Financier | Commitments |
---|---|
IDA Grant | 180.00 |
P104497
Closed
Mahine Diop
N/A
March 5, 2007
(as of board presentation)
March 29, 2007
July 6, 2007
US$ 180.00 million
N/A
2007
US$ 180.00 million
B
Not Applicable
May 31, 2013
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
IDA Grant | 180.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 180.00 |
IBRD + IDA Commitment | 180.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 180.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 29, 2007 | IDA-H2820 | Loan Commitment | 180,000,000.00 |
Oct 4, 2013 | IDA-H5960 | Loan Disb | -188,455.64 |
Oct 4, 2013 | IDA-H2820 | Loan Disb | 120,890.85 |
Dec 6, 2013 | IDA-H5960 | Loan Cancel | 23,472,948.00 |
Sep 12, 2013 | IDA-H5960 | Loan Disb | -24,696.12 |
Nov 26, 2013 | IDA-H2820 | Loan Disb | -344.30 |
Sep 6, 2013 | IDA-H2820 | Loan Disb | 537,228.90 |
Jul 18, 2013 | IDA-H2820 | Loan Disb | 39,776.10 |
Aug 20, 2013 | IDA-H2820 | Loan Disb | 639,437.50 |
Jun 10, 2013 | IDA-H5960 | Loan Disb | -462,842.12 |
Jul 9, 2013 | IDA-H2820 | Loan Disb | 671,171.80 |
Nov 26, 2013 | IDA-H2820 | Loan Disb | -0.02 |
Nov 26, 2013 | IDA-H2820 | Loan Cancel | 3,712,117.50 |
Nov 26, 2013 | IDA-H5960 | Loan Disb | -4,115,499.80 |
Nov 26, 2013 | IDA-H5960 | Loan Disb | -121,377.49 |
Nov 26, 2013 | IDA-H2820 | Loan Disb | -1,623.13 |
Oct 4, 2013 | IDA-H2820 | Loan Disb | -164,246.19 |
Jun 18, 2010 | IDA-H5960 | Loan Commitment | 40,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2013-02-10 |
Monitoring and Evaluation | Satisfactory | 2013-02-10 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2013-02-10 |
Procurement | Satisfactory | 2013-02-10 |
Counterpart Funding | Satisfactory | 2013-02-10 |
Project Management | Satisfactory | 2013-02-10 |
Financial Management | Moderately Satisfactory | 2013-02-10 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-28-2013 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 07-29-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Exemplary | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Children under 5 years old sleeping under bed nets in Kinshasa | Value | 32.00 | 64.70 | 60.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | Target exceeded |
Children under 5 years old sleeping under bed nets in Bandundu | Value | 20.00 | 20.00 | 60.00 |
Date | May 31, 2010 | January 14, 2013 | May 31, 2013 | |
Comment | Distribution of 2,800,000 bed nets completed and surveys are ongoing. |
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 89000.00 | 239000.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | The newly rehabilitated network is not yet operational. |
Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project | Value | 0.00 | 940000.00 | 800000.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | Works for 13 kms of urban roads are underway. |
Direct project beneficiaries | Value | 0.00 | 21.61 | 21.61 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | Measured in millions. | With the distribution of bed nets in the Bandundu province project beneficiaries has increased. | Measured in millions. Estimated as persons protected by bed nets (2 per bednet) in Kinshasa and Bandundu provinces, plus thenumber of children in primary and secondary schools in DRC, excluding Kinshasa and Bandundu Provinces (source: Statistics report,2007/08, MEPSP) |
Children under 5 years old sleeping under bed nets in targeted areas. | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment | Please see sub indicator | Please see sub indicator |
Schools receiving payments that have improved their learning environment (basic school supplies, small equipment and repairs, otherpedagogical inputs) | Value | 0.00 | 99.00 | 70.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | Target exceeded |
Creditors party to the amended settlement having received the full payment. | Value | 0.00 | 99.50 | 95.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | Target exceeded. |
Female beneficiaries | Value | 51.80 | 51.80 | 51.80 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | Estimated as persons protected by bed nets (2 per bednet) in Kinshasa and Bandundu provinces, plus the number of children inprimary and secondary schools in DRC, excluding Kinshasa and Bandundu Provinces (source: Statistics report, 2007/08, MEPSP) |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Long-lasting insecticide-treated malaria nets purchased and/or distributed (number) | Value | 0.00 | 4781851.00 | 4500000.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | 2,800,000 have been distributed under the additional financing and surveys are underway. |
Roads rehabilitated, Non-rural | Value | 0.00 | 17.00 | 40.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | 22 km of road works underway. |
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 949.00 | 8300.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | Works are underway. |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 87.00 | 89.00 |
Date | September 27, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | 87 connected to the water network. |
Primary, secondary and tertiary piped network constructed or rehabilitated | Value | 0.00 | 75.00 | 140.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | works underway |
Eligible schools having received all installments | Value | 0.00 | 99.00 | 70.00 |
Date | September 28, 2007 | January 14, 2013 | May 31, 2013 | |
Comment | Target exceeded for the initial project. |