Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 3.80 |
Borrower/Recipient | 1.20 |
P103539
Closed
John Morton
N/A
November 29, 2006
(as of board presentation)
October 11, 2007
January 28, 2008
US$ 5.00 million
N/A
2008
US$ 3.80 million
B
Not Applicable
August 30, 2013
BANK APPROVED
July 8, 2015
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 3.80 |
Borrower/Recipient | 1.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 3.80 |
Total Project Cost** | 5.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2013-05-21 |
Project Management | Moderately Satisfactory | 2013-05-21 |
Counterpart Funding | Satisfactory | 2013-05-21 |
Overall Safeguards Rating | Satisfactory | 2013-05-21 |
Overall Implementation Progress (IP) | Satisfactory | 2013-05-21 |
Overall Safeguards Rating | Satisfactory | 2013-05-21 |
Summary Global Objective Rating | Satisfactory | 2013-05-21 |
Financial Management | Satisfactory | 2013-05-21 |
Monitoring and Evaluation | Satisfactory | 2013-05-21 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-07-2014 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 03-09-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Study findings and priorities work presented by MOA to Donors | Value | No donor meeting held | Several donor meetings undertaken. | Donor meeting held |
Date | November 1, 2012 | March 31, 2013 | ||
Comment |
Light detection and ranging (LIDAR) data capture of Coastal Lowlands forRegion 3 and 4 completed | Value | LIDAR not completed | Data capture completed and DEM under preparation. | DEM Created for Region 3 and 4 |
Date | November 1, 2012 | March 31, 2013 | ||
Comment |
1D-2D model developed to identify key drainage regimes and map key interventions to be made within conservancy to improve water flow to the Demerara River | Value | ID-2D not developed | Draft model developed. | Model Calibrated |
Date | November 1, 2012 | March 31, 2013 | ||
Comment |
Measurements taken and dam safety analysis completed to highlight areas in critical need of repair | Value | Measurements and safety analysis not completed | Dam safety study complete, sections in need of rep | |
Date | August 11, 2011 | March 31, 2013 | ||
Comment |
Leveling and Bathymetry completed | Value | Measurements not taken | EDWC reservoir bathymetry completed- | |
Date | August 11, 2011 | March 31, 2013 | ||
Comment |
Number of key staff trained in use of Digital Elevation Models, and Flow Models, Monitoring Equipment | Value | 0.00 | 0.00 | 30.00 |
Date | August 11, 2011 | March 31, 2013 | ||
Comment | 10 GoG engineers fully trained in use of flow models and engineering equipment |
Hydraulic engineering foundation, critical for flood control management, developed | Value | Models and training not completed. | Draft hydraulic model completed. | Hydraulic model calibrated |
Date | November 1, 2012 | March 31, 2013 | ||
Comment |
Identification of at least 10 key drainage interventions for follow-on action | Value | Model not completed and works not identified. | Under preparation. | 10 key drainage interventions identified and pre-e |
Date | November 1, 2012 | March 31, 2013 | ||
Comment |
Contingency Plan developed | Value | No Contingency Plan developed | Contingency Plan updated | |
Date | August 11, 2011 | March 31, 2013 | ||
Comment |
Repairs identified at appraisal executed by end of project | Value | 0.00 | 100.00 | 100.00 |
Date | August 11, 2011 | March 31, 2013 | ||
Comment |
Implementation secretariat formed and operational | Value | Implementation Secretariat established and operati | ||
Date | March 31, 2013 | |||
Comment |
Kilometer of key canal widened in compliance with national and project priorities | Value | Cunha canal project to be pursued as a separate pr | TBD | |
Date | November 1, 2012 | March 31, 2013 | ||
Comment |
Discharge capacity increased of key relief canal from EDWC to Demerara river | Value | Cunha canal project to be pursued as a separate pr | Increase of 30% of discharge capacity | |
Date | March 31, 2013 | |||
Comment |
Key equipment purchased | Value | Equipment purchased. | Key equipment purchased | |
Date | November 1, 2012 | March 31, 2013 | ||
Comment |