Skip to Main Navigation

PE Sierra Irrigation Subsector

Abstract*

The objective of the Sierra Irrigation Project for Peru is to contribute to increasing agricultural production and productivity in targeted areas of the Sierra. There are five components to the project, the first component being modernization and rehabilitation of collective irrigation. This component will finance pre-investment studies and design, execution and supervision of subprojects to support eligible Water Users' Organization (WUO) to improve...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to contribute to increasing agricultural production and productivity in targeted areas of the Sierra.

Key Details

Project Details

  • P104760

  • Closed

  • Marie-Laure Lajaunie , Griselle Vega

  • Ministerio de Economia y Finanzas - MEF

  • Peru

  • April 11, 2007

  • (as of board presentation)

    July 27, 2010

  • February 15, 2011

  • US$ 48.33 million

  • Ministry of Agriculture through Programa Subsectorial de Irrigacion (PSI),Autoridad Nacional del Agua, Ministry of Agriculture

  • Latin America and Caribbean

  • 2011

  • US$ 20.00 million

  • B

  • November 14, 2022

  • December 31, 2016

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 24.00
Local Farmer Organizations 4.33
International Bank for Reconstruction and Development 20.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 20.00
IDA Commitment N/A
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 48.33

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 21, 2015 IBRD-78780 Loan Disb 638,969.06
Jan 28, 2016 IBRD-78780 Loan Disb 404,287.22
Oct 23, 2015 IBRD-78780 Loan Disb 602,744.00
Apr 19, 2016 IBRD-78780 Loan Disb 501,596.22
Oct 16, 2014 IBRD-78780 Loan Disb 406,318.70
Oct 28, 2014 IBRD-78780 Loan Disb 403,829.78
Aug 29, 2013 IBRD-78780 Loan Disb 574,587.50
Dec 9, 2014 IBRD-78780 Loan Disb 449,860.94
Dec 9, 2014 IBRD-78780 Loan Disb 514,799.44
Jul 9, 2013 IBRD-78780 Loan Disb 479,485.75
Dec 15, 2013 IBRD-78780 Int Charges 28,606.19
Oct 31, 2013 IBRD-78780 Loan Disb 320,320.28
Feb 18, 2014 IBRD-78780 Loan Disb 493,056.25
Dec 5, 2013 IBRD-78780 Loan Disb 776,687.70
Jun 15, 2014 IBRD-78780 Int Charges 536.05
Jun 15, 2014 IBRD-78780 Int Charges 34,043.78
May 28, 2014 IBRD-78780 Loan Disb 550,561.10
Mar 25, 2014 IBRD-78780 Loan Disb 294,811.12
Dec 18, 2014 IBRD-78780 Loan Disb 438,532.47
Dec 18, 2014 IBRD-78780 Loan Disb 429,642.72
Dec 17, 2014 IBRD-78780 Loan Disb 516,485.75
Jun 15, 2023 IBRD-78780 Int Charges 25,501.77
Jun 15, 2024 IBRD-78780 Int Charges 3,963.24
Jun 15, 2024 IBRD-78780 Int Charges 657,997.44
Jul 27, 2010 IBRD-78780 Loan Commitment 20,000,000.00
Dec 15, 2019 IBRD-78780 Int Charges 305,995.62
Jun 15, 2020 IBRD-78780 Int Charges 261,413.47
Dec 15, 2020 IBRD-78780 Int Charges 112,468.58
Jun 15, 2021 IBRD-78780 Int Charges 95,730.90
Jun 15, 2022 IBRD-78780 Int Charges 103,792.43
Dec 15, 2021 IBRD-78780 Int Charges 89,164.28
Dec 15, 2022 IBRD-78780 Int Charges 369,725.44
Sep 13, 2016 IBRD-78780 Loan Disb -0.07
Aug 8, 2016 IBRD-78780 Loan Disb 511,602.00
Jun 15, 2016 IBRD-78780 Int Charges 1,666.46
Jun 15, 2016 IBRD-78780 Int Charges 123,363.35
Sep 13, 2016 IBRD-78780 Loan Disb 211,784.84
Dec 15, 2016 IBRD-78780 Int Charges 1,032.46
Dec 15, 2016 IBRD-78780 Int Charges 151,558.40
Jun 15, 2017 IBRD-78780 Loan Disb -30,409.83
Jun 23, 2017 IBRD-78780 Loan Disb -15,750.92
Jun 15, 2017 IBRD-78780 Int Charges 193,122.22
Jun 23, 2017 IBRD-78780 Loan Disb -21,435.82
Jun 23, 2017 IBRD-78780 Loan Cancel 67,596.64
Dec 15, 2017 IBRD-78780 Int Charges 209,755.81
Jun 15, 2018 IBRD-78780 Int Charges 243,861.88
Dec 15, 2018 IBRD-78780 Int Charges 321,194.06
Jun 15, 2019 IBRD-78780 Int Charges 361,762.06
Dec 15, 2014 IBRD-78780 Int Charges 38,850.55
Mar 27, 2015 IBRD-78780 Loan Disb 893,440.40
Sep 2, 2014 IBRD-78780 Loan Disb 830,905.70
Jun 15, 2015 IBRD-78780 Int Charges 1,087.37
Jun 15, 2015 IBRD-78780 Int Charges 57,607.07
Apr 29, 2015 IBRD-78780 Loan Disb 628,150.50
Aug 21, 2015 IBRD-78780 Loan Disb 420,548.50
Aug 3, 2015 IBRD-78780 Loan Disb 480,437.90
Dec 18, 2015 IBRD-78780 Loan Disb 607,779.94
Dec 15, 2015 IBRD-78780 Int Charges 688.88
Dec 15, 2015 IBRD-78780 Int Charges 77,065.30
Nov 12, 2015 IBRD-78780 Loan Disb 906,149.50
Dec 15, 2014 IBRD-78780 Int Charges 222.97
Dec 15, 2023 IBRD-78780 Int Charges 0.01
Dec 15, 2023 IBRD-78780 Int Charges 10,600.06
Dec 15, 2023 IBRD-78780 Int Charges 620,506.94
Jun 15, 2023 IBRD-78780 Int Charges 541,234.25

