Financier | Commitments |
---|---|
Global Partnership on Output-based Aid | 8.00 |
P105651
Closed
Issa Diaw
N/A
November 11, 2008
(as of board presentation)
November 11, 2008
May 29, 2009
US$ 8.00 million
N/A
2009
US$ 8.00 million
B
Not Applicable
June 30, 2013
BANK APPROVED
September 16, 2021
Financier | Commitments |
---|---|
Global Partnership on Output-based Aid | 8.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 8.00 |
Total Project Cost** | 8.00 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Satisfactory | 2012-12-28 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2012-12-28 |
Project Management | Moderately Satisfactory | 2012-12-28 |
Monitoring and Evaluation | Satisfactory | 2012-12-28 |
Overall Safeguards Rating | Satisfactory | 2012-12-28 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2012-12-28 |
Procurement | Moderately Unsatisfactory | 2012-12-28 |
Counterpart Funding | Satisfactory | 2012-12-28 |
Overall | Moderately Low | 2012-12-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-30-2014 |
---|---|
Outcomes | Unsatisfactory |
Risk to Development Outcome | High |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Unsatisfactory |
Government Performance | Unsatisfactory |
Implementing Agency | Moderately Unsatisfactory |
INDICATOR | ICR REVIEW: 12-30-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of new household with an operative metered connection made by EEPCo who received a 5-year loan to finance such connection | Value | Zero. No customer connections so far meet the requ | 60,000 | A total of 228,571 rural hhs will be connected and |
Date | May 29, 2009 | June 18, 2013 | June 29, 2012 | |
Comment | to be verified by IVA |
Number of energy efficient CFLs (two per household) provided to those new households | Value | Zero. No customer connections so far meet the requ | 120,000 | 457,142 CFLs will be distributed to those customer |
Date | May 29, 2009 | June 18, 2013 | June 29, 2012 | |
Comment | to be verified by IVA |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Monitoring and Verification Agency hired and operational | Value | No M&V in place, No TOR | IVA is pursuing the final verifications of connect | TOR, procurement of firm, operational and able to |
Date | May 29, 2009 | June 18, 2013 | November 30, 2009 | |
Comment |