DRC Emergency Urban and Social Rehabilitation Project

Development Objective

To respond to urgent challenges by: (i) supporting domestic debt settlement; and (ii) addressing urgent rehabilitation and social needs in targeted areas.

Key Details

Project Details

  • P104497

  • Closed

  • Mahine Diop

  • N/A

  • US$ 180.00 million

  • B

  • Not Applicable

  • May 31, 2013

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 180.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 180.00
IBRD + IDA Commitment 180.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 180.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 29, 2007 IDA-H2820 Loan Commitment 180,000,000.00
Oct 4, 2013 IDA-H5960 Loan Disb -188,455.64
Oct 4, 2013 IDA-H2820 Loan Disb 120,890.85
Dec 6, 2013 IDA-H5960 Loan Cancel 23,472,948.00
Sep 12, 2013 IDA-H5960 Loan Disb -24,696.12
Nov 26, 2013 IDA-H2820 Loan Disb -344.30
Sep 6, 2013 IDA-H2820 Loan Disb 537,228.90
Jul 18, 2013 IDA-H2820 Loan Disb 39,776.10
Aug 20, 2013 IDA-H2820 Loan Disb 639,437.50
Jun 10, 2013 IDA-H5960 Loan Disb -462,842.12
Jul 9, 2013 IDA-H2820 Loan Disb 671,171.80
Nov 26, 2013 IDA-H2820 Loan Disb -0.02
Nov 26, 2013 IDA-H2820 Loan Cancel 3,712,117.50
Nov 26, 2013 IDA-H5960 Loan Disb -4,115,499.80
Nov 26, 2013 IDA-H5960 Loan Disb -121,377.49
Nov 26, 2013 IDA-H2820 Loan Disb -1,623.13
Oct 4, 2013 IDA-H2820 Loan Disb -164,246.19
Jun 18, 2010 IDA-H5960 Loan Commitment 40,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2013-02-10
Monitoring and Evaluation Satisfactory 2013-02-10
Overall Implementation Progress (IP) Moderately Satisfactory 2013-02-10
Procurement Satisfactory 2013-02-10
Counterpart Funding Satisfactory 2013-02-10
Project Management Satisfactory 2013-02-10
Financial Management Moderately Satisfactory 2013-02-10

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 11-28-2013
Outcomes
Risk to Development OutcomeSubstantial
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-29-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualityExemplaryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Children under 5 years old sleeping under bed nets in KinshasaValue32.0064.7060.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    CommentTarget exceeded
  • Children under 5 years old sleeping under bed nets in BandunduValue20.0020.0060.00
    DateMay 31, 2010January 14, 2013May 31, 2013
    CommentDistribution of 2,800,000 bed nets completed and surveys are ongoing.
  • Number of people in urban areas provided with access to Improved Water Sources under the projectValue0.0089000.00239000.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    CommentThe newly rehabilitated network is not yet operational.
  • Number of people in urban areas provided with access to all-season roads within a 500 meter range under the projectValue0.00940000.00800000.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    CommentWorks for 13 kms of urban roads are underway.
  • Direct project beneficiariesValue0.0021.6121.61
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    CommentMeasured in millions.With the distribution of bed nets in the Bandundu province project beneficiaries has increased.Measured in millions. Estimated as persons protected by bed nets (2 per bednet) in Kinshasa and Bandundu provinces, plus thenumber of children in primary and secondary schools in DRC, excluding Kinshasa and Bandundu Provinces (source: Statistics report,2007/08, MEPSP)
  • Children under 5 years old sleeping under bed nets in targeted areas.Value0.000.000.00
    Date
    CommentPlease see sub indicatorPlease see sub indicator
  • Schools receiving payments that have improved their learning environment (basic school supplies, small equipment and repairs, otherpedagogical inputs)Value0.0099.0070.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    CommentTarget exceeded
  • Creditors party to the amended settlement having received the full payment.Value0.0099.5095.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    CommentTarget exceeded.
  • Female beneficiariesValue51.8051.8051.80
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    CommentEstimated as persons protected by bed nets (2 per bednet) in Kinshasa and Bandundu provinces, plus the number of children inprimary and secondary schools in DRC, excluding Kinshasa and Bandundu Provinces (source: Statistics report, 2007/08, MEPSP)

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Long-lasting insecticide-treated malaria nets purchased and/or distributed (number)Value0.004781851.004500000.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    Comment2,800,000 have been distributed under the additional financing and surveys are underway.
  • Roads rehabilitated, Non-ruralValue0.0017.0040.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    Comment22 km of road works underway.
  • New piped household water connections that are resulting from the project interventionValue0.00949.008300.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    CommentWorks are underway.
  • Improved community water points constructed or rehabilitated under the projectValue0.0087.0089.00
    DateSeptember 27, 2007January 14, 2013May 31, 2013
    Comment87 connected to the water network.
  • Primary, secondary and tertiary piped network constructed or rehabilitatedValue0.0075.00140.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    Commentworks underway
  • Eligible schools having received all installmentsValue0.0099.0070.00
    DateSeptember 28, 2007January 14, 2013May 31, 2013
    CommentTarget exceeded for the initial project.