Financier | Commitments |
---|---|
IDA Credit | 245.00 |
Borrower/Recipient | 63.23 |
P106872
Closed
Haileyesus Mengesha
Federal Ministry of Finance and Economic Cooperation (MoFEC)
November 25, 2008
(as of board presentation)
June 2, 2009
September 14, 2009
US$ 308.23 million
Ethiopian Roads Authority
2009
US$ 245.00 million
A
July 15, 2021
June 30, 2017
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 245.00 |
Borrower/Recipient | 63.23 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 245.00 |
IBRD + IDA Commitment | 245.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 308.23 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2021 | IDA-45610 | Int Charges | 681,644.50 |
Dec 15, 2021 | IDA-45610 | Int Charges | 681,644.50 |
Dec 15, 2022 | IDA-45610 | Loan Repay | 64,078.43 |
Dec 15, 2022 | IDA-45610 | Loan Repay | 1,759,253.50 |
Dec 15, 2022 | IDA-45610 | Int Charges | 535,526.94 |
Dec 15, 2022 | IDA-45610 | Int Charges | 535,526.94 |
Jun 15, 2023 | IDA-45610 | Int Charges | 100,648.15 |
Jun 15, 2023 | IDA-45610 | Int Charges | 100,648.15 |
Jun 15, 2023 | IDA-45610 | Loan Repay | 1,828,565.80 |
Jun 15, 2023 | IDA-45610 | Int Charges | 630,855.10 |
Jun 15, 2023 | IDA-45610 | Int Charges | 630,855.10 |
Dec 15, 2023 | IDA-45610 | Loan Repay | 38,287.00 |
Dec 15, 2023 | IDA-45610 | Loan Repay | 1,798,718.50 |
Dec 15, 2023 | IDA-45610 | Int Charges | 570,150.25 |
Dec 15, 2020 | IDA-45610 | Loan Repay | 1,970,164.60 |
Dec 15, 2020 | IDA-45610 | Int Charges | 328.36 |
Dec 15, 2020 | IDA-45610 | Int Charges | 328.36 |
Dec 15, 2020 | IDA-45610 | Int Charges | 666,662.00 |
Jun 15, 2021 | IDA-45610 | Int Charges | 50,026.80 |
Jun 15, 2021 | IDA-45610 | Int Charges | 50,026.80 |
Jun 15, 2021 | IDA-45610 | Loan Repay | 1,971,795.10 |
Jun 15, 2021 | IDA-45610 | Int Charges | 689,783.44 |
Jun 15, 2021 | IDA-45610 | Int Charges | 689,783.44 |
Jun 15, 2022 | IDA-45610 | Loan Repay | 28,718.43 |
Jun 15, 2022 | IDA-45610 | Loan Repay | 1,795,997.20 |
Jun 15, 2022 | IDA-45610 | Int Charges | 643,212.30 |
Jun 15, 2022 | IDA-45610 | Int Charges | 643,212.30 |
Jun 15, 2019 | IDA-45610 | Loan Repay | 9,689.98 |
Jun 15, 2019 | IDA-45610 | Loan Repay | 1,885,599.10 |
Jun 15, 2019 | IDA-45610 | Int Charges | 710,733.44 |
Jun 15, 2019 | IDA-45610 | Int Charges | 710,733.44 |
Dec 15, 2019 | IDA-45610 | Loan Repay | 13,526.23 |
Dec 15, 2019 | IDA-45610 | Loan Repay | 1,882,804.20 |
Dec 15, 2019 | IDA-45610 | Int Charges | 678,912.70 |
Dec 15, 2019 | IDA-45610 | Int Charges | 678,912.70 |
Jun 23, 2020 | IDA-45610 | Loan Repay | 1,892,795.60 |
Jun 23, 2020 | IDA-45610 | Int Charges | 667,415.56 |
Jun 23, 2020 | IDA-45610 | Int Charges | 667,415.56 |
Jun 23, 2020 | IDA-45610 | Int Charges | 25,053.16 |
Jun 23, 2020 | IDA-45610 | Int Charges | 25,053.16 |
Dec 15, 2020 | IDA-45610 | Int Charges | 666,662.00 |
Dec 15, 2020 | IDA-45610 | Int Charges | 29,339.01 |
Dec 15, 2020 | IDA-45610 | Int Charges | 29,339.01 |
Dec 15, 2017 | IDA-45610 | Int Charges | 752,363.44 |
Dec 15, 2017 | IDA-45610 | Int Charges | 752,363.44 |
Dec 7, 2017 | IDA-45610 | Loan Disb | -4,626,823.00 |
Jan 24, 2018 | IDA-45610 | Loan Disb | -1,842,054.90 |
Dec 15, 2017 | IDA-45610 | Int Charges | 2,196.66 |
Dec 15, 2017 | IDA-45610 | Int Charges | 2,196.66 |
Dec 7, 2017 | IDA-45610 | Loan Disb | -460,269.16 |
Jan 24, 2018 | IDA-45610 | Loan Cancel | 7,066,969.00 |
Jun 15, 2018 | IDA-45610 | Int Charges | 378.87 |
Jun 15, 2018 | IDA-45610 | Int Charges | 378.87 |
Jun 15, 2018 | IDA-45610 | Int Charges | 725,206.50 |
Sep 9, 2013 | IDA-45610 | Loan Disb | 3,015,367.00 |
Sep 10, 2013 | IDA-45610 | Loan Disb | 3,613,491.00 |
Jan 22, 2014 | IDA-45610 | Loan Disb | 4,132,877.50 |
Jun 15, 2018 | IDA-45610 | Int Charges | 725,206.50 |
Dec 15, 2018 | IDA-45610 | Int Charges | 22,301.56 |
Dec 15, 2018 | IDA-45610 | Int Charges | 22,301.56 |
Dec 15, 2018 | IDA-45610 | Int Charges | 686,202.06 |
Dec 15, 2018 | IDA-45610 | Int Charges | 686,202.06 |
Jun 15, 2016 | IDA-45610 | Int Charges | 705,863.80 |
Jun 15, 2016 | IDA-45610 | Int Charges | 705,863.80 |
Jun 15, 2016 | IDA-45610 | Int Charges | 10,783.83 |
Jun 15, 2016 | IDA-45610 | Int Charges | 10,783.83 |
Dec 20, 2016 | IDA-45610 | Loan Disb | 1,856,735.20 |
Jul 11, 2016 | IDA-45610 | Loan Disb | 4,959,461.00 |
Dec 15, 2016 | IDA-45610 | Int Charges | 727,156.56 |
Dec 15, 2016 | IDA-45610 | Int Charges | 727,156.56 |
Dec 15, 2016 | IDA-45610 | Int Charges | 301.17 |
Dec 15, 2016 | IDA-45610 | Int Charges | 301.17 |
Jun 16, 2016 | IDA-45610 | Loan Disb | 4,929,129.00 |
Mar 7, 2017 | IDA-45610 | Loan Disb | 1,900,134.60 |
Apr 25, 2017 | IDA-45610 | Loan Disb | -8,462,517.00 |
Apr 25, 2017 | IDA-45610 | Loan Cancel | 33,012,058.00 |
Jun 20, 2017 | IDA-45610 | Int Charges | 729,777.40 |
Jun 20, 2017 | IDA-45610 | Int Charges | 729,777.40 |
Jun 15, 2017 | IDA-45610 | Int Charges | 21,099.74 |
Jun 15, 2017 | IDA-45610 | Int Charges | 21,099.74 |
Jun 16, 2015 | IDA-45610 | Loan Disb | 4,987,864.50 |
Jun 24, 2015 | IDA-45610 | Loan Disb | 4,465,504.50 |
Jun 30, 2015 | IDA-45610 | Loan Disb | 3,543,411.80 |
Jun 30, 2015 | IDA-45610 | Loan Disb | 1,801,257.10 |
Jun 15, 2015 | IDA-45610 | Int Charges | 4,235.82 |
Jun 15, 2015 | IDA-45610 | Int Charges | 4,235.82 |
Jun 15, 2015 | IDA-45610 | Int Charges | 539,063.30 |
Apr 21, 2015 | IDA-45610 | Loan Disb | 6,607,680.50 |
May 27, 2015 | IDA-45610 | Loan Disb | 4,251,670.50 |
Dec 16, 2015 | IDA-45610 | Int Charges | 21,517.79 |
Dec 16, 2015 | IDA-45610 | Int Charges | 21,517.79 |
Dec 16, 2015 | IDA-45610 | Int Charges | 667,398.06 |
Dec 16, 2015 | IDA-45610 | Int Charges | 667,398.06 |
Nov 10, 2015 | IDA-45610 | Loan Disb | 5,311,714.50 |
Jan 8, 2016 | IDA-45610 | Loan Disb | 4,543,188.50 |
Mar 30, 2016 | IDA-45610 | Loan Disb | 4,349,841.00 |
Feb 21, 2014 | IDA-45610 | Loan Disb | 4,608,444.00 |
May 12, 2014 | IDA-45610 | Loan Disb | 10,136,750.00 |
Apr 15, 2014 | IDA-45610 | Loan Disb | 6,083,734.00 |
Mar 31, 2014 | IDA-45610 | Loan Disb | 4,015,689.00 |
May 12, 2014 | IDA-45610 | Loan Disb | 1,974,379.50 |
Jun 15, 2014 | IDA-45610 | Int Charges | 2,840.81 |
Jun 15, 2014 | IDA-45610 | Int Charges | 2,840.81 |
Jun 23, 2014 | IDA-45610 | Loan Disb | 10,060,434.00 |
Dec 15, 2014 | IDA-45610 | Int Charges | 513,593.88 |
Dec 15, 2014 | IDA-45610 | Int Charges | 513,593.88 |
Jun 15, 2014 | IDA-45610 | Int Charges | 416,426.62 |
Jun 15, 2014 | IDA-45610 | Int Charges | 416,426.62 |
Dec 15, 2014 | IDA-45610 | Int Charges | 12,848.57 |
Dec 15, 2014 | IDA-45610 | Int Charges | 12,848.57 |
Mar 3, 2015 | IDA-45610 | Loan Disb | 4,256,741.50 |
Jan 20, 2015 | IDA-45610 | Loan Disb | 7,292,738.00 |
Apr 1, 2015 | IDA-45610 | Loan Disb | 4,015,565.20 |
Jun 15, 2015 | IDA-45610 | Int Charges | 539,063.30 |
Dec 15, 2013 | IDA-45610 | Int Charges | 7,062.41 |
Dec 15, 2013 | IDA-45610 | Int Charges | 354,982.90 |
Dec 15, 2013 | IDA-45610 | Int Charges | 354,982.90 |
Dec 15, 2013 | IDA-45610 | Int Charges | 7,062.41 |
Dec 30, 2013 | IDA-45610 | Loan Disb | 2,066,590.40 |
Nov 19, 2013 | IDA-45610 | Loan Disb | 1,800,869.50 |
Nov 20, 2014 | IDA-45610 | Loan Disb | 7,649,210.50 |
Dec 15, 2023 | IDA-45610 | Int Charges | 570,150.25 |
Jun 15, 2024 | IDA-45610 | Int Charges | 55,747.50 |
Jun 15, 2024 | IDA-45610 | Int Charges | 55,747.50 |
Jun 15, 2024 | IDA-45610 | Loan Repay | 1,805,260.40 |
Jun 15, 2024 | IDA-45610 | Int Charges | 606,931.94 |
Jun 15, 2024 | IDA-45610 | Int Charges | 606,931.94 |
Jun 2, 2009 | IDA-45610 | Loan Commitment | 245,000,000.00 |
Dec 15, 2021 | IDA-45610 | Int Charges | 19,468.48 |
Dec 15, 2021 | IDA-45610 | Int Charges | 19,468.48 |
Dec 15, 2021 | IDA-45610 | Loan Repay | 1,913,388.10 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2017-06-23 |
Financial Management | Moderately Satisfactory | 2017-06-23 |
Counterpart Funding | Satisfactory | 2017-06-23 |
Progress towards achievement of PDO | Satisfactory | 2017-06-23 |
Project Management | Satisfactory | 2017-06-23 |
Monitoring and Evaluation | Satisfactory | 2017-06-23 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-06-23 |
Overall Safeguards Rating | Moderately Satisfactory | 2017-06-23 |
Overall Safeguards Rating | Moderately Satisfactory | 2017-06-23 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-29-2018 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 11-06-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Average travel time (minutes/km) | Value | 2.50 | 1.00 | 1.00 |
Date | May 1, 2009 | June 30, 2017 | June 30, 2017 | |
Comment |
Share of rural population with access to an all-season road | Value | 20.00 | 57.00 | 57.00 |
Date | June 1, 2009 | June 16, 2017 | June 30, 2017 | |
Comment |
Roads in good and fair condition as a share of total classified roads | Value | 65.00 | 80.00 | 86.00 |
Date | June 30, 2008 | June 16, 2017 | June 30, 2017 | |
Comment |
Welkite - Hosaina | Value | 2.50 | 1.00 | 1.00 |
Date | May 1, 2009 | June 16, 2017 | June 30, 2017 | |
Comment |
Mekenajo - Dembi Dolo | Value | 3.00 | 1.00 | 1.00 |
Date | May 1, 2009 | June 16, 2017 | June 30, 2017 | |
Comment |
Number of rural people with access to an all-season road | Value | 12580000.00 | 43525200.00 | 43525200.00 |
Date | June 1, 2009 | June 16, 2017 | June 30, 2017 | |
Comment |
Size of the total classified network | Value | 14363.00 | 113213.00 | 113213.00 |
Date | June 30, 2008 | June 16, 2017 | June 30, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Poverty impact assessments implemented | Value | 3.00 | 4.00 | 4.00 |
Date | May 1, 2009 | June 16, 2017 | June 30, 2017 | |
Comment |
Roads rehabilitated, Non-rural | Value | 0.00 | 302.00 | 302.00 |
Date | May 1, 2009 | June 16, 2017 | June 30, 2017 | |
Comment |
Contracts completed within contract period and budget | Value | 0.00 | 60.00 | 60.00 |
Date | May 1, 2009 | June 16, 2017 | June 30, 2017 | |
Comment |
Preparatory study for a Highway Engineering Research Center completed and implementation of agreed organizational option commenced | Value | not yet started | Implementation commenced | Implementation of research programs commenced in 2 |
Date | May 1, 2009 | June 16, 2017 | June 30, 2017 | |
Comment |
Road traffic census program and comprehensive road safety program established | Value | No | Yes | Yes |
Date | May 1, 2009 | June 30, 2016 | June 30, 2017 | |
Comment |
Comprehensive Capacity Building Program activities implemented | Value | 0.00 | 100.00 | 100.00 |
Date | May 1, 2009 | June 16, 2017 | June 30, 2017 | |
Comment |
Road maintenance and financing needs for the coming 10 years projected (ETB million) | Value | 1070.00 | 1720.00 | 1450.00 |
Date | June 30, 2008 | June 30, 2016 | June 30, 2017 | |
Comment |