Financier | Commitments |
---|---|
Borrower/Recipient | 135.98 |
Carbon Fund | 2.90 |
P105152
Dropped
Rohit Mittal
N/A
November 28, 2007
(as of board presentation)
May 28, 2010
May 31, 2010
US$ 138.88 million
N/A
2014
US$ 2.90 million
N/A
Not Applicable
December 31, 2018
BEGIN NEGOTIATION
December 19, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 135.98 |
Carbon Fund | 2.90 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 2.90 |
Total Project Cost** | 138.88 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2012-06-26 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2012-06-26 |
Counterpart Funding | Satisfactory | 2012-06-26 |
Project Management | Satisfactory | 2012-06-26 |
Monitoring and Evaluation | Satisfactory | 2012-06-26 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Certified Emission Reductions (CERs) | Value | 0.00 | 0.00 | 805000.00 |
Date | June 1, 2010 | May 31, 2012 | December 31, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Registration of Project by UNFCCC | Value | No | No | Yes |
Date | June 1, 2010 | May 31, 2012 | December 31, 2013 | |
Comment | Application for CDM registration to UNFCCC will be submitted after successful completion of validation |
Completion of Validation | Value | No | No | Yes |
Date | March 31, 2010 | May 31, 2012 | December 31, 2012 | |
Comment | Validation is ongoing |