Ho Chi Minh City Investment Fund for Urban Development Project

Abstract*

The project aims to develop Ho Chi Minh City Investment Fund for Urban (HIFU) Development as a model Local Development Investment Fund LDIF (in terms of internal policy and procedures for financial policy, sub-project appraisal, social and environmental safeguards, and partnership with the private sector) and increase private sector participation in financing municipal infrastructure in Ho Chi Minh City. There are 2 components to the project. Component...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To develop HIFU as a model LDIF (in terms of internal policy and procedures for financial policy, sub-project appraisal, social and environmental safeguards, and partnership with the private sector) and increase private sector participation in financing municipal infrastructure in HCMC

Key Details

Project Details

  • P104848

  • Closed

  • Phan Huyen

  • N/A

  • Viet Nam

  • April 5, 2007

  • (as of board presentation)

    June 20, 2007

  • March 14, 2008

  • US$ 50.00 million

  • F

  • Not Applicable

  • December 31, 2012

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 30.50
IDA Credit 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 50.00
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 80.50

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 2016 IDA-43290 Int Charges 157,409.33
Jun 15, 2017 IDA-43290 Int Charges 155,051.67
Jun 15, 2017 IDA-43290 Int Charges 155,051.67
Jun 15, 2017 IDA-43290 Int Charges 4,567.65
Jun 15, 2017 IDA-43290 Int Charges 4,567.65
Dec 15, 2017 IDA-43290 Int Charges 2,837.83
Dec 15, 2017 IDA-43290 Loan Repay 443,030.44
Dec 15, 2017 IDA-43290 Int Charges 166,136.40
Dec 15, 2014 IDA-43290 Int Charges 170,691.02
Dec 15, 2014 IDA-43290 Int Charges 170,691.02
Jun 15, 2015 IDA-43290 Int Charges 2,696.38
Jun 15, 2015 IDA-43290 Int Charges 2,696.38
Jun 15, 2015 IDA-43290 Int Charges 158,570.12
Jun 15, 2015 IDA-43290 Int Charges 158,570.12
Dec 15, 2015 IDA-43290 Int Charges 3,706.86
Dec 15, 2015 IDA-43290 Int Charges 3,706.86
Dec 15, 2015 IDA-43290 Int Charges 163,759.61
Dec 15, 2015 IDA-43290 Int Charges 163,759.61
Jun 15, 2016 IDA-43290 Int Charges 2,894.37
Jun 15, 2016 IDA-43290 Int Charges 2,894.37
Jun 15, 2016 IDA-43290 Int Charges 162,246.90
Jun 15, 2016 IDA-43290 Int Charges 162,246.90
Dec 15, 2013 IDA-43290 Int Charges 1,295.04
Dec 15, 2013 IDA-43290 Int Charges 1,295.04
Dec 15, 2013 IDA-43290 Int Charges 179,753.83
Dec 15, 2013 IDA-43290 Int Charges 179,753.83
Jun 15, 2014 IDA-43290 Int Charges 929.89
Jun 15, 2014 IDA-43290 Int Charges 929.89
Jun 15, 2014 IDA-43290 Int Charges 180,876.56
Jun 15, 2014 IDA-43290 Int Charges 180,876.56
Dec 15, 2014 IDA-43290 Int Charges 1,006.15
Dec 15, 2014 IDA-43290 Int Charges 1,006.15
Jun 15, 2024 IDA-43290 Int Charges 22,003.04
Jun 15, 2024 IDA-43290 Int Charges 22,003.04
Jun 15, 2024 IDA-43290 Loan Repay 825,630.80
Jun 15, 2024 IDA-43290 Int Charges 126,016.16
Jun 15, 2024 IDA-43290 Int Charges 126,016.16
Jun 20, 2007 IDA-43290 Loan Commitment 50,000,000.00
Dec 15, 2021 IDA-43290 Int Charges 150,951.77
Dec 15, 2021 IDA-43290 Int Charges 150,951.77
Dec 15, 2021 IDA-43290 Int Charges 4,414.97
Dec 15, 2021 IDA-43290 Int Charges 4,414.97
Dec 15, 2021 IDA-43290 Loan Repay 875,082.75
Dec 15, 2022 IDA-43290 Loan Repay 25,324.58
Dec 15, 2022 IDA-43290 Loan Repay 808,571.20
Dec 15, 2022 IDA-43290 Int Charges 97,946.63
Dec 15, 2022 IDA-43290 Int Charges 97,946.63
Dec 15, 2023 IDA-43290 Loan Repay 15,118.49
Dec 15, 2023 IDA-43290 Loan Repay 825,030.80
Dec 15, 2023 IDA-43290 Int Charges 109,933.54
Dec 15, 2023 IDA-43290 Int Charges 109,933.54
Jun 15, 2023 IDA-43290 Int Charges 39,759.99
Jun 15, 2023 IDA-43290 Int Charges 39,759.99
Jun 15, 2023 IDA-43290 Loan Repay 836,289.44
Jun 15, 2023 IDA-43290 Int Charges 134,851.66
Jun 15, 2023 IDA-43290 Int Charges 134,851.66
Dec 15, 2020 IDA-43290 Int Charges 5,698.18
Dec 15, 2020 IDA-43290 Int Charges 5,698.18
Dec 15, 2020 IDA-43290 Loan Repay 450,524.66
Dec 15, 2020 IDA-43290 Int Charges 147,492.84
Dec 15, 2020 IDA-43290 Int Charges 147,492.84
Jun 15, 2021 IDA-43290 Loan Repay 450,897.50
Jun 15, 2021 IDA-43290 Int Charges 152,700.80
Jun 15, 2021 IDA-43290 Int Charges 152,700.80
Jun 15, 2021 IDA-43290 Int Charges 11,326.45
Jun 15, 2021 IDA-43290 Int Charges 11,326.45
Jun 15, 2022 IDA-43290 Loan Repay 823,209.94
Jun 15, 2022 IDA-43290 Int Charges 140,826.73
Jun 15, 2022 IDA-43290 Int Charges 140,826.73
Jun 15, 2022 IDA-43290 Loan Repay 11,318.75
Jun 15, 2019 IDA-43290 Loan Repay 425,322.20
Jun 15, 2019 IDA-43290 Int Charges 157,650.23
Jun 15, 2019 IDA-43290 Int Charges 157,650.23
Jun 15, 2019 IDA-43290 Loan Repay 8,080.43
Dec 15, 2019 IDA-43290 Loan Repay 3,067.78
Dec 15, 2019 IDA-43290 Loan Repay 430,572.94
Dec 15, 2019 IDA-43290 Int Charges 150,418.06
Dec 15, 2019 IDA-43290 Int Charges 150,418.06
Jun 15, 2020 IDA-43290 Int Charges 148,489.62
Jun 15, 2020 IDA-43290 Int Charges 148,489.62
Jun 15, 2020 IDA-43290 Int Charges 5,673.10
Jun 15, 2020 IDA-43290 Int Charges 5,673.10
Jun 15, 2020 IDA-43290 Loan Repay 432,155.66
Dec 15, 2017 IDA-43290 Int Charges 166,136.40
Dec 15, 2017 IDA-43290 Int Charges 2,837.83
Jun 15, 2018 IDA-43290 Int Charges 164,124.98
Jun 15, 2018 IDA-43290 Int Charges 164,124.98
Jun 15, 2018 IDA-43290 Loan Repay 307.30
Dec 15, 2018 IDA-43290 Loan Repay 413,410.34
Dec 15, 2018 IDA-43290 Int Charges 158,775.75
Dec 15, 2018 IDA-43290 Int Charges 158,775.75
Jun 15, 2018 IDA-43290 Loan Repay 441,780.10
Dec 15, 2018 IDA-43290 Loan Repay 18,632.53
Dec 15, 2016 IDA-43290 Int Charges 69.40
Dec 15, 2016 IDA-43290 Int Charges 69.40
Dec 15, 2016 IDA-43290 Int Charges 157,409.33

