Financier | Commitments |
---|---|
IDA Credit | 75.00 |
P106596
Closed
Justin Runji
Ministry of Transport and Communications,National Road Fund Agency
September 9, 2008
(as of board presentation)
October 16, 2009
March 30, 2010
US$ 75.00 million
National Council for Construction,Ministry of Works and Supply,Road Transport and Safety Agency
2010
US$ 75.00 million
B
Not Applicable
April 30, 2016
BANK APPROVED
July 15, 2021
Financier | Commitments |
---|---|
IDA Credit | 75.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 75.00 |
IBRD + IDA Commitment | 75.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 75.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 1, 2017 | IDA-46540 | Int Charges | 1,887.89 |
Oct 1, 2017 | IDA-46540 | Int Charges | 1,887.89 |
Oct 12, 2017 | IDA-46540 | Int Charges | 253,846.12 |
Oct 12, 2017 | IDA-46540 | Int Charges | 253,846.12 |
Apr 13, 2018 | IDA-46540 | Int Charges | 500.99 |
Apr 13, 2018 | IDA-46540 | Int Charges | 500.99 |
Apr 13, 2018 | IDA-46540 | Int Charges | 263,431.80 |
Oct 1, 2014 | IDA-46540 | Int Charges | 554.67 |
Oct 1, 2014 | IDA-46540 | Int Charges | 554.67 |
Oct 1, 2014 | IDA-46540 | Int Charges | 101,217.14 |
Oct 1, 2014 | IDA-46540 | Int Charges | 101,217.14 |
Oct 18, 2013 | IDA-46540 | Int Charges | 53,783.95 |
Oct 18, 2013 | IDA-46540 | Int Charges | 53,783.95 |
Nov 1, 2013 | IDA-46540 | Loan Disb | 826,702.10 |
Jan 31, 2014 | IDA-46540 | Loan Disb | 3,832,636.20 |
Oct 1, 2013 | IDA-46540 | Int Charges | 1,178.68 |
Oct 1, 2013 | IDA-46540 | Int Charges | 1,178.68 |
Apr 8, 2014 | IDA-46540 | Int Charges | 1,189.01 |
Apr 8, 2014 | IDA-46540 | Int Charges | 1,189.01 |
Apr 8, 2014 | IDA-46540 | Int Charges | 75,886.34 |
Apr 8, 2014 | IDA-46540 | Int Charges | 75,886.34 |
Jun 12, 2014 | IDA-46540 | Loan Disb | 6,835,876.50 |
Sep 23, 2014 | IDA-46540 | Loan Disb | 19,663,614.00 |
Aug 19, 2015 | IDA-46540 | Loan Disb | 2,552,495.20 |
Apr 1, 2015 | IDA-46540 | Int Charges | 168,172.16 |
Apr 1, 2015 | IDA-46540 | Int Charges | 24.42 |
Apr 1, 2015 | IDA-46540 | Int Charges | 24.42 |
Apr 1, 2015 | IDA-46540 | Int Charges | 168,172.16 |
Apr 7, 2015 | IDA-46540 | Loan Disb | 14,961,851.00 |
Nov 20, 2015 | IDA-46540 | Loan Disb | 4,377,660.00 |
Oct 1, 2023 | IDA-46540 | Loan Repay | 634,870.50 |
Oct 1, 2023 | IDA-46540 | Int Charges | 319.34 |
Oct 1, 2023 | IDA-46540 | Int Charges | 319.34 |
Oct 1, 2023 | IDA-46540 | Loan Repay | 264.82 |
Oct 1, 2023 | IDA-46540 | Int Charges | 221,503.40 |
Oct 1, 2023 | IDA-46540 | Int Charges | 221,503.40 |
Apr 1, 2024 | IDA-46540 | Int Charges | 220,571.42 |
Apr 1, 2024 | IDA-46540 | Int Charges | 220,571.42 |
Apr 1, 2024 | IDA-46540 | Loan Repay | 623,221.20 |
Oct 1, 2020 | IDA-46540 | Loan Repay | 9,457.47 |
Oct 13, 2020 | IDA-46540 | Loan Repay | 673,800.30 |
Oct 13, 2020 | IDA-46540 | Int Charges | 597.88 |
Oct 13, 2020 | IDA-46540 | Int Charges | 597.88 |
Oct 13, 2020 | IDA-46540 | Int Charges | 252,637.19 |
Oct 13, 2020 | IDA-46540 | Int Charges | 252,637.19 |
Oct 1, 2015 | IDA-46540 | Int Charges | 3,661.96 |
Oct 1, 2015 | IDA-46540 | Int Charges | 3,661.96 |
Oct 1, 2015 | IDA-46540 | Int Charges | 49,095.62 |
Oct 1, 2015 | IDA-46540 | Int Charges | 49,095.62 |
Oct 1, 2015 | IDA-46540 | Int Charges | 171,833.58 |
Oct 1, 2015 | IDA-46540 | Int Charges | 171,833.58 |
Apr 20, 2016 | IDA-46540 | Int Charges | 245,020.36 |
