Financier | Commitments |
---|---|
IDA Grant | 11.00 |
IDA Credit | 10.00 |
P106870
Closed
Amparo Gordillo-Tobar
Ministry of Health, Government of Nicaragua
April 20, 2010
(as of board presentation)
December 7, 2010
April 4, 2011
US$ 21.00 million
Ministry of Finance -- Uriel Perez,Ministry of Health
2011
US$ 21.00 million
B
April 25, 2024
May 31, 2016
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 11.00 |
IDA Credit | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 21.00 |
IBRD + IDA Commitment | 21.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 21.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2024 | IDA-48300 | Int Charges | 29,384.15 |
Aug 15, 2024 | IDA-48300 | Int Charges | 29,384.15 |
Aug 15, 2024 | IDA-48300 | Loan Repay | 1,628.40 |
Aug 15, 2024 | IDA-53680 | Loan Repay | 100,000.00 |
Aug 15, 2024 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2024 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2024 | IDA-48300 | Loan Repay | 88,055.79 |
Feb 15, 2024 | IDA-48300 | Loan Repay | 88,420.74 |
Feb 15, 2024 | IDA-48300 | Int Charges | 31,241.70 |
Feb 15, 2024 | IDA-48300 | Int Charges | 31,241.70 |
Feb 15, 2024 | IDA-48300 | Loan Repay | 208.20 |
Feb 15, 2024 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2024 | IDA-53680 | Int Charges | 70,000.00 |
Dec 7, 2010 | IDA-48300 | Loan Commitment | 10,000,000.00 |
Feb 24, 2014 | IDA-53680 | Loan Commitment | 10,000,000.00 |
Dec 7, 2010 | IDA-H6220 | Loan Commitment | 11,000,000.00 |
Feb 15, 2022 | IDA-48300 | Loan Repay | 1,732.40 |
Feb 15, 2022 | IDA-48300 | Loan Repay | 92,123.88 |
Feb 15, 2022 | IDA-48300 | Int Charges | 34,098.20 |
Feb 15, 2022 | IDA-48300 | Int Charges | 34,098.20 |
Aug 15, 2022 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2022 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2022 | IDA-48300 | Int Charges | 371.36 |
Aug 15, 2022 | IDA-48300 | Int Charges | 371.36 |
Aug 15, 2022 | IDA-48300 | Loan Repay | 88,466.13 |
Aug 15, 2022 | IDA-48300 | Int Charges | 32,179.52 |
Aug 15, 2022 | IDA-48300 | Int Charges | 32,179.52 |
Feb 15, 2023 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2023 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2023 | IDA-48300 | Loan Repay | 1,047.58 |
Feb 15, 2023 | IDA-48300 | Loan Repay | 88,556.88 |
Feb 15, 2023 | IDA-48300 | Int Charges | 31,658.95 |
Feb 15, 2023 | IDA-48300 | Int Charges | 31,658.95 |
Aug 15, 2023 | IDA-48300 | Int Charges | 31,801.52 |
Aug 15, 2023 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2023 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2023 | IDA-48300 | Int Charges | 596.40 |
Aug 15, 2023 | IDA-48300 | Int Charges | 596.40 |
Aug 15, 2023 | IDA-48300 | Loan Repay | 89,267.45 |
Aug 15, 2023 | IDA-48300 | Int Charges | 31,801.52 |
Feb 15, 2021 | IDA-48300 | Int Charges | 778.84 |
Feb 15, 2021 | IDA-48300 | Int Charges | 778.84 |
Feb 15, 2021 | IDA-48300 | Loan Repay | 96,530.25 |
Feb 15, 2021 | IDA-48300 | Int Charges | 35,942.16 |
Feb 15, 2021 | IDA-48300 | Int Charges | 35,942.16 |
Feb 15, 2021 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2021 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2021 | IDA-48300 | Int Charges | 253.05 |
Aug 15, 2021 | IDA-48300 | Int Charges | 253.05 |
Aug 15, 2021 | IDA-48300 | Loan Repay | 95,163.45 |
Aug 15, 2021 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2021 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2021 | IDA-48300 | Int Charges | 35,329.39 |
