Development Objective

This carbon offset project consists of purchase of ERs generated from installation of up to 1,000,000 solar homes systems by Grameen Shakti, the project proponent, to rural users in Bangladesh. The costs of the SHS can be paid on a cash basis, or can be purchased through a variety of monthly installment plans to maximize participation by increasing affordability. Grameen Shakti has installed over 75,000 such systems in Bangladesh, and has set up 120 offices for service delivery and performance monitoring. The use of the solar home system technology will displace kerosene and/or diesel for larger systems to meet household lighting and personal electricity needs. The systems are large enough to provide sufficient power for 1-2 lights and a television or radio. One of the major local environmental benefits would be the reduction of household indoor air pollution. Carbon Finance Revenues would allow for the implementation of the program by providing additional resources to capitalize a revolving fund which will combine CF revenues, funds from Grameen, and funds from IDCOL (both grant and loan) to finance the loans to the individual households. The implementation of this program will increase access in Bangladesh to modern energy sources, where less than 15% of the population is connected to the national electricity grid. The purchase would be made by the World Bank-managed Community Development Carbon Fund (CDCF). The CDCF provides carbon finance to small-scale CDM projects in the least developed countries and poorer areas of all developing countries and seek to facilitate projects which include, as a measurable output, the provision of goods and services that would lead to improvement in the social welfare of the communities involved in the projects.

Key Details

Project Details

  • P106135

  • Closed

  • Zubair Sadeque

  • N/A

  • Bangladesh

  • January 8, 2008

  • (as of board presentation)

    December 17, 2007

  • December 19, 2007

  • US$ 428.00 million

  • N/A

  • South Asia

  • 2008

  • US$ 9.00 million

  • N/A

  • December 19, 2024

  • June 30, 2017

  • BANK APPROVED

  • P131263

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 32.00
Non-Government Organization (NGO) of Borrowing Country 45.00
Local Sources of Borrowing Country 168.10
PROTOTYPE CARBON FUND 9.00
Local Communities 80.90
Borrowing Country's Fin. Intermediary/ies 93.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 9.00
Total Project Cost** 428.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2015-12-30
Progress towards achievement of PDO Moderately Satisfactory 2015-12-30
Procurement Satisfactory 2015-12-30
Overall Implementation Progress (IP) Moderately Satisfactory 2015-12-30
Overall Safeguards Rating Satisfactory 2015-12-30
Counterpart Funding Satisfactory 2015-12-30
Financial Management Satisfactory 2015-12-30
Monitoring and Evaluation Satisfactory 2015-12-30
Overall Safeguards Rating Satisfactory 2015-12-30

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.