Health Sector Strategic Plan Support Project

Abstract*

The overall objective of the Health Sector Strategic Plan Support Project (HSSP-SP) is to improve the quality and coverage of preventive and curative health services, particularly for women and children, in order to accelerate progress toward the health Millennium Development Goals (MDGs). The HSSP-SP will have two parts (a) direct financial support based on the Health Sector Strategic Plan and Medium Term Expenditure Framework (MTEF) and (b) addressing...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The revised PDO is to support Government of Timor-Leste to get more resources to where they are needed most to improve the deliveryof health services in districts and subdistricts.

Key Details

Project Details

  • P104794

  • Closed

  • Eileen Brainne Sullivan

  • Ministry of Finance

  • Timor-Leste

  • March 30, 2007

  • (as of board presentation)

    December 13, 2007

  • March 25, 2008

  • US$ 8.13 million

  • Ministry of Health,The World Bank Group

  • East Asia and Pacific

  • 2008

  • US$ 8.13 million

  • C

  • October 16, 2023

  • June 15, 2015

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 1.20
IDA Credit 6.93

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 1.20
IDA Commitment 6.93
IBRD + IDA Commitment 8.13
Lending Instrument
Grant Amount N/A
Total Project Cost** 8.13

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 4, 2013 IDA-H3430 Loan Disb 20,524.97
Dec 13, 2007 IDA-H3430 Loan Commitment 1,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2015-06-07
Project Management Moderately Unsatisfactory 2015-06-07
Financial Management Moderately Unsatisfactory 2015-06-07
Monitoring and Evaluation Moderately Satisfactory 2015-06-07
Procurement Moderately Satisfactory 2015-06-07
Overall Implementation Progress (IP) Moderately Unsatisfactory 2015-06-07

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-17-2015
Outcomes
Risk to Development OutcomeModerately Satisfactory
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-15-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • No. of budget divisions receiving advances per quarter and who acquit w/n 30 days following end of calendar quarter(National Hospital not included)Value9.5018.0018.00
    DateJune 30, 2014May 22, 2015June 15, 2015
    Comment
  • Management of expiry dates leads to reduction of expired medicine at warehouseValue7.204.6010.00
    DateJuly 1, 2014May 22, 2015June 15, 2015
    Comment
  • Joint annual sector review and planning meetings held as planned (at least 1/year)ValueNoYesYes
    DateDecember 31, 2012May 22, 2015June 15, 2015
    Comment
  • Number of districts that have undertaken a facility readiness surveyValue3.0013.0013.00
    DateJune 30, 2014May 22, 2015June 15, 2015
    Comment
  • Percentage of district health posts having undertaken Readiness Assessment scoring =>80%Value0.003.0010.00
    DateApril 30, 2014May 22, 2015June 15, 2015
    Comment
  • Percentage of district Community Health Centers undertaking Readiness Assessment scoring =>80%Value0.0025.0050.00
    DateApril 30, 2014May 22, 2015June 15, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Amount of Dept Pharmacy procurement activities using direct contracting (sole source) in $ value from October 2013 to date.Value182845.00182845.000.00
    DateJune 30, 2014May 22, 2015June 15, 2015
    Comment
  • Number of structured sector coordination meetings held to progress toward one plan, one budget, and one sector M&E frameworkValue0.002.002.00
    DateDecember 31, 2012May 22, 2015June 15, 2015
    Comment
  • Percentage of targeted staff who pass competency test in the 7 PFM areas organized by the MOFValue0.000.0050.00
    DateJuly 31, 2014May 22, 2015June 15, 2015
    Comment
  • Percentage of stock-outs of tracer essential drugs at SAMESValue19.0033.0015.00
    DateDecember 31, 2012May 22, 2015June 15, 2015
    Comment
  • Percentage of SAMES’ procurement activities using direct contracting (emergency order, in $ value) from Nov 2011 to Oct 2013.Value47.000.000.00
    DateDecember 31, 2012May 22, 2015June 15, 2015
    Comment
  • Number of districts and hospitals with functional National Logistics Management Information SystemValue0.000.0015.00
    DateJuly 31, 2014May 22, 2015June 15, 2015
    Comment
  • A computerized drug registration system availableValueNo computerized systemPartialFunctional system available
    DateDecember 31, 2012May 22, 2015June 15, 2015
    Comment
  • Number of districts implementing supportive supervisionValue3.0013.0013.00
    DateJuly 31, 2014May 22, 2015June 15, 2015
    Comment
  • Percentage of rejected Commitment Payment Vouchers on a quarterly basisValue7.007.555.00
    DateAugust 31, 2014May 22, 2015June 15, 2015
    Comment
  • Number of pilots with functional mSupply/mobile mSupply by 2015Value0.002.003.00
    DateJuly 31, 2014May 22, 2015June 15, 2015
    Comment