Aug 15, 2021 | IDA-48300 | Int Charges | 35,329.39 |
Feb 15, 2022 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2022 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2019 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2019 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2013 | IDA-48300 | Int Charges | 17,690.83 |
Aug 13, 2013 | IDA-48300 | Loan Disb | 1,200,000.00 |
Aug 15, 2019 | IDA-48300 | Int Charges | 34,531.55 |
Aug 15, 2019 | IDA-48300 | Int Charges | 34,531.55 |
Aug 15, 2019 | IDA-48300 | Int Charges | 188.79 |
Aug 15, 2019 | IDA-48300 | Int Charges | 188.79 |
Feb 15, 2020 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2020 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2020 | IDA-48300 | Int Charges | 34,132.84 |
Feb 15, 2020 | IDA-48300 | Int Charges | 34,132.84 |
Feb 15, 2020 | IDA-48300 | Int Charges | 225.84 |
Feb 15, 2020 | IDA-48300 | Int Charges | 225.84 |
Aug 15, 2020 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2020 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2020 | IDA-48300 | Int Charges | 416.57 |
Aug 15, 2020 | IDA-48300 | Int Charges | 416.57 |
Aug 15, 2020 | IDA-48300 | Int Charges | 34,239.59 |
Aug 15, 2020 | IDA-48300 | Int Charges | 34,239.59 |
Aug 15, 2017 | IDA-48300 | Int Charges | 34,723.03 |
Aug 15, 2017 | IDA-48300 | Int Charges | 34,723.03 |
Aug 15, 2017 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2017 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2018 | IDA-48300 | Int Charges | 35,508.10 |
Feb 15, 2018 | IDA-48300 | Int Charges | 660.07 |
Feb 15, 2018 | IDA-48300 | Int Charges | 660.07 |
Feb 15, 2018 | IDA-48300 | Int Charges | 35,508.10 |
Feb 15, 2018 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2018 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2018 | IDA-48300 | Int Charges | 1,080.24 |
Aug 15, 2018 | IDA-48300 | Int Charges | 1,080.24 |
Aug 15, 2018 | IDA-48300 | Int Charges | 34,757.42 |
Aug 15, 2018 | IDA-48300 | Int Charges | 34,757.42 |
Aug 15, 2018 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2018 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2019 | IDA-48300 | Int Charges | 716.82 |
Feb 15, 2019 | IDA-48300 | Int Charges | 33,930.30 |
Feb 15, 2019 | IDA-48300 | Int Charges | 33,930.30 |
Feb 15, 2019 | IDA-48300 | Int Charges | 716.82 |
Feb 15, 2019 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2019 | IDA-53680 | Int Charges | 70,000.00 |
Apr 28, 2016 | IDA-H6220 | Loan Disb | 36,866.99 |
Jul 13, 2016 | IDA-48300 | Loan Disb | 122,966.17 |
May 31, 2016 | IDA-48300 | Loan Disb | 1,509.55 |
May 18, 2016 | IDA-53680 | Loan Disb | 631,692.20 |
May 26, 2016 | IDA-53680 | Loan Disb | 326,623.62 |
Jul 13, 2016 | IDA-H6220 | Loan Disb | 52,067.84 |
Aug 15, 2016 | IDA-53680 | Int Charges | 64,463.56 |
Aug 15, 2016 | IDA-53680 | Int Charges | 64,463.56 |
Aug 15, 2016 | IDA-48300 | Int Charges | 271.13 |
Aug 15, 2016 | IDA-48300 | Int Charges | 271.13 |
Aug 15, 2016 | IDA-48300 | Int Charges | 34,597.99 |
Aug 15, 2016 | IDA-48300 | Int Charges | 34,597.99 |
Aug 15, 2016 | IDA-53680 | Int Charges | 2,701.97 |
Aug 15, 2016 | IDA-53680 | Int Charges | 2,701.97 |
Feb 15, 2017 | IDA-48300 | Int Charges | 183.03 |
Feb 15, 2017 | IDA-48300 | Int Charges | 183.03 |
Feb 15, 2017 | IDA-48300 | Int Charges | 33,478.96 |
Feb 15, 2017 | IDA-48300 | Int Charges | 33,478.96 |
