Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 120.00 |
Borrower/Recipient | 30.00 |
P107146
Closed
Johannes Jansen , Luis Alvestegui Justiniano
STATE OF ACRE
May 6, 2008
(as of board presentation)
December 18, 2008
January 30, 2009
US$ 150.00 million
Secretaria de Estado de Planejamento e Gestão - SEPLAG
2009
US$ 120.00 million
A
Not Applicable
December 31, 2021
BANK APPROVED
November 3, 2022
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 120.00 |
Borrower/Recipient | 30.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 120.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 120.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 15, 2024 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Jun 15, 2024 | IBRD-84420 | Int Charges | 13,651.86 |
Jun 15, 2024 | IBRD-84420 | Int Charges | 2,161,918.80 |
Jun 15, 2024 | IBRD-84420 | Loan Repay | 2,145,496.00 |
Sep 29, 2014 | IBRD-84420 | Loan Commitment | 150,000,000.00 |
Dec 18, 2008 | IBRD-76250 | Loan Commitment | 120,000,000.00 |
Jun 15, 2023 | IBRD-84420 | Int Charges | 93,351.17 |
Jun 15, 2023 | IBRD-84420 | Int Charges | 1,886,812.20 |
Jun 15, 2023 | IBRD-84420 | Loan Repay | 165,332.45 |
Jun 15, 2023 | IBRD-84420 | Loan Repay | 1,980,163.50 |
Oct 15, 2023 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Oct 15, 2023 | IBRD-76250 | Int Charges | 2,088,701.80 |
Dec 15, 2023 | IBRD-84420 | Int Charges | 37,654.27 |
Dec 15, 2023 | IBRD-84420 | Int Charges | 2,102,513.50 |
Dec 15, 2023 | IBRD-84420 | Loan Repay | 2,145,496.00 |
Apr 15, 2024 | IBRD-76250 | Int Charges | 2,168,454.50 |
Sep 16, 2021 | IBRD-84420 | Loan Cancel | 50,000,000.00 |
Oct 15, 2022 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Oct 15, 2022 | IBRD-76250 | Int Charges | 851,426.70 |
Dec 15, 2021 | IBRD-84420 | Loan Repay | 300,897.88 |
Apr 15, 2023 | IBRD-76250 | Int Charges | 1,880,461.40 |
Apr 15, 2023 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Dec 15, 2022 | IBRD-84420 | Int Charges | 1,320,473.50 |
Dec 15, 2022 | IBRD-84420 | Loan Repay | 825,022.44 |
Dec 15, 2022 | IBRD-84420 | Loan Repay | 1,320,473.50 |
Apr 15, 2022 | IBRD-76250 | Int Charges | 346,574.03 |
Apr 15, 2022 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Aug 5, 2022 | IBRD-84420 | Loan Disb | -1,079,736.00 |
Aug 5, 2022 | IBRD-84420 | Loan Disb | -31,098.32 |
Dec 15, 2021 | IBRD-84420 | Int Charges | 300,897.88 |
Dec 15, 2021 | IBRD-84420 | Loan Repay | 1,877,267.90 |
Aug 5, 2022 | IBRD-84420 | Loan Cancel | 15,254,618.00 |
Jun 15, 2021 | IBRD-84420 | Loan Repay | 2,035,189.00 |
Jun 15, 2021 | IBRD-84420 | Int Charges | 323,623.84 |
Apr 15, 2021 | IBRD-76250 | Int Charges | 406,226.34 |
Apr 15, 2021 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Jun 15, 2018 | IBRD-84420 | Int Charges | 10,056.32 |
Jun 15, 2018 | IBRD-84420 | Int Charges | 557,631.75 |
Oct 15, 2016 | IBRD-76250 | Loan Repay | 2,781,010.00 |
Dec 30, 2016 | IBRD-76250 | Loan Cancel | 3,150,844.50 |
Jul 19, 2016 | IBRD-84420 | Loan Disb | 582,301.50 |
Dec 15, 2016 | IBRD-84420 | Int Charges | 18,781.44 |
Dec 15, 2016 | IBRD-84420 | Int Charges | 105,123.21 |
May 12, 2017 | IBRD-84420 | Loan Disb | 15,000,000.00 |
Jun 26, 2017 | IBRD-84420 | Int Charges | 476.00 |
Jun 26, 2017 | IBRD-84420 | Int Charges | 152,400.23 |
Apr 15, 2017 | IBRD-76250 | Int Charges | 1,130,862.80 |
Apr 15, 2017 | IBRD-76250 | Loan Repay | 2,781,010.00 |
Sep 22, 2017 | IBRD-76250 | Loan Cancel | 6,700,279.50 |
Oct 15, 2017 | IBRD-76250 | Int Charges | 1,182,150.90 |
Oct 15, 2017 | IBRD-76250 | Loan Repay | 2,781,010.00 |
Sep 22, 2017 | IBRD-76250 | Loan Disb | -6,700,279.50 |
Apr 15, 2015 | IBRD-76250 | Int Charges | 556,435.00 |
Oct 15, 2015 | IBRD-76250 | Int Charges | 689,020.50 |
Mar 24, 2016 | IBRD-84420 | Loan Disb | 375,000.00 |
Mar 24, 2016 | IBRD-84420 | Fee Charges | 375,000.00 |
Apr 25, 2016 | IBRD-84420 | Loan Disb | 9,000,000.00 |
Jul 18, 2016 | IBRD-84420 | Loan Disb | 1,758,346.90 |
Jul 18, 2016 | IBRD-84420 | Loan Disb | 428,153.53 |
Apr 29, 2016 | IBRD-84420 | Loan Disb | 658,521.20 |
Apr 15, 2016 | IBRD-76250 | Int Charges | 754,358.70 |
