Abstract*

The objective of the West Bengal Institutional Strengthening of Gram Panchayats (GPs) Project for India is to develop institutionally strengthened GPs. There are four components to the project. The first component of the project is grants to GPs: component one will comprise two subcomponents: (a) block grants, and (b) state funded untied grants. This subcomponent will support an annual, performance-based block grant to the 1000 GPs participating in...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To develop institutionally strengthened Gram Panchayats (GPs).

Key Details

Project Details

  • P105990

  • Closed

  • Soma Ghosh Moulik

  • Government of West Bengal

  • India

  • July 16, 2009

  • (as of board presentation)

    June 8, 2010

  • September 3, 2010

  • US$ 230.40 million

  • Panchayats and Rural Developemnt Department

  • South Asia

  • 2010

  • US$ 195.40 million

  • B

  • Not Applicable

  • June 30, 2016

  • BANK APPROVED

  • August 9, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 35.00
IDA Credit 195.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 195.40
IBRD + IDA Commitment 195.40
Lending Instrument
Grant Amount N/A
Total Project Cost** 230.40

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 1, 2017 IDA-47580 Int Charges 524,712.80
Jun 1, 2017 IDA-47580 Int Charges 524,712.80
Jun 1, 2017 IDA-47580 Loan Repay 159,917.55
Dec 1, 2017 IDA-47580 Int Charges 106,478.72
Dec 1, 2017 IDA-47580 Int Charges 106,478.72
Dec 1, 2017 IDA-47580 Loan Repay 4,635,241.00
Dec 1, 2017 IDA-47580 Int Charges 605,628.90
Dec 1, 2017 IDA-47580 Int Charges 605,628.90
Jun 1, 2018 IDA-47580 Int Charges 20,114.37
Jun 1, 2018 IDA-47580 Int Charges 20,114.37
Jun 1, 2018 IDA-47580 Loan Repay 4,631,941.00
Jun 1, 2018 IDA-47580 Int Charges 607,942.25
Jun 1, 2018 IDA-47580 Int Charges 607,942.25
Dec 1, 2018 IDA-47580 Int Charges 576,249.90
Dec 1, 2018 IDA-47580 Int Charges 576,249.90
Dec 1, 2018 IDA-47580 Loan Repay 134,504.50
Dec 1, 2018 IDA-47580 Loan Repay 4,385,102.00
Jun 1, 2019 IDA-47580 Loan Repay 46,234.53
Jun 1, 2019 IDA-47580 Loan Repay 4,455,042.00
Jun 1, 2019 IDA-47580 Int Charges 557,033.00
Jun 1, 2019 IDA-47580 Int Charges 557,033.00
Dec 1, 2019 IDA-47580 Loan Repay 38,663.77
Dec 1, 2019 IDA-47580 Loan Repay 4,447,190.50
Dec 1, 2019 IDA-47580 Int Charges 498,486.88
Dec 1, 2019 IDA-47580 Int Charges 498,486.88
Jun 1, 2020 IDA-47580 Int Charges 39,767.73
Jun 1, 2020 IDA-47580 Int Charges 39,767.73
Jun 1, 2020 IDA-47580 Int Charges 501,222.53
Jun 1, 2020 IDA-47580 Int Charges 501,222.53
Dec 1, 2020 IDA-47580 Int Charges 488,031.50
Dec 1, 2020 IDA-47580 Int Charges 20,458.05
Dec 1, 2020 IDA-47580 Int Charges 20,458.05
Dec 1, 2020 IDA-47580 Loan Repay 2,334,578.50
Dec 1, 2020 IDA-47580 Int Charges 488,031.50
Jun 1, 2021 IDA-47580 Int Charges 37,666.44
Jun 1, 2021 IDA-47580 Int Charges 37,666.44
Jun 1, 2021 IDA-47580 Loan Repay 2,360,767.00
Jun 1, 2021 IDA-47580 Int Charges 464,896.22
Jun 1, 2021 IDA-47580 Int Charges 464,896.22
Dec 1, 2021 IDA-47580 Loan Repay 2,286,383.80
