BBMB Hydro Power Rehab Project - Carbon Finance

Development Objective

The development objective of the Project is to improve the reliability, efficiency and safety of the operation of BBMB’s hydraulic structures and generation equipment to meet the increasing demand for power in the Northern Electricity Grid of India through existing clean renewable energy resources.

Key Details

Project Details

  • P105152

  • Dropped

  • Rohit Mittal

  • N/A

  • India

  • November 28, 2007

  • (as of board presentation)

    May 28, 2010

  • May 31, 2010

  • US$ 138.88 million

  • N/A

  • South Asia

  • 2014

  • US$ 2.90 million

  • N/A

  • Not Applicable

  • December 31, 2018

  • BEGIN NEGOTIATION

  • December 19, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 135.98
Carbon Fund 2.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 2.90
Total Project Cost** 138.88

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2012-06-26
Overall Implementation Progress (IP) Moderately Satisfactory 2012-06-26
Counterpart Funding Satisfactory 2012-06-26
Project Management Satisfactory 2012-06-26
Monitoring and Evaluation Satisfactory 2012-06-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Certified Emission Reductions (CERs)Value0.000.00805000.00
    DateJune 1, 2010May 31, 2012December 31, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Registration of Project by UNFCCCValueNoNoYes
    DateJune 1, 2010May 31, 2012December 31, 2013
    CommentApplication for CDM registration to UNFCCC will be submitted after successful completion of validation
  • Completion of ValidationValueNoNoYes
    DateMarch 31, 2010May 31, 2012December 31, 2012
    CommentValidation is ongoing