Feb 15, 2017 | IDA-53680 | Int Charges | 70,000.00 |
Feb 15, 2017 | IDA-53680 | Int Charges | 70,000.00 |
Aug 15, 2017 | IDA-48300 | Int Charges | 265.33 |
Aug 15, 2017 | IDA-48300 | Int Charges | 265.33 |
Aug 15, 2015 | IDA-53680 | Int Charges | 87.49 |
Aug 15, 2015 | IDA-53680 | Int Charges | 87.49 |
Aug 15, 2015 | IDA-53680 | Int Charges | 20,827.38 |
Aug 15, 2015 | IDA-53680 | Int Charges | 20,827.38 |
Apr 23, 2015 | IDA-53680 | Loan Disb | 700,000.00 |
Aug 15, 2015 | IDA-48300 | Int Charges | 875.97 |
Aug 15, 2015 | IDA-48300 | Int Charges | 875.97 |
Aug 15, 2015 | IDA-48300 | Int Charges | 27,640.10 |
Aug 15, 2015 | IDA-48300 | Int Charges | 27,640.10 |
Jun 9, 2015 | IDA-48300 | Loan Disb | 900,000.00 |
Aug 27, 2015 | IDA-53680 | Loan Disb | 900,000.00 |
May 21, 2015 | IDA-H6220 | Loan Disb | 1,204,407.40 |
May 13, 2015 | IDA-53680 | Loan Disb | 298,692.72 |
Nov 16, 2015 | IDA-53680 | Loan Disb | 1,200,000.00 |
Oct 22, 2015 | IDA-53680 | Loan Disb | 600,000.00 |
Dec 14, 2015 | IDA-48300 | Loan Disb | 1,030,000.00 |
Dec 17, 2015 | IDA-53680 | Loan Disb | 700,000.00 |
Nov 30, 2015 | IDA-H6220 | Loan Disb | 1,195,534.50 |
Dec 21, 2015 | IDA-53680 | Loan Disb | 298,692.72 |
Jan 28, 2016 | IDA-53680 | Loan Disb | 750,000.00 |
Nov 9, 2015 | IDA-H6220 | Loan Disb | 802,938.25 |
Dec 22, 2015 | IDA-H6220 | Loan Disb | 797,023.06 |
Feb 15, 2016 | IDA-48300 | Int Charges | 31,734.15 |
Feb 15, 2016 | IDA-48300 | Int Charges | 31,734.15 |
Apr 25, 2016 | IDA-53680 | Loan Disb | 650,000.00 |
Feb 22, 2016 | IDA-53680 | Loan Disb | 534,000.00 |
Apr 15, 2016 | IDA-48300 | Loan Disb | 66,299.99 |
Apr 15, 2016 | IDA-53680 | Loan Disb | 23,181.39 |
Feb 15, 2016 | IDA-48300 | Int Charges | 15.44 |
Feb 15, 2016 | IDA-48300 | Int Charges | 15.44 |
Feb 15, 2016 | IDA-53680 | Int Charges | 36,370.68 |
Feb 15, 2016 | IDA-53680 | Int Charges | 36,370.68 |
Feb 15, 2014 | IDA-48300 | Int Charges | 27.11 |
Feb 15, 2014 | IDA-48300 | Int Charges | 27.11 |
Feb 15, 2014 | IDA-48300 | Int Charges | 24,572.32 |
Feb 15, 2014 | IDA-48300 | Int Charges | 24,572.32 |
Apr 4, 2014 | IDA-48300 | Loan Disb | 1,000,000.00 |
Feb 15, 2015 | IDA-48300 | Int Charges | 186.70 |
Feb 15, 2015 | IDA-48300 | Int Charges | 186.70 |
Jan 30, 2015 | IDA-53680 | Loan Disb | 150,000.00 |
Feb 15, 2015 | IDA-53680 | Int Charges | 11,281.19 |
Feb 15, 2015 | IDA-53680 | Int Charges | 11,281.19 |
Aug 15, 2014 | IDA-48300 | Int Charges | 98.84 |
Aug 15, 2014 | IDA-48300 | Int Charges | 98.84 |
Feb 15, 2015 | IDA-48300 | Int Charges | 26,833.10 |
Feb 15, 2015 | IDA-48300 | Int Charges | 26,833.10 |
Sep 12, 2014 | IDA-53680 | Loan Disb | 1,000,000.00 |
Aug 15, 2014 | IDA-48300 | Int Charges | 27,167.79 |
Aug 15, 2014 | IDA-48300 | Int Charges | 27,167.79 |
Aug 26, 2014 | IDA-53680 | Loan Disb | 50,000.00 |
Oct 8, 2013 | IDA-H6220 | Loan Disb | 1,200,000.00 |
Sep 26, 2014 | IDA-53680 | Loan Disb | 300,000.00 |
Oct 17, 2014 | IDA-48300 | Loan Disb | 400,000.00 |
Nov 7, 2014 | IDA-53680 | Loan Disb | 887,117.40 |
Aug 15, 2013 | IDA-48300 | Int Charges | 1,035.80 |
Aug 15, 2013 | IDA-48300 | Int Charges | 1,035.80 |
Aug 15, 2013 | IDA-48300 | Int Charges | 17,690.83 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2016-05-31 |
Overall Implementation Progress (IP) | Satisfactory | 2016-05-31 |
Overall Safeguards Rating | Satisfactory | 2016-05-31 |
Progress towards achievement of PDO | Satisfactory | 2016-05-31 |