Dec 1, 2021 IDA-47580 Int Charges 497,288.47
Dec 1, 2021 IDA-47580 Int Charges 497,288.47
Dec 1, 2021 IDA-47580 Int Charges 55,614.14
Dec 1, 2021 IDA-47580 Int Charges 55,614.14
Jun 1, 2022 IDA-47580 Int Charges 471,128.50
Jun 1, 2022 IDA-47580 Int Charges 471,128.50
Jun 1, 2022 IDA-47580 Loan Repay 24,710.62
Jun 1, 2022 IDA-47580 Loan Repay 2,179,399.20
Dec 1, 2022 IDA-47580 Loan Repay 61,946.46
Dec 1, 2022 IDA-47580 Loan Repay 4,253,870.50
Dec 1, 2022 IDA-47580 Int Charges 305,202.12
Dec 1, 2022 IDA-47580 Int Charges 305,202.12
Jun 1, 2023 IDA-47580 Int Charges 148,980.28
Jun 1, 2023 IDA-47580 Int Charges 148,980.28
Jun 1, 2023 IDA-47580 Loan Repay 4,345,616.00
Jun 1, 2023 IDA-47580 Int Charges 439,993.60
Jun 1, 2023 IDA-47580 Int Charges 439,993.60
Dec 1, 2023 IDA-47580 Loan Repay 4,296,484.00
Dec 1, 2023 IDA-47580 Int Charges 362,457.75
Dec 1, 2023 IDA-47580 Int Charges 362,457.75
Dec 1, 2023 IDA-47580 Loan Repay 56,581.66
Jun 8, 2010 IDA-47580 Loan Commitment 200,000,000.00
Jun 1, 2024 IDA-47580 Loan Repay 3,664,274.20
Jun 1, 2024 IDA-47580 Int Charges 405,428.80
Jun 1, 2024 IDA-47580 Int Charges 405,428.80
Jun 1, 2024 IDA-47580 Int Charges 61,560.57
Jun 1, 2024 IDA-47580 Int Charges 61,560.57
Jun 1, 2024 IDA-47580 Loan Repay 660,299.50
Dec 1, 2014 IDA-47580 Int Charges 1,637.04
Dec 1, 2014 IDA-47580 Int Charges 1,637.04
Dec 1, 2014 IDA-47580 Int Charges 561,401.30
Dec 1, 2014 IDA-47580 Int Charges 561,401.30
Oct 31, 2013 IDA-47580 Loan Disb 3,634,056.80
Feb 7, 2014 IDA-47580 Loan Disb 47,692,972.00
Dec 1, 2013 IDA-47580 Int Charges 813.35
Dec 1, 2013 IDA-47580 Int Charges 813.35
Dec 1, 2013 IDA-47580 Int Charges 397,603.30
Dec 1, 2013 IDA-47580 Int Charges 397,603.30
Jun 1, 2014 IDA-47580 Int Charges 1,916.28
Jun 1, 2014 IDA-47580 Int Charges 1,916.28
Jun 1, 2014 IDA-47580 Int Charges 526,764.44
Jun 1, 2014 IDA-47580 Int Charges 526,764.44
Dec 29, 2014 IDA-47580 Loan Disb 2,660,463.20
Apr 9, 2015 IDA-47580 Loan Disb 37,796,592.00
Jun 1, 2015 IDA-47580 Int Charges 7,355.60
Jun 1, 2015 IDA-47580 Int Charges 7,355.60
Jun 1, 2015 IDA-47580 Int Charges 531,472.00
Jun 1, 2015 IDA-47580 Int Charges 531,472.00
Dec 1, 2015 IDA-47580 Loan Repay 4,527,066.50
Dec 1, 2015 IDA-47580 Int Charges 679,059.94
Dec 1, 2015 IDA-47580 Int Charges 679,059.94
Dec 1, 2015 IDA-47580 Int Charges 44,068.79
Dec 1, 2015 IDA-47580 Int Charges 44,068.79
Jun 1, 2016 IDA-47580 Loan Repay 100,844.77
Jun 1, 2016 IDA-47580 Loan Repay 50.00
Jun 1, 2016 IDA-47580 Loan Repay 4,521,331.00
Jun 1, 2016 IDA-47580 Int Charges 676,000.50
Jun 1, 2016 IDA-47580 Int Charges 676,000.50
Dec 1, 2016 IDA-47580 Loan Repay 23,907.72
Dec 1, 2016 IDA-47580 Loan Repay 4,435,314.50
Dec 1, 2016 IDA-47580 Int Charges 635,439.20
Dec 1, 2016 IDA-47580 Int Charges 635,439.20
Dec 30, 2016 IDA-47580 Loan Disb -1,371,357.90
Dec 30, 2016 IDA-47580 Loan Cancel 1,371,357.90
Jun 1, 2017 IDA-47580 Loan Repay 4,364,753.50
Jun 1, 2020 IDA-47580 Loan Repay 4,480,463.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2016-06-30
Overall Safeguards Rating Satisfactory 2016-06-30
Counterpart Funding Satisfactory 2016-06-30
Overall Implementation Progress (IP) Satisfactory 2016-06-30
Progress towards achievement of PDO Satisfactory 2016-06-30
Financial Management Satisfactory 2016-06-30
Monitoring and Evaluation Satisfactory 2016-06-30
Overall Safeguards Rating Satisfactory 2016-06-30
Project Management Satisfactory 2016-06-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-22-2016
OutcomesHighly Satisfactory
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceHighly Satisfactory
Government PerformanceHighly Satisfactory
Implementing AgencyHighly Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-22-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeModestN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceHighly SatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencyHighly SatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • By EOP, minimum of 80% of 1000 GPs have well functioning fiduciary and planning systems in placeValue52.0098.9080.00
    DateMarch 29, 2010June 1, 2016June 30, 2016
    Comment
  • A performance based grant transfer system is well established to roll out to other GPsValue0.001.001.00
    DateSeptember 3, 2010June 15, 2016June 30, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Grant to GPs(Component 1) By EOP,80% of GPs(800) receive annual grants after passing performance assessmentsValue0.0099.9080.00
    DateJune 1, 2016June 30, 2016
    Comment
  • Number of project beneficiaries of which x% are femaleValue0.0053.2850.00
    DateJune 1, 2016June 30, 2016
    Comment
  • Capacity Builidng GPs ( Component 2) : Minimum of 2000 GPs trained over life of the projectValue0.003320.002000.00
    DateJune 1, 2016June 30, 2016
    Comment
  • Minimum of 2 GP operating system areas ( planning and GPMS) are improvedValue0.002.002.00
    DateJune 1, 2016June 30, 2016
    Comment
  • State Government Oversight and Monitoring of PRIs ( Component 3): The performance of 100% of targeted GPs is assessed each yearValue0.00100.00100.00
    DateSeptember 3, 2010June 1, 2016June 30, 2016
    Comment
  • By EOP, detailed reports on GP investments are available for 80% of targeted GPsValue0.00100.0080.00
    DateJune 1, 2016June 30, 2016
    Comment
  • Three Thematic evaluations or studies are completed by EOPValue0.003.003.00
    DateSeptember 3, 2010June 1, 2016June 30, 2016
    Comment
  • Project Management and Implementation ( Component 4 ) : Project Coordination Cells at the state and district levels are functioningto provide suport and oversight to GPs.Value1.001.001.00
    DateSeptember 3, 2010June 1, 2016June 30, 2016
    Comment
  • Information regarding project is distributed widely to all 1000 participating GPs by EOPValue0.001000.001000.00
    DateMarch 29, 2010June 1, 2016June 30, 2016
    Comment
  • Direct project beneficiariesValue0.0021330516.000.00
    DateMarch 29, 2010June 1, 2016June 30, 2016
    Comment
  • Female beneficiariesValue0.0053.180.00
    DateMarch 29, 2010June 1, 2016June 30, 2016
    Comment