Apr 20, 2016 | IDA-46540 | Int Charges | 245,020.36 |
Apr 20, 2016 | IDA-46540 | Int Charges | 3,164.73 |
Apr 20, 2016 | IDA-46540 | Int Charges | 3,164.73 |
Oct 13, 2016 | IDA-46540 | Int Charges | 5,883.06 |
Oct 13, 2016 | IDA-46540 | Int Charges | 5,883.06 |
Oct 13, 2016 | IDA-46540 | Int Charges | 249,872.81 |
Oct 13, 2016 | IDA-46540 | Int Charges | 249,872.81 |
Apr 10, 2017 | IDA-46540 | Int Charges | 241,763.45 |
Apr 10, 2017 | IDA-46540 | Int Charges | 241,763.45 |
Apr 1, 2017 | IDA-46540 | Int Charges | 3,220.21 |
Apr 1, 2017 | IDA-46540 | Int Charges | 3,220.21 |
Apr 26, 2019 | IDA-46540 | Int Charges | 121,450.05 |
Apr 26, 2019 | IDA-46540 | Int Charges | 121,450.05 |
Apr 26, 2019 | IDA-46540 | Int Charges | 127,735.66 |
Apr 26, 2019 | IDA-46540 | Int Charges | 127,735.66 |
Apr 1, 2019 | IDA-46540 | Int Charges | 1,059.78 |
Apr 1, 2019 | IDA-46540 | Int Charges | 1,059.78 |
Oct 1, 2019 | IDA-46540 | Int Charges | 3,048.77 |
Oct 1, 2019 | IDA-46540 | Int Charges | 3,048.77 |
Nov 8, 2019 | IDA-46540 | Int Charges | 245,025.45 |
Nov 8, 2019 | IDA-46540 | Int Charges | 245,025.45 |
May 13, 2020 | IDA-46540 | Loan Repay | 658,193.75 |
May 13, 2020 | IDA-46540 | Int Charges | 246,822.66 |
May 13, 2020 | IDA-46540 | Int Charges | 246,822.66 |
May 13, 2020 | IDA-46540 | Int Charges | 666.42 |
May 13, 2020 | IDA-46540 | Int Charges | 666.42 |
Apr 1, 2024 | IDA-46540 | Loan Repay | 16,116.27 |
Oct 16, 2009 | IDA-46540 | Loan Commitment | 75,000,000.00 |
May 4, 2021 | IDA-46540 | Int Charges | 1,045.11 |
May 4, 2021 | IDA-46540 | Loan Repay | 691,602.90 |
May 4, 2021 | IDA-46540 | Int Charges | 170.50 |
May 4, 2021 | IDA-46540 | Int Charges | 170.50 |
May 4, 2021 | IDA-46540 | Int Charges | 254,164.05 |
May 4, 2021 | IDA-46540 | Int Charges | 254,164.05 |
May 4, 2021 | IDA-46540 | Int Charges | 1,045.11 |
Apr 1, 2021 | IDA-46540 | Int Charges | 0.01 |
Apr 1, 2021 | IDA-46540 | Int Charges | 0.01 |
Oct 1, 2021 | IDA-46540 | Loan Repay | 4,239.26 |
Oct 4, 2021 | IDA-46540 | Loan Repay | 678,375.00 |
Oct 4, 2021 | IDA-46540 | Int Charges | 469.31 |
Oct 4, 2021 | IDA-46540 | Int Charges | 469.31 |
Oct 4, 2021 | IDA-46540 | Int Charges | 248,302.64 |
Oct 4, 2021 | IDA-46540 | Int Charges | 248,302.64 |
Apr 14, 2022 | IDA-46540 | Loan Repay | 652,326.94 |
Apr 14, 2022 | IDA-46540 | Int Charges | 41.15 |
Apr 14, 2022 | IDA-46540 | Int Charges | 41.15 |
Apr 14, 2022 | IDA-46540 | Int Charges | 238,488.60 |
Apr 14, 2022 | IDA-46540 | Int Charges | 238,488.60 |
Apr 1, 2022 | IDA-46540 | Loan Repay | 10,206.53 |
Oct 26, 2022 | IDA-46540 | Loan Repay | 605,944.44 |
Oct 26, 2022 | IDA-46540 | Int Charges | 166.24 |
Oct 26, 2022 | IDA-46540 | Int Charges | 166.24 |
Oct 26, 2022 | IDA-46540 | Int Charges | 222,071.89 |
Oct 26, 2022 | IDA-46540 | Int Charges | 222,071.89 |
Oct 1, 2022 | IDA-46540 | Loan Repay | 17,270.71 |
Apr 1, 2023 | IDA-46540 | Loan Repay | 22,519.66 |
Apr 26, 2023 | IDA-46540 | Int Charges | 330.42 |
Apr 26, 2023 | IDA-46540 | Int Charges | 330.42 |
Apr 26, 2023 | IDA-46540 | Int Charges | 230,067.27 |
Apr 26, 2023 | IDA-46540 | Int Charges | 230,067.27 |
Apr 26, 2023 | IDA-46540 | Loan Repay | 630,051.94 |
Apr 13, 2018 | IDA-46540 | Int Charges | 263,431.80 |
Oct 1, 2018 | IDA-46540 | Int Charges | 194.17 |
Oct 1, 2018 | IDA-46540 | Int Charges | 194.17 |
Oct 16, 2018 | IDA-46540 | Int Charges | 252,882.53 |
Oct 16, 2018 | IDA-46540 | Int Charges | 252,882.53 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Moderately Satisfactory | 2016-05-04 |
Progress towards achievement of PDO | Satisfactory | 2016-05-04 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2016-05-04 |
Project Management | Satisfactory | 2016-05-04 |
Overall Safeguards Rating | Satisfactory | 2016-05-04 |
Procurement | Satisfactory | 2016-05-04 |
Financial Management | Satisfactory | 2016-05-04 |
Overall Safeguards Rating | Satisfactory | 2016-05-04 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-28-2016 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 05-01-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Substantial | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Total annual number of road fatalities in Lusaka and Copperbelt provinces | Value | 714.00 | 882.00 | 900.00 |
Date | October 27, 2009 | April 8, 2016 | April 30, 2016 | |
Comment |
Roads rehabilitated, Non-rural | Value | 0.00 | 51.00 | 50.00 |
Date | October 30, 2009 | April 8, 2016 | April 30, 2016 | |
Comment |
Roads in good and fair condition as a share of total classified roads | Value | 50.00 | 90.00 | 80.00 |
Date | October 30, 2009 | April 8, 2016 | April 30, 2016 | |
Comment |
Share of rural population with access to an all-season road | Value | 0.00 | 83.00 | 60.00 |
Date | April 8, 2016 | April 30, 2016 | ||
Comment |
Size of the total classified network | Value | 67000.00 | 67671.00 | 67631.00 |
Date | October 30, 2009 | April 8, 2016 | April 30, 2016 | |
Comment |
Number of rural people with access to an all-season road | Value | 0.00 | 33730.00 | 7080.00 |
Date | April 8, 2016 | April 30, 2016 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Annual road fatalities per 10,000 registered vehicles | Value | 48.00 | 32.00 | 36.00 |
Date | October 27, 2009 | April 8, 2016 | April 30, 2016 | |
Comment |
Number of trucks subjected to annual axle load check at locations financed by the project (Copperbelt and Eastern Provinces ) | Value | 0.00 | 0.00 | 100000.00 |
Date | April 8, 2016 | April 30, 2016 | ||
Comment |
RDA Procurement process compliance rate with international standards | Value | 72.00 | 90.00 | 90.00 |
Date | October 27, 2009 | April 8, 2016 | April 30, 2016 | |
Comment |
Compliance rate with Road Sector Goverance Plan | Value | 0.00 | 95.00 | 90.00 |
Date | April 8, 2016 | April 30, 2016 | ||
Comment |
Number of vehicles crossing the Mufuchani bridge annually | Value | 0.00 | 1.00 | 60000.00 |
Date | April 8, 2016 | April 30, 2016 | ||
Comment |
Number of school children trained annually at the road safety school part in Lusaka | Value | 0.00 | 0.00 | 30000.00 |
Date | April 8, 2016 | April 30, 2016 | ||
Comment |
Number of private and commercial vehicle undergoing technical inspections in Lusaka | Value | 0.00 | 0.00 | 100000.00 |
Date | April 8, 2016 | June 30, 2014 | ||
Comment |
Number of people reached by HIV/AIDS awareness campaigns | Value | 0.00 | 9822.00 | 5000.00 |
Date | April 8, 2016 | June 30, 2014 | ||
Comment |
Kilometers of roads benefitting from spot improvements in the targeted 3 districts | Value | 0.00 | 196.60 | 72.00 |
Date | April 8, 2016 | April 30, 2016 | ||
Comment |
Total number of small bridges rehabilitated in the 3 targeted districts | Value | 0.00 | 22.00 | 6.00 |
Date | April 8, 2016 | April 30, 2016 | ||
Comment |