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2016-12-30
Progress towards achievement of PDO Satisfactory 2016-12-30
Financial Management Satisfactory 2016-12-30
Monitoring and Evaluation Satisfactory 2016-12-30
Overall Implementation Progress (IP) Satisfactory 2016-12-30
Counterpart Funding Satisfactory 2016-12-30
Project Management Satisfactory 2016-12-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2017
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-15-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of WUAs that satisfactorily implement the O&M plans of the irrigation and drainage systems modernized or rehabilitated by the ProjectValue0.0012.007.00
    DateJuly 27, 2010December 19, 2016December 31, 2016
    Comment
  • % of producers' groups supported by the Project that have satisfactorily implemented their business planValue0.0080.0080.00
    DateJuly 27, 2010December 19, 2016December 31, 2016
    Comment
  • % of Water Users Organizations that benefited from Component A that are implementing satisfactorily their O&M plan.Value0.0079.0060.00
    DateJune 14, 2010December 19, 2016December 31, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of WUOs that have benefited from collective I&D infrastructure improved/rehabilitated by the Project.Value0.0012.009.00
    DateJuly 27, 2010May 17, 2016December 31, 2016
    Comment
  • Number of water users that have benefited from the modernization or rehabilitation of collective I&D infrastructure by the ProjectValue0.0018758.0018785.00
    DateJune 1, 2010December 19, 2016December 31, 2016
    Comment
  • Area (ha) that benefited from the modernization/rehabiliation of collective infrastructure carried out by the ProjectValue0.0014770.0014770.00
    DateJune 1, 2010December 19, 2016December 31, 2016
    Comment
  • Number of WUAs in which O&M plans for I&D infrastructure modernized/rehabilitated by the Project have been formulatedValue0.0012.0010.00
    DateJune 1, 2010December 19, 2016December 31, 2016
    Comment
  • Producers that benefited from improved on-farm irrigation management carried out by the ProjectValue0.001684.001000.00
    DateJune 1, 2010December 19, 2016December 31, 2016
    Comment
  • Area that benefited from improved on-farm irrigation management carried out by the ProjectValue0.001969.001500.00
    DateJune 1, 2010December 19, 2016December 31, 2016
    Comment
  • Percentage of producers' groups that satisfactorily operate the improved on-farm irrigation systemsValue0.0080.0080.00
    DateJune 1, 2010December 19, 2016December 31, 2016
    Comment
  • Producer groups that have formulated a business plan according to Project guidelinesValue0.00268.00100.00
    DateJuly 27, 2010December 19, 2016December 31, 2016
    Comment
  • Number of water licenses issuedValue0.002700.003000.00
    DateJuly 27, 2010December 19, 2016December 31, 2016
    Comment
  • Number of water licenses registeredValue0.002700.002700.00
    DateJuly 27, 2010December 19, 2016December 31, 2016
    Comment
  • Number of water measuring devices installedValue0.00263.00250.00
    DateJune 1, 2010December 19, 2016December 31, 2016
    Comment
  • Area provided with irrigation and drainage services (ha)Value0.0016739.0016739.00
    DateMay 10, 2010December 19, 2016December 31, 2016
    Comment
  • Operational water user associations created and/or strengthened (number)Value0.0075.0075.00
    DateJune 14, 2010December 19, 2016December 31, 2016
    Comment
  • Water users provided with new/improved irrigation and drainage services (number)Value0.0020442.0020442.00
    DateJune 14, 2010December 19, 2016December 31, 2016
    Comment
  • Area provided with irrigation and drainage services - Improved (ha)Value0.0016739.0016793.00
    DateMay 10, 2010December 19, 2016December 31, 2016
    Comment
  • Water users provided with irrigation and drainage services - female (number)Value0.008082.008000.00
    DateJune 14, 2010December 19, 2016December 31, 2016
    Comment