Skip to Main Navigation

Conservancy Adaptation Project

Abstract*

The project development objective of the Conservancy Adaptation Project (CAP) is to reduce the vulnerability of catastrophic flooding in the Guyana low-lying coastal area that is currently threatened by sea level rise resulting from global climate change. This project has been developed to guide a comprehensive upgrading program of the East Demerara Water Conservancy (EDWC) and lowland drainage system, aimed at increasing discharge capacity and improving...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the CAP is to reduce the vulnerability of catastrophic flooding in Guyana's low-lying coastal area that is currently threatened by sea level rise resulting from global climate change.

Key Details

Project Details

  • P103539

  • Closed

  • John Morton

  • N/A

  • Guyana

  • November 29, 2006

  • (as of board presentation)

    October 11, 2007

  • January 28, 2008

  • US$ 3.80 million

  • B

  • Not Applicable

  • August 30, 2013

  • BANK APPROVED

  • July 8, 2015

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 3.80
Borrower/Recipient 1.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 3.80
Total Project Cost** 5.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2013-05-21
Project Management Moderately Satisfactory 2013-05-21
Counterpart Funding Satisfactory 2013-05-21
Overall Safeguards Rating Satisfactory 2013-05-21
Overall Implementation Progress (IP) Satisfactory 2013-05-21
Overall Safeguards Rating Satisfactory 2013-05-21
Summary Global Objective Rating Satisfactory 2013-05-21
Financial Management Satisfactory 2013-05-21
Monitoring and Evaluation Satisfactory 2013-05-21

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-07-2014
Outcomes
Risk to Development OutcomeSubstantial
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-09-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Study findings and priorities work presented by MOA to DonorsValueNo donor meeting heldSeveral donor meetings undertaken.Donor meeting held
    DateNovember 1, 2012March 31, 2013
    Comment
  • Light detection and ranging (LIDAR) data capture of Coastal Lowlands forRegion 3 and 4 completedValueLIDAR not completedData capture completed and DEM under preparation.DEM Created for Region 3 and 4
    DateNovember 1, 2012March 31, 2013
    Comment
  • 1D-2D model developed to identify key drainage regimes and map key interventions to be made within conservancy to improve water flow to the Demerara RiverValueID-2D not developedDraft model developed.Model Calibrated
    DateNovember 1, 2012March 31, 2013
    Comment
  • Measurements taken and dam safety analysis completed to highlight areas in critical need of repairValueMeasurements and safety analysis not completedDam safety study complete, sections in need of rep
    DateAugust 11, 2011March 31, 2013
    Comment
  • Leveling and Bathymetry completedValueMeasurements not takenEDWC reservoir bathymetry completed-
    DateAugust 11, 2011March 31, 2013
    Comment
  • Number of key staff trained in use of Digital Elevation Models, and Flow Models, Monitoring EquipmentValue0.000.0030.00
    DateAugust 11, 2011March 31, 2013
    Comment10 GoG engineers fully trained in use of flow models and engineering equipment
  • Hydraulic engineering foundation, critical for flood control management, developedValueModels and training not completed.Draft hydraulic model completed.Hydraulic model calibrated
    DateNovember 1, 2012March 31, 2013
    Comment
  • Identification of at least 10 key drainage interventions for follow-on actionValueModel not completed and works not identified.Under preparation.10 key drainage interventions identified and pre-e
    DateNovember 1, 2012March 31, 2013
    Comment
  • Contingency Plan developedValueNo Contingency Plan developedContingency Plan updated
    DateAugust 11, 2011March 31, 2013
    Comment
  • Repairs identified at appraisal executed by end of projectValue0.00100.00100.00
    DateAugust 11, 2011March 31, 2013
    Comment
  • Implementation secretariat formed and operationalValueImplementation Secretariat established and operati
    DateMarch 31, 2013
    Comment
  • Kilometer of key canal widened in compliance with national and project prioritiesValueCunha canal project to be pursued as a separate prTBD
    DateNovember 1, 2012March 31, 2013
    Comment
  • Discharge capacity increased of key relief canal from EDWC to Demerara riverValueCunha canal project to be pursued as a separate prIncrease of 30% of discharge capacity
    DateMarch 31, 2013
    Comment
  • Key equipment purchasedValueEquipment purchased.Key equipment purchased
    DateNovember 1, 2012March 31, 2013
    Comment