Financial Management | Moderately Satisfactory | 2016-05-31 |
Monitoring and Evaluation | Satisfactory | 2016-05-31 |
Procurement | Satisfactory | 2016-05-31 |
Project Management | Satisfactory | 2016-05-31 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-29-2016 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 06-16-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Negligible | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage increase in the provision of first time consultations during the year | Value | P 13%AF1 5%AF 2 14% | P 29% AF1 31% AF2 26% | P 20%AF1 9%AF2 18% |
Date | December 30, 2011 | May 20, 2016 | May 31, 2016 | |
Comment |
Percentage increase in the provision of follow-up health consultations provided during the year for each health facility. | Value | P 22%AF1 23%AF2 47% | P 32% AF1 69% AF2 74% | P 30%AF3 32%AF4 51% |
Date | December 30, 2011 | May 20, 2016 | May 31, 2016 | |
Comment |
Percentage of Pregnancy among adolescent women in the municipalities | Value | P 27.5%AF 26% | P 24% AF 22% | P 27%AF 25% |
Date | December 30, 2011 | May 20, 2016 | May 31, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of Municipal Agreements evaluated satisfactory by the social consultations | Value | P 0%AF 0% | P 100% AF 100% | P 85%AF 75% |
Date | May 20, 2016 | May 31, 2016 | ||
Comment |
Percentage of pregnant women receiving four prenatal checkups in targeted municipal health networks | Value | P 50%AF 74% | P 74%, AF 70% | P 75%AF 76% |
Date | November 2, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |
Percentage of children less than one year old immunized with the Pentavalent vaccine in targeted municipal health networks | Value | P 88%AF 93% | P 100%, AF 97% | P 98.5%AF 96% |
Date | November 2, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |
Percentage of Municipal Agreements with the municipal health networks that have achieved at least 7 of 10 of the performance goals | Value | 0.00 | 84.00 | 84.00 |
Date | November 2, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |
At least 3 hospitals implement the hospital waste management plan satisfactory. | Value | P 0 | P 9 | P 3 |
Date | November 2, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |
Percentage of post-partum women receiving postnatal care within 10 days of delivery in targeted municipal health networks. | Value | P 32%AF 50% | P 65%, AF 73% | P 55%AF 55% |
Date | November 2, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |
Number of facilities in the national Health Networks that completed the process of replacing medical and nonmedical equipment required to re-establish operating capacity | Value | P 0AF 0 | P 12 Hosp, 32 MHN34 MHN | P 12 Hosp32 MHNAF 16 MHN34 MHN |
Date | November 2, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |
Percentage of institutional deliveries in targeted municipal health networks. | Value | P 72%AF 73% | P 93%, AF 88% | P 90%AF 75% |
Date | November 2, 2012 | May 20, 2016 | May 31, 2016 | |
Comment |
Establishment of two mobile regional maintenance centers for medical and nonmedical equipment | Value | P 0 | P 2 | P 2 |
Date | November 2, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |
Percentage of health units with inter-sectoral plans for comprehensive development of adolescent health in all targeted municipalities | Value | P 0 | P 56% | P 25% |
Date | November 2, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |