Timor Leste - Youth Development Project

Development Objective

The overall objectives of the YDP are to promote youth empowerment and inclusion in development by expanding the capacities of, and opportunities for, youth groups to initiate and participate in community and local development initiatives.

Key Details

Project Details

  • P106220

  • Closed

  • Ingo Wiederhofer

  • N/A

  • Timor-Leste

  • May 6, 2008

  • (as of board presentation)

    July 1, 2008

  • March 12, 2009

  • US$ 2.10 million

  • C

  • Not Applicable

  • September 30, 2012

  • BANK APPROVED

  • May 19, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 2.10

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 2.10
IBRD + IDA Commitment 2.10
Lending Instrument
Grant Amount N/A
Total Project Cost** 2.10

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 1, 2008 IDA-H4140 Loan Commitment 2,118,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2012-03-17
Overall Safeguards Rating Satisfactory 2012-03-17
Project Management Moderately Unsatisfactory 2012-03-17
Financial Management Unsatisfactory 2012-03-17
Overall Implementation Progress (IP) Moderately Satisfactory 2012-03-17
Procurement Moderately Unsatisfactory 2012-03-17
Counterpart Funding Satisfactory 2012-03-17
Overall Safeguards Rating Satisfactory 2012-03-17
Monitoring and Evaluation Moderately Satisfactory 2012-03-17

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-21-2013
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-22-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved SSYS Performance Ratings.ValueLow.Moderately improved.Moderately Satisfactory.
    DateJanuary 22, 2009January 6, 2012September 30, 2012
    CommentBased on assessment conducted during most recent implementation support mission.
  • % of targeted communities that report increased youth participation in local and community development activitiesValue0.000.0060.00
    DateJanuary 22, 2009January 6, 2012September 30, 2012
    CommentNo baseline required.The data will be obtained at the end of the project.
  • % of targeted communities where youth feel that there are more opportunities for youth participation in community and local developmentValue0.000.0060.00
    DateJanuary 22, 2009January 6, 2012September 30, 2012
    CommentNo baseline required.The data will be obtained at the end of the project.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • % of initiatives funded through Youth Grants that continue after funding expiresValue0Not available70%
    DateJanuary 22, 2009June 8, 2011December 31, 2011
    CommentNot yet available, as first round of sub-projects still under implementation.
  • Performance Monitoring System for SSYS designed and functioningValueNoneIn process of being designedSystem functioning
    DateJanuary 22, 2009January 6, 2012September 30, 2012
    Comment
  • % of YCMC members from targeted Youth Centers that report an increase in leadership, management and planning skillsValue0.000.0060.00
    DateJanuary 22, 2009January 6, 2012September 30, 2012
    CommentNo baseline required.The data will be available at the end of the project.
  • % of youth participating in youth decision-making meetings in targeted communitiesValue0.000.0030.00
    DateJanuary 22, 2009January 6, 2012September 30, 2012
    CommentNo baseline required.
  • Number of YDP subprojects implemented by youth in targeted communitiesValue0.00280.00200.00
    DateJanuary 22, 2009January 6, 2012September 30, 2012
    Comment
  • % of youth participating in the implementation of youth development projects in targted communitiesValue0.000.0020.00
    DateJanuary 22, 2009January 6, 2012December 31, 2012
    CommentNo baseline data available.Annual measurement. No data available at this time.
  • % of youth in FGDs in targeted communities who are satisfied with the goods and services delivered through the YDP youth grantsValue0.000.0070.00
    DateJanuary 22, 2009January 6, 2012September 30, 2012
    CommentThe data will be available at the end of the project.