Pontianak - LFG Recovery Project

Abstract*

The project development objective is to reduce methane emissions from solid waste disposed in the Tempat Pembuangan Akhir (TPA) Batu Layang landfill in Pontianak, Indonesia through a carbon finance transaction between the World Bank-managed The Netherlands Clean Development Facility (NCDMF) and the project sponsor. There are two components to the project. The first component of the project is Landfill Gas (LFG) project. The first activity will consist...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to reduce methane emissions from solid waste disposed in TPA Batu Layang landfill Pontianak, through a carbon finance transaction between the World Bank-managed NCDMF and the project sponsor, Gikoko.

Key Details

Project Details

  • P104482

  • Closed

  • Ina Pranoto

  • N/A

  • Indonesia

  • May 29, 2007

  • (as of board presentation)

    June 15, 2007

  • N/A

  • US$ 3.86 million

  • N/A

  • Not Applicable

  • July 1, 2013

  • BANK APPROVED

  • December 19, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
PROTOTYPE CARBON FUND 3.86

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 3.86
Total Project Cost** 3.86

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2012-04-02
Progress towards achievement of PDO Unsatisfactory 2012-04-02
Counterpart Funding Satisfactory 2012-04-02
Overall Implementation Progress (IP) Unsatisfactory 2012-04-02
Monitoring and Evaluation Moderately Satisfactory 2012-04-02

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Emission ReductionsValue0.000.00250000.00
    DateJune 14, 2007December 31, 2012
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Annual Emission Reduction ScheduleValue0.000.002500000.00
    DateJune 14, 2007December 31, 2012
    Comment