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) 4.50
Foundation/s (identified) 4.70
Global Environment Facility (GEF) 8.75

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 13.25
Total Project Cost** 18.87

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Summary Global Objective Rating Moderately Satisfactory 2016-12-23
Financial Management Satisfactory 2016-12-23
Monitoring and Evaluation Satisfactory 2016-12-23
Overall Implementation Progress (IP) Moderately Satisfactory 2016-12-23
Overall Safeguards Rating Satisfactory 2016-12-23
Procurement Satisfactory 2016-12-23
Counterpart Funding Satisfactory 2016-12-23
Project Management Moderately Satisfactory 2016-12-23

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2017
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-10-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1. Caribbean Biodiversity Fund (CBF) is operational with a Board, a Secretariat, an asset manager, a work program and has an endowment of US$15 million for the Participating Countries to generate incoValue0.0032400000.0015000000.00
    DateAugust 4, 2011December 1, 2016December 30, 2016
    Comment
  • 2. The national level trust funds (NPATFs) provide recurrent financing per year for 3 of the 5 participating countriesValue0.000.003.00
    DateAugust 4, 2011June 14, 2016December 30, 2016
    Comment
  • 4. At least two demonstration sites generate useful MPA management information and lessons for other Project Participating Countries and for increased dissemination to MPA managers in the Caribbean reValue0.002.002.00
    DateAugust 4, 2011December 1, 2016December 30, 2016
    Comment
  • 5. A region-wide, open access, web-based monitoring system for effective PA management is operational and the outputs are availableto natural resources managers at the national and regional levelsValueVarious databases exist but not a single one with This has been created and is in use among PA managUser friendly PA data and reports are available fo
    DateAugust 4, 2011December 1, 2016December 30, 2016
    Comment
  • 1.1 The CBF is established with a governance structure and operating rulesValue0CBF Established completelyAchieved: CBF established along with a Secretariat
    DateAugust 4, 2011December 1, 2016January 30, 2014
    Comment
  • 1.2 The CBF is generating investment income for disbursement to NPATFsValue0CBF generating investments at approximately 7-8%Investment income from the CBF capital is availabl
    DateAugust 4, 2011December 1, 2016December 31, 2014
    Comment
  • 1.3 Sustainable financing mechanisms and/or a financial complement provide resources for long term management and use of PAs in each participating country. Target Value: By year 5 at least 3 NPATFs rValueCBF has not provided any funds to NPATFsThe NPATFs have only disbursed pre-financing and hBy year 5 at least 3 countries receive funds from
    DateAugust 4, 2011December 1, 2016December 30, 2016
    Comment
  • 1.4 National sustainable financing plans completed in all participating countries and adopted by at least three Governments.Value2.002.003.00
    DateAugust 4, 2011December 1, 2016December 30, 2016
    Comment
  • 1.5 Each Participating Country adopted/implemented financing mechanisms and/or a financial complement to generate additional resources to at least complement the investment income from the endowment fValue0.004.002.00
    DateAugust 4, 2011December 1, 2016December 30, 2016
    Comment
  • 2.2 Demonstration of good management practices for MPA are implemented in at least two MPAsValue0.002.002.00
    DateAugust 4, 2011December 1, 2016December 30, 2016
    Comment
  • 2.3 Lessons learned from the two demonstration sites are disseminated through workshops, publications and websites among the MPA managers and policy makers in the Project Participating CountriesValueNoneLessons are shared widely from the 2 demonstrationLessons are widely shared within the region
    DateAugust 4, 2011December 1, 2016December 30, 2016
    Comment
  • 3.1 Relevant biodiversity; ecological, economic, and social indicators for effective management of PA network in the Participating Countries are identified and begin to be monitoredValueNoneCompleted- system is established and operational aRegional monitoring and information system is oper
    DateAugust 4, 2011December 1, 2016December 31, 2015
    Comment
  • 3.2 A standardized, web-based information system for housing the data collected is established and made accessible to users in the region through an electronic portalValueNoneDatabases created for all the countries and websitDatabases created in all of the Participating Coun
    DateAugust 4, 2011December 1, 2016December 30, 2016
    Comment
  • Natural resource managers and other key stakeholders apply the regional monitoring and information system outputs to the managementof PA networkValueNoneIncreased usage of data between May-June (More thaUser friendly PA data and reports are available fo
    DateAugust 4, 2011June 14, 2016December 30, 2016
    Comment
  • 4.1 Project staff, including at the national and regional levels, are in place and functioning at all times during the Project withsufficient capacity to carry out all Project activitiesValueRegional level personnel exist with sufficient capCompleteAll personnel are hired to carry out Project activ
    DateAugust 4, 2011December 1, 2014December 31, 2013
    Comment
  • 4.2 Quarterly operational and financial status reports prepared and submitted to the bankValueNoneOperational and financial reports have been submitOperational anf financial reports submitted to the
    DateAugust 4, 2011December 1, 2015March 30, 2012
    Comment