Apr 15, 2016 | IBRD-76250 | Loan Repay | 2,781,010.00 |
Oct 15, 2016 | IBRD-76250 | Int Charges | 956,746.56 |
Jun 15, 2016 | IBRD-84420 | Int Charges | 1,193.13 |
Aug 17, 2016 | IBRD-84420 | Loan Disb | 3,609,370.50 |
Oct 26, 2016 | IBRD-84420 | Loan Disb | 243,060.60 |
Nov 5, 2014 | IBRD-76250 | Loan Disb | 7,134,289.50 |
Oct 15, 2014 | IBRD-76250 | Int Charges | 488,175.88 |
Oct 15, 2013 | IBRD-76250 | Int Charges | 9,796.33 |
Oct 15, 2013 | IBRD-76250 | Int Charges | 542,924.56 |
Apr 15, 2014 | IBRD-76250 | Int Charges | 503,658.12 |
Feb 12, 2015 | IBRD-76250 | Loan Disb | 19,962,902.00 |
Sep 13, 2021 | IBRD-84420 | Loan Disb | 5,143,048.00 |
Oct 15, 2021 | IBRD-76250 | Int Charges | 383,829.72 |
Oct 15, 2021 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Jun 15, 2022 | IBRD-84420 | Int Charges | 358,453.66 |
Jun 15, 2022 | IBRD-84420 | Loan Repay | 1,819,712.10 |
Jun 15, 2022 | IBRD-84420 | Loan Repay | 358,453.66 |
Apr 15, 2020 | IBRD-76250 | Int Charges | 1,184,748.00 |
Apr 15, 2020 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Jun 15, 2020 | IBRD-84420 | Int Charges | 827,948.44 |
Jun 15, 2020 | IBRD-84420 | Loan Repay | 1,683,985.80 |
Oct 15, 2020 | IBRD-76250 | Int Charges | 834,007.70 |
Oct 15, 2020 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Dec 15, 2020 | IBRD-84420 | Int Charges | 50,595.83 |
Dec 15, 2020 | IBRD-84420 | Int Charges | 397,103.12 |
Dec 15, 2020 | IBRD-84420 | Loan Repay | 2,035,189.00 |
Apr 15, 2019 | IBRD-76250 | Int Charges | 1,549,155.50 |
Apr 15, 2019 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Oct 15, 2019 | IBRD-76250 | Int Charges | 1,509,951.60 |
Oct 15, 2019 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Dec 15, 2019 | IBRD-84420 | Int Charges | 999,838.50 |
Dec 15, 2019 | IBRD-84420 | Loan Repay | 1,683,985.80 |
Apr 21, 2020 | IBRD-84420 | Loan Disb | 13,353,736.00 |
Nov 30, 2018 | IBRD-84420 | Loan Disb | 9,571,188.00 |
Dec 27, 2018 | IBRD-84420 | Int Charges | 889,602.56 |
Oct 15, 2018 | IBRD-76250 | Int Charges | 1,416,783.10 |
Oct 15, 2018 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Oct 15, 2018 | IBRD-76250 | Int Charges | 108,573.16 |
Jun 15, 2019 | IBRD-84420 | Int Charges | 12,243.15 |
Jun 15, 2019 | IBRD-84420 | Int Charges | 1,188,482.40 |
Nov 7, 2017 | IBRD-84420 | Loan Disb | 888,689.20 |
Feb 15, 2018 | IBRD-76250 | Loan Cancel | 3,614,187.50 |
Dec 15, 2017 | IBRD-84420 | Int Charges | 25,641.66 |
Dec 15, 2017 | IBRD-84420 | Int Charges | 316,995.97 |
Dec 5, 2017 | IBRD-84420 | Loan Disb | 15,000,000.00 |
Feb 15, 2018 | IBRD-76250 | Loan Disb | -3,614,187.50 |
Apr 15, 2018 | IBRD-76250 | Int Charges | 1,124,190.60 |
Apr 15, 2018 | IBRD-76250 | Loan Repay | 2,509,696.50 |
Apr 15, 2018 | IBRD-76250 | Int Charges | 3,730.65 |
Jun 29, 2018 | IBRD-84420 | Loan Disb | 10,244,800.00 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Moderately Unsatisfactory | 2021-06-30 |
Financial Management | Moderately Satisfactory | 2021-06-30 |
Monitoring and Evaluation | Moderately Satisfactory | 2021-06-30 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2021-06-30 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2021-06-30 |
Procurement | Moderately Unsatisfactory | 2021-06-30 |
Counterpart Funding | Satisfactory | 2021-06-30 |
Project Management | Moderately Satisfactory | 2021-06-30 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2021-06-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2022 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-12-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of beneficiaries satisfied with support and extension services for productive inclusion activities | Value | 0.00 | 83.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | December 31, 2021 | |
Comment |
Increase the percentage of surviving newborns with low weight at birth in Acre’s hospitals from 90% to 96% | Value | 90.00 | 96.00 | 0.00 |
Date | January 1, 2008 | January 30, 2015 | ||
Comment |
Increase the general ambulatory consultancies in excluded target population (CAU and CAP) from 7% to 67% | Value | 7.00 | 67.00 | 0.00 |
Date | January 1, 2008 | January 30, 2015 | ||
Comment |
Increased population in isolated areas with improved urban environment from 0 in 2013 to 19,470 people in 2021 | Value | 0.00 | 16401.00 | 0.00 |
Date | March 27, 2013 | December 31, 2021 | December 31, 2021 | |
Comment |
60% of beneficiaries satisfied with Project support and extension services for productive inclusion activities | Value | 0.00 | 60.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
People who received at least one of the services related to drinking water, sanitation or micro-drainage | Value | 0.00 | 16401.00 | 19470.00 |
Date | December 31, 2013 | December 31, 2021 | December 31, 2021 | |
Comment |
Improvements in the Basic Education Development Index (IDEB) of State schools for early fundamentaI education from 5.5 in 2015 to 6.4 in 2021 | Value | 3.80 | 5.50 | 6.40 |
Date | December 31, 2007 | January 22, 2020 | December 31, 2021 | |
Comment |
Improvement of the Basic Education Development Index (IDEB) of of State schools for final fundamentaI education from 4.7 in 2015 to5.3 in 2021 | Value | 3.80 | 4.70 | 5.30 |
Date | December 31, 2007 | January 22, 2020 | December 31, 2021 | |
Comment |
Reduction in Infant Mortality Rate from 17.29 in 2015 to 12.85 in 2021 | Value | 17.29 | 17.89 | 15.45 |
Date | December 31, 2015 | December 31, 2021 | December 31, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
250 Demonstration Units receiving Project support operational | Value | 0.00 | 0.00 | 250.00 |
Date | December 31, 2008 | June 6, 2019 | March 31, 2020 | |
Comment |
Percentage of activities financed in the area of ??entrepreneurship development for excluded urban communities in operation | Value | 0.00 | 60.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Better Project Management, Monitoring and Information Systems | Value | 2 | 5 | |
Date | January 1, 2014 | December 31, 2021 | ||
Comment |
125 rural schools benefiting from the implementation of school subprojects. | Value | 0.00 | 125.00 | 0.00 |
Date | December 31, 2016 | December 31, 2021 | ||
Comment |
Number of people benefiting from river access | Value | 0.00 | 20752.00 | 20752.00 |
Date | December 31, 2013 | December 31, 2021 | December 31, 2021 | |
Comment |
Number of 6th to 9th grade teachers and coordinators in urban state schools who received training | Value | 0.00 | 1500.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Assess 93,000 students in the 3rd, 5th and 9th grade of elementary school and students in the 3rd grade of high school based on writing skills | Value | 0.00 | 93000.00 | 0.00 |
Date | January 1, 2016 | December 31, 2021 | ||
Comment |
At least 60% of the productive subprojects financed by the project remain in operation at project closing | Value | 0.00 | 60.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Kilometers of paved public roads with curbs constructed | Value | 0.00 | 34.22 | 25.96 |
Date | December 31, 2013 | December 31, 2020 | December 31, 2021 | |
Comment |
Number of high school teachers and coordinators in urban state schools who received training | Value | 0.00 | 800.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Implement the Human Resources System and perform payroll auditing as people management instruments, increasing the efficiency of public spending | Value | No HR system | System in place | |
Date | January 1, 2016 | December 31, 2021 | ||
Comment |
Maintain at least 95% satisfactory samples of PCCU collections, carried out by the Itinerant Health Program team. | Value | 96.31 | 95.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Number of EJA (teaching youth and adults program) teachers and coordinators in elementary schools and high schools who received training | Value | 0.00 | 800.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Increase from 2,025, in 2013, to 4,503, in 2021, the number of households with piped treated water. | Value | 2025.00 | 4503.00 | 0.00 |
Date | January 1, 2013 | December 31, 2021 | ||
Comment |
Number of Environmental Inspection operations (air, land and river) performed. | Value | 0.00 | 35.00 | 0.00 |
Date | December 31, 2019 | December 31, 2021 | ||
Comment |
Increase in data transfer capacity of Rio Branco public units connected to the network | Value | 0.10 | 10.00 | 0.00 |
Date | December 31, 2019 | December 31, 2021 | ||
Comment |
Number of Integrated Environment Centers and Integrated Management Units strengthened | Value | 0.00 | 6.00 | 0.00 |
Date | January 1, 2021 | December 31, 2021 | ||
Comment |
Improved micro-drainage services benefiting 19,470 urban inhabitants (urban population from the four municipalities) | Value | 0.00 | 19470.00 | 0.00 |
Date | March 31, 2016 | December 31, 2021 | ||
Comment |
Serve 20,000 students in urban areas with the Quero Ler read program; (cumulative goal) | Value | 0.00 | 0.00 | 0.00 |
Date | December 31, 2015 | January 21, 2020 | ||
Comment |
Increased data processing capacity in the state's enterprise systems infrastructure | Value | 8601.00 | 93331.00 | 0.00 |
Date | December 31, 2019 | December 31, 2021 | ||
Comment |
Number of Indigenous Land Management Plans (PGTIs) developed | Value | 0.00 | 17.00 | 29.00 |
Date | December 31, 2008 | December 31, 2021 | December 31, 2021 | |
Comment |
Preschool care (4-5 years) for 2,000 children/year of Early Childhood in Rural Education (Asinha da Florestania) | Value | 0.00 | 276.00 | 1000.00 |
Date | December 31, 2015 | December 31, 2021 | December 31, 2021 | |
Comment |
Number of high school students benefiting from full-time school studies | Value | 0.00 | 2800.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Increased storage capacity for critical state data in a secure environment | Value | 40.00 | 40.00 | 0.00 |
Date | December 31, 2019 | June 15, 2021 | ||
Comment |
Cumulative number of cultural spaces in the state established/renovated | Value | 0.00 | 9.00 | 6.00 |
Date | December 31, 2017 | December 31, 2021 | December 31, 2020 | |
Comment |
Percentage of subprojects financed in the area of commercialization of agricultural and forestry products (IPCs, PRA and productionsubprojects) in operation at project closing | Value | 0.00 | 60.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Schooling for 5,000 students/year (1st to 5th grade) in the Pathways of Field Education Program (Multigrade Classes). | Value | 0.00 | 5000.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Improved Project Management, Monitoring and Information Systems | Value | 2.00 | 5.00 | 0.00 |
Date | December 31, 2013 | December 31, 2021 | ||
Comment |
Net enrollment for 5,000 students/year (6th to 9th grade) - Programa Caminhos da educação do campo - elementary school final years (Asas da Florestania Program). | Value | 0.00 | 5000.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Percentage of complaints received that are answered | Value | 0.00 | 80.00 | 0.00 |
Date | January 22, 2020 | December 31, 2021 | ||
Comment |
Ratio of cervical cytopathological examinations in women aged 25-64 and the population of the same age group | Value | 0.58 | 0.75 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
7,000 new children age 4 and 5 enrolled in ECD programs in COPs | Value | 0.00 | 14687.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
Ratio of screening mammograms performed on women aged 50 to 69 years and population of the same age group | Value | 0.06 | 0.40 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Net enrollment for 6,000 High School Students/Year - Programa Caminhos da educação do campo - High School Program (Asas da Florestania Program) | Value | 0.00 | 6000.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
Improve payroll auditing as instrument to increase the efficiency of public spending | Value | No | No | |
Date | December 31, 2008 | December 31, 2021 | ||
Comment |
26,000 new students in fundamental schools (grades 1-4) and 8,800 new students in fundamental schools (grades 5-8) benefiting from the implementation of a GESTAR I and II-like methodology | Value | 0.00 | 69120.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