Energy Community of South East Europe APL 3 - Montenegro Project

Abstract*

The objective of the Energy Community of South East Europe Third Adaptable Program Loan (ECSEE APL3) Project in Montenegro is to improve the efficiency and reliability of the power system in Montenegro, through better supply security and closer integration into the regional markets. It will consist of three components. Component 1, telecommunications system development, focuses on development of a modern telecommunications network, including links...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of ECSEE APL is the development of a functioning regional electricity market in South East Europe and its integration into the internal electricity market of the European Union, through the implementation of priority investments supporting electricity market and power system operations in electricity generation, transmission and distribution as well as technical assistance for institutional/systems development and project preparation and implementation. Within the overall ECSEE APL objectives/context, this project (ECSEE APL 3 - Montenegro) would provide investment support to EPCG, the Electric Power Utility of Montenegro. Specifically, the objective of the ECSEE APL3-Montenegro project is to improve the efficiency and reliability of the power system in Montenegro, through better supply security and closer integration into the regional markets. The ECSEE APL 3 - Montenegro Project consists of the following components: I. Telecommunications System Development II. Transmission Network Reinforcement III. Improvement of Operational Reliability of Perucica HPP

Key Details

Project Details

  • P106899

  • Closed

  • Gazmend Daci

  • N/A

  • Montenegro

  • July 6, 2007

  • (as of board presentation)

    July 6, 2007

  • January 28, 2008

  • US$ 9.00 million

  • B

  • October 2, 2023

  • September 30, 2013

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 9.00
Borrower/Recipient 7.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 9.00
IBRD + IDA Commitment 9.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 16.50

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 15, 2018 IDA-43510 Int Charges 21,122.07
May 15, 2018 IDA-43510 Int Charges 480.58
May 15, 2018 IDA-43510 Int Charges 480.58
May 15, 2018 IDA-43510 Loan Repay 415,474.88
Nov 15, 2018 IDA-43510 Int Charges 8,204.07
Nov 15, 2013 IDA-43510 Int Charges 137.83
Nov 15, 2013 IDA-43510 Int Charges 137.83
May 15, 2014 IDA-43510 Int Charges 28.21
May 15, 2014 IDA-43510 Int Charges 28.21
May 15, 2014 IDA-43510 Int Charges 33,268.24
May 15, 2014 IDA-43510 Int Charges 33,268.24
Sep 30, 2013 IDA-43510 Loan Disb 103,429.51
Nov 15, 2013 IDA-43510 Int Charges 31,925.07
Nov 15, 2013 IDA-43510 Int Charges 31,925.07
Nov 15, 2014 IDA-43510 Int Charges 363.04
Nov 15, 2014 IDA-43510 Int Charges 363.04
Nov 15, 2014 IDA-43510 Int Charges 31,508.34
Nov 15, 2014 IDA-43510 Int Charges 31,508.34
Sep 13, 2013 IDA-43510 Loan Disb 6,344.26
Sep 16, 2013 IDA-43510 Loan Disb 12,985.10
Aug 8, 2013 IDA-43510 Loan Disb 142,878.90
Sep 10, 2013 IDA-43510 Loan Disb 67,731.67
Dec 31, 2013 IDA-43510 Loan Cancel 280,157.30
Oct 8, 2013 IDA-43510 Loan Disb 148,782.55
Nov 15, 2023 IDA-43510 Loan Repay 6,089.49
Nov 15, 2023 IDA-43510 Loan Repay 379,751.00
Nov 15, 2023 IDA-43510 Int Charges 11,575.22
Nov 15, 2023 IDA-43510 Int Charges 11,575.22
May 15, 2024 IDA-43510 Loan Repay 5,479.96
May 15, 2024 IDA-43510 Loan Repay 379,479.10
May 15, 2024 IDA-43510 Int Charges 10,105.16
May 15, 2024 IDA-43510 Int Charges 10,105.16
Jul 6, 2007 IDA-43510 Loan Commitment 9,000,000.00
Nov 15, 2022 IDA-43510 Int Charges 8,479.54
Nov 15, 2022 IDA-43510 Int Charges 8,479.54
Nov 15, 2022 IDA-43510 Loan Repay 382,820.90
Nov 15, 2022 IDA-43510 Int Charges 14,355.79
Nov 15, 2022 IDA-43510 Int Charges 14,355.79
May 15, 2023 IDA-43510 Loan Repay 379,314.22
May 15, 2023 IDA-43510 Int Charges 13,182.21
May 15, 2023 IDA-43510 Int Charges 13,182.21
May 15, 2023 IDA-43510 Loan Repay 11,270.91
Nov 15, 2020 IDA-43510 Loan Repay 413,031.28
Nov 15, 2020 IDA-43510 Int Charges 2,038.56
Nov 15, 2020 IDA-43510 Int Charges 2,038.56
Nov 15, 2020 IDA-43510 Int Charges 103.26
Nov 15, 2020 IDA-43510 Int Charges 103.26
Nov 15, 2020 IDA-43510 Int Charges 17,720.36
Nov 15, 2020 IDA-43510 Int Charges 17,720.36
May 15, 2021 IDA-43510 Int Charges 20,402.98
May 15, 2021 IDA-43510 Int Charges 20,402.98
May 15, 2021 IDA-43510 Int Charges 4,016.49
May 15, 2021 IDA-43510 Int Charges 4,016.49
May 15, 2021 IDA-43510 Loan Repay 418,523.56
Nov 15, 2021 IDA-43510 Loan Repay 3,437.16
Nov 15, 2021 IDA-43510 Loan Repay 405,262.56
Nov 15, 2021 IDA-43510 Int Charges 10,997.33
Nov 15, 2021 IDA-43510 Int Charges 10,997.33
May 15, 2022 IDA-43510 Int Charges 7,003.86
May 15, 2022 IDA-43510 Int Charges 7,003.86
May 15, 2022 IDA-43510 Loan Repay 387,126.28
May 15, 2022 IDA-43510 Int Charges 7,394.04
May 15, 2022 IDA-43510 Int Charges 7,394.04
May 15, 2019 IDA-43510 Int Charges 24,008.24
May 15, 2019 IDA-43510 Int Charges 24,008.24
May 15, 2019 IDA-43510 Int Charges 8,068.00
May 15, 2019 IDA-43510 Int Charges 8,068.00
May 15, 2019 IDA-43510 Loan Repay 402,125.30
Nov 15, 2019 IDA-43510 Loan Repay 399,850.44
Nov 15, 2019 IDA-43510 Int Charges 21,315.27
Nov 15, 2019 IDA-43510 Int Charges 21,315.27
Nov 15, 2019 IDA-43510 Int Charges 1,618.03
Nov 15, 2019 IDA-43510 Int Charges 1,618.03
May 27, 2020 IDA-43510 Int Charges 20,405.49
May 27, 2020 IDA-43510 Int Charges 20,405.49
May 27, 2020 IDA-43510 Int Charges 2,661.08
May 27, 2020 IDA-43510 Int Charges 2,661.08
May 27, 2020 IDA-43510 Loan Repay 397,657.00
Nov 15, 2017 IDA-43510 Loan Repay 410,475.97
Nov 15, 2017 IDA-43510 Int Charges 30,351.80
Nov 15, 2017 IDA-43510 Int Charges 30,351.80
Nov 15, 2017 IDA-43510 Loan Repay 553.90
May 15, 2018 IDA-43510 Int Charges 21,122.07
Nov 15, 2018 IDA-43510 Int Charges 8,204.07
Nov 15, 2018 IDA-43510 Loan Repay 401,933.30
Nov 15, 2018 IDA-43510 Int Charges 19,066.36
Nov 15, 2018 IDA-43510 Int Charges 19,066.36
May 15, 2016 IDA-43510 Int Charges 841.59
May 15, 2016 IDA-43510 Int Charges 841.59
May 15, 2016 IDA-43510 Int Charges 30,784.26
May 15, 2016 IDA-43510 Int Charges 30,784.26
Nov 15, 2016 IDA-43510 Int Charges 330.16
Nov 15, 2016 IDA-43510 Int Charges 330.16
Nov 15, 2016 IDA-43510 Int Charges 28,934.39
Nov 15, 2016 IDA-43510 Int Charges 28,934.39
May 15, 2017 IDA-43510 Int Charges 487.53
May 15, 2017 IDA-43510 Int Charges 487.53
May 15, 2017 IDA-43510 Int Charges 29,898.24
May 15, 2017 IDA-43510 Int Charges 29,898.24
May 15, 2015 IDA-43510 Int Charges 420.80
May 15, 2015 IDA-43510 Int Charges 420.80
May 15, 2015 IDA-43510 Int Charges 30,893.57
May 15, 2015 IDA-43510 Int Charges 30,893.57
Nov 15, 2015 IDA-43510 Int Charges 28,204.42
Nov 15, 2015 IDA-43510 Int Charges 28,204.42
Nov 15, 2015 IDA-43510 Int Charges 1,167.61
Nov 15, 2015 IDA-43510 Int Charges 1,167.61

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2013-09-27
Overall Safeguards Rating Satisfactory 2013-09-27
Financial Management Satisfactory 2013-09-27
Monitoring and Evaluation Satisfactory 2013-09-27
Overall Low 2013-09-27
Overall Implementation Progress (IP) Moderately Satisfactory 2013-09-27
Counterpart Funding Satisfactory 2013-09-27
Procurement Satisfactory 2013-09-27
Project Management Moderately Satisfactory 2013-09-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-13-2014
Outcomes
Risk to Development OutcomeSubstantial
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-28-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • ECSEE APL INDICATOR: Market Liberalization in the regional marketValueECSEE Treaty signed in October 2005Partially AchievedFully liberalized power market and competitive mar
    DateOctober 25, 2005May 31, 2013September 30, 2013
    CommentWith regard to market liberalization, the Law envisages that all household customers will become eligible to choose their supplierin 2015. Non-household customers (32,300 or 10% of all customers) are currently eligible to switch suppliers. The EnergyRegulatory Agency made a decision that from January 1, 2013 the customers connected to transmission network, are obligated toswitch to othersuppliers. There are two customers which consume one-third of the total yearly electricity supply in Montenegro.
  • The integration of Montenegro into the regional power sector is improved as a result of the improved telecommunications systemValueExisting EPCG telecommunications system is outdate100% AchievedMontenegro system fully integrated with regional m
    DateDecember 31, 2006May 31, 2013September 30, 2013
    CommentThe new telecommunication links are established with Bosnia&Herzegovina and Serbia. The new system enables moderntelecommunication for the existing SCADA system, for integration in the regional market and the connection with ENTSO-E operationfacilities.After the finalization of component 1 of the project a total of total 550 km OPGW and 26 pieces telecommunication equipment willbeinstalled and will be in operation. Three international links will be established.
  • The substations of component 2 have fewer blackoutsValue2006 Interruptions (baseline document to be provi100% AchievedReduce interruptions by 50%
    DateDecember 31, 2006May 31, 2013September 30, 2013
    CommentSince August 2011, the extension of Andrijevica substation was in operation. The quality of supply (voltage profile and powerinterruptions) in the area has significantly improved. In 2012, there were only 5 outages with interruption of 921 minutes and theundelivered electricity was estimated at 59 MWh.Since August 2013, the extension of Mojkovac substation was in operation. Thequality ofsupply (voltage profile and power interruptions) in the area is improved; however the new results have to be verified bythe end of2013.Data provided for operation year 2010.In Andrijevica area were reported 23 outages with interruption of 757 minutes; theundelivered electricity was estimated 54 MWh.In Mojokovac area were reported 5 outages with interruption of 588 minutes; theundelivered electricity was estimated 39 MWhData provided for operation year 2011.In Andrijevica area were reported 31 outageswith interruptionof 6073 minutes; the undelivered electricity was estimated 414 MWh.In Mojokovac area were reported 9 outages withinterruption of 445 minutes; the undelivered electricity was estimated 43 MWh.Data provided for operation year 2012. InAndrijevica area were reported 5 outages with interruption of 921 minutes; the undelivered electricity was estimated 59 MWh.TargetachievedIn Mojokovac areawere reported 11 outages with interruption of 3291 minutes; the undelivered electricity was estimated 385MWh.
  • Operational reliability of Perucica HPP is improved by: (1) reducing O&M cost for the turbine runners (2) reduce outage time for turbine runnersValue(1) Increase in O& M of runners due to runners pro100% Achieved(1) O&M cost of runner is reduced by 10%(2) Outag
    DateDecember 31, 2006May 31, 2013December 31, 2012
    CommentThe O&M costs of the replaced runner was estimated at Euro 11,000 for 2012; the costs are reduced by 20% compared to 2006.ThenewTurbine Runner (unit-Nb7) has been in operation since September 2011. The new runner worked for 2,315 hours generating 168GWh.Theoutages are reduced by 20%.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Progress in implementation of the telecommunications componentValueNil100% AchievedComponent is 100% implemented
    DateDecember 31, 2006May 31, 2013September 30, 2013
    CommentThe new telecommunication system comprises the inter telecommunication links with Bosnia&Herzegovina and Serbia and internaltelecommunication links. The new system is completed and fully functional.The telecommunication link with Kosovo has to beestablished.
  • Progress in implementation of the transmission componentValue100% Achieved.Component is 100% implemented
    DateMay 31, 2013September 30, 2013
    Comment(i) The construction of the 110 kV line and the extension of Andrijevica substation were completed and the sub-project was inoperation since August 24, 2011.(ii) The construction of 220 kV line and extension of Mojkovac substation were completed and thesub-project was in trial operation since August 1, 2013.
  • Progress in implementation of the HPP Perucica generation componentValueNil100% AchievedComponent is 100% implemented
    DateDecember 31, 2006May 31, 2013March 30, 2013
    Comment(i) The new trash rack and trash rack cleaning machine are installed in the plant's bottom outlet in Vrtac Dam and have been inoperation since December 2009.(ii) The new turbine runner is installed in power plant unit 7 and has been in operation sinceSeptember2011.