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2012-12-26
Progress towards achievement of PDO Satisfactory 2012-12-26
Procurement Satisfactory 2012-12-26
Financial Management Satisfactory 2012-12-26
Monitoring and Evaluation Satisfactory 2012-12-26
Overall Implementation Progress (IP) Moderately Satisfactory 2012-12-26
Counterpart Funding Satisfactory 2012-12-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2013
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-30-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Total number of HFIC investment (including both debt and equity) per year in municipal infrastructure projects with private sector involvement.Value1 (debt)plus 9 new investments(7 debt and 2 equity)3 (debt) annual target
    DateJune 20, 2007October 31, 2012December 31, 2012
    Comment- PAD defined the total accumulative target: 11-15 investments- The total accumulative achievement to date: 35 investments (27debts and 8 direct)Annual target
  • Total amount of HFIC investment (including both debt and equity) per year in municipal infrastructure projects with private sector involvement.Value$4 million (debt)$15.6 milliondebt: $10.02 million equity: $5.58 $17 million (debt) annual target
    DateJune 20, 2007October 31, 2012December 31, 2012
    Comment- PAD defined the total accumulative target: US$49.5 - 77 million- The total accumulative achievement to date: US$128.5 million($118.51million debts and $9.99 million direct)Annual target
  • Improvement in private capital leveraged in municipal infrastructure projects per year (private capital in project / HFIC investment in project).ValueNA2.01.0x
    DateJune 20, 2007October 31, 2012December 31, 2012
    CommentThis target for this indicator was revised since HIFU was reformed to be HFIC and increase the State capital invested through HFIC
  • Continued compliance with the Financial CovenantsValueFull complianceFull complianceFull compliance
    DateJune 20, 2007October 31, 2012December 31, 2012
    Comment
  • Percentage of HFIC projects processed in accordance with the PPA manual guidelines.Value0%100%100%
    DateJune 20, 2007October 31, 2012December 31, 2012
    Comment
  • Percentage of Private Sector Partners of HFIC selected using the PSP manual guidelines, if there is equity investment by HFIC.Value0 %NA (no equity investment under HDP )
    DateJune 20, 2007October 31, 2012December 31, 2012
    CommentPSP manual is implemented in a phased manner, if there is equity investment by HFIC: Process is operational for early evaluations,if potential equity-investment opportunity arose.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of new investments (including both debt and equity) undertaken by HFIC with the LOC.Value06 (debt)2 (debt) annual target
    DateJune 20, 2007October 31, 2012December 31, 2012
    Comment- PAD defined the total accumulative target: 11 investments- The total accumulative achievement to date: 12 investmentsAnnual target
  • Amount of new investments (including both debt and equity) undertaken by HFIC with the LOC.Value0$9.83 million (debt)
    DateOctober 31, 2012
    Comment- PAD defined the total accumulative target: US$50- 77 million- The total accumulative achievement to date: US$104.9 million
  • Projects feasibility studies meet adequate quality standards.ValueProject owners manage project preparation and qual100% Compliance100% Compliance
    DateJune 20, 2007October 31, 2012December 31, 2012
    Comment
  • Level of compliance of projects with Environment and Social Safeguards.ValueNone100% Compliance
    DateOctober 31, 2012
    Comment
  • PSP manual is implemented in a phased manner, if there is equity investment by HFIC.ValueProvisions of the PSP Manual are new to HFICSelection process is operational for any early evaSelection process is operational for any early eva
    DateJune 20, 2007October 31, 2012December 31, 2012
    Comment