Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IBRD Fund | 20.00 |
Global Environment Facility (GEF) | 5.00 |
Borrower/Recipient | 30.00 |
P105229
Closed
Qun Li
N/A
April 5, 2007
(as of board presentation)
April 17, 2008
November 13, 2008
US$ 55.00 million
N/A
2008
US$ 5.00 million
C
Not Applicable
June 30, 2012
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IBRD Fund | 20.00 |
Global Environment Facility (GEF) | 5.00 |
Borrower/Recipient | 30.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 5.00 |
Total Project Cost** | 55.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2011-12-28 |
Financial Management | Satisfactory | 2011-12-28 |
Monitoring and Evaluation | Satisfactory | 2011-12-28 |
Overall Safeguards Rating | Satisfactory | 2011-12-28 |
Summary Global Objective Rating | Satisfactory | 2011-12-28 |
Project Management | Satisfactory | 2011-12-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-17-2012 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Highly Satisfactory |
Government Performance | Highly Satisfactory |
Implementing Agency | Highly Satisfactory |
INDICATOR | ICR REVIEW: 06-19-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Satisfactory | N/a |
Risk To Development Outcome | Negligible | N/a |
Bank Performance | Highly Satisfactory | N/a |
Borrower Performance | Highly Satisfactory | N/a |
Government Performance | Not Rated | N/a |
Implementing Agency | Highly Satisfactory | N/a |
Icr Quality | Not Rated | N/a |
M&e Quality | Substantial | N/a |