Skip to Main Navigation

Pakistan: Lahore Composting project

Development Objective

The overarching development objectives of the proposed Carbon Finance project are to: # Avoid generation of methane emission from biodegradable wastes; and # Improve cultivated land by using compost as a natural soil conditioner The Carbon Finance project will provide additional support for achieving the following objectives and benefits, namely to reduce carbon emission in a financially sustainable way, to promote and provide organic conditioner for agriculture; to increase recycling of valuable materials; to reduce health hazard by overall reduction of waste disposed off in landfills; and reduce the demand for landfill capacity.

Key Details

Project Details

  • P106652

  • Closed

  • Claudia Croce

  • N/A

  • Pakistan

  • June 18, 2008

  • (as of board presentation)

    August 27, 2008

  • August 27, 2008

  • US$ 5.52 million

  • N/A

  • South Asia

  • 2009

  • US$ 5.52 million

  • N/A

  • December 19, 2024

  • July 26, 2016

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Carbon Fund 5.52

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 5.52
Total Project Cost** 5.52

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2014-05-09
Counterpart Funding Moderately Satisfactory 2014-05-09
Monitoring and Evaluation Moderately Satisfactory 2014-05-09
Overall Low 2014-05-09
Overall Implementation Progress (IP) Satisfactory 2014-05-09
Project Management Moderately Satisfactory 2014-05-09

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Sale of compostValue0.0019.6558.86
    DateNovember 1, 2005December 31, 2012December 31, 2017
    CommentStarting date of the project activityThe figure was calculated based on the number of actual commercial sales (excluding promotional sales) compared with the availablecompost between January 1 to December 31, 2012.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • REgistration at UNFCCC in 2010ValueNoYes
    DateNovember 5, 2005April 5, 2010December 31, 2017
    Comment