Abstract*

The proposed project is the third phase of the World Bank's horizontal Adaptable Program Loan (APL) Africa Stockpiles Programme-Project 1 (ASP-Pl), which was approved by the GEF CEO on August 16, 2005 and by the World Bank Board on September 8, 2005. The APL program covers: (a) country operations (ASP-P1 Component 1); (b) technical support to country projects (ASP-P1 Component 2); (c) cross-cutting activities in communication and knowledge management...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to assist the Recipient in: (a) eliminating inventoried publicly held obsolete pesticide stocks and associated waste; and (b) implementing measures to reduce and prevent future related risks.

Key Details

Project Details

  • P105711

  • Closed

  • Dinesh Aryal

  • N/A

  • Africa

  • June 19, 2007

  • (as of board presentation)

    June 19, 2007

  • July 13, 2007

  • US$ 8.67 million

  • N/A

  • Africa

  • 2007

  • US$ 8.25 million

  • A

  • Not Applicable

  • June 28, 2013

  • BANK APPROVED

  • May 20, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 0.42
JAPAN: Gov. of (excl. Ministry of Finance - PHRD Grants) 1.14
BELGIUM: MOFA-Directorate-General for Int. Coop.(DGIC) 3.47
FINLAND: Ministry for Foreign Affairs 1.02
Global Environment Facility (GEF) 2.62

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.25
Total Project Cost** 8.67

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Summary Global Objective Rating Moderately Satisfactory 2013-05-29
Overall Implementation Progress (IP) Moderately Satisfactory 2013-05-29
Overall Safeguards Rating Satisfactory 2013-05-29
Counterpart Funding Satisfactory 2013-05-29
Procurement Moderately Satisfactory 2013-05-29
Project Management Satisfactory 2013-05-29
Financial Management Satisfactory 2013-05-29
Monitoring and Evaluation Satisfactory 2013-05-29
Overall Safeguards Rating Satisfactory 2013-05-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 11-29-2013
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-29-2016PROJECT PERFORMANCE ASSESSMENT REPORT: 03-27-2015
Outcome RatingUnsatisfactory Unsatisfactory
Risk To Development OutcomeLowModerate
Bank PerformanceUnsatisfactoryUnsatisfactory
Borrower PerformanceModerately UnsatisfactoryModerately Unsatisfactory
Government PerformanceNot RatedModerately Satisfactory
Implementing AgencyNot RatedModerately Unsatisfactory
Icr QualityNot RatedSatisfactory
M&e QualityNegligibleNegligible

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • PMT functions satisfactorilyValuePMT not yet functionalPMT satisfactorily maintained throughout project.
    DateJuly 1, 2007May 9, 2013May 31, 2013
    CommentNot reported.This is an old indicator and is not in the Results Framework of the Restructuring Paper of 2011.
  • The training program under Part D of the project is implemented and the knowledge so acquired is being used by the RecipientValueTraining program identifiedTraining program satisfactorily completedTraining program satisfactorily completed
    DateJuly 1, 2007May 9, 2013May 31, 2013
    CommentNot reported.This is an old indicator and is not in the Results Framework of the Restructuring Paper of 2011.
  • Inventory database of publicly held obsolete pesticides stocks and associated waste in place and in use.ValueDatabase not availableDatabase regularly updated and in useDatabase regularly updated and in use
    DateJuly 1, 2007May 9, 2013July 1, 2011
    CommentThe end of project target was achieved by 06/16/2010.
  • Legal and regulatory framework for pesticide management improved, including measures to strengthen compliance with the Basil convention and the Rotterdam conventionValueFramework compliance unknownPesticides Registration and Control Proclamation wFramework reviewed and measures proposed.
    DateJuly 1, 2007August 31, 2012July 1, 2011
    CommentSeveral policies and guidelines have been approved/adopted to improve the pesticide management practices in the country. No newlegal or regulatory framework is considered with the project support.This is an old indicator and is not in the Results Framework of the Restructuring Paper of 2011.
  • Completion of CESA and implementation of measures contained thereinValueNot applicableCESA cleared by the Bank and disclosed at InfoShopCESA carried out and mitigation measures implement
    DateJuly 1, 2007May 9, 2013May 31, 2013
    CommentIn the Restructuring Paper, the text is "Approved CESA available for use by the disposal company" which has been achieved.Approved CESA was available for use for disposal company.
  • Pesticide management strategy is developedValueNo strategy availableA final draft container management strategy submitStrategy formally adopted
    DateJuly 1, 2007May 9, 2013May 31, 2013
    CommentIn the Restructuring Paper, the text is "A final draft container management strategy submitted to the Steering Committee forapproval" which has been achieved.
  • Inventoried publicly held obsolete pesticide stocks disposed of, as a result of the completion of the disposal services contract(s)in accordance with national and international laws and regulationsValueNo disposal, no inventory450 tonnes450 tonnes of stocks disposed
    DateJuly 1, 2007May 9, 2013May 31, 2013
    Comment300 tonnes being incinerated and 150 tonnes in route to disposal facility for incineration.
  • Reduction of Obsolete Pesticide Associated waste Re-AccumulationValue0.000.000.00
    DateJune 30, 2011May 9, 2013May 31, 2013
    CommentNot reported.This is an old indicator and is not in the Results Framework of the Restructuring Paper of 2011.
  • A strategy for sustainable management of future accumulations adopted by the Steering Committee by the end of the project.ValueNo strategy in placeDraft strategy prepared anddiscussed with stakehoStrategy adopted by SC
    DateMay 9, 2013May 31, 2013
    CommentThis is a new indicator as per Project Restructuring of 2011.
  • Two planned communication tools implementedValue0.002.002.00
    DateMay 9, 2013May 31, 2013
    CommentThis is new indicator per Restructuring Paper of 2011. The target was fully achieved - 1) posters and other similar materials wereprepared to raise awareness on the harmful nature of pesticides to human health the ecosystem; and 2) a one year TV and Radioawareness program were conducted in three local languages to raise awareness on pesticides use.The target was fully achieved - 1) posters and other similar materials were prepared to raise awareness on the harmful nature ofpesticides to human health the ecosystem; and 2) a one year TV and Radio awareness program were conducted in three local languagesto raise awareness on pesticides use.
  • - A final draft sustainable management plan for obsolete pesticides and associated wastes prepared and submitted to the SC for endorsementValueNo plan in placeA draft prevention strategy for preventing future A final draftstrategy finalizedand submitted to
    DateMay 9, 2013May 31, 2013
    CommentNew indicator as per Restructuring Paper of 2011.The target has already been achieved since these strategies are drafted,presented to stakeholders and are being tabled to SC.SC is expected to endorse
  • A Pesticide Registration and Control Proclamation drafted for submission to ParliamentValueNone in place.A revised pesticide registration and control proclWorkshops for updatingand merger of ministeriald
    DateMay 9, 2013May 31, 2013
    CommentNew indicator as per Restructuring Paper of 2011.
  • Availability of one new storage warehouse for pesticide managementValue0.000.000.00
    DateMay 9, 2013May 31, 2013
    CommentNew indicator as per Restructuring Paper of 2011, but the activity was dropped to release funds for disposal of OPs.No longer reported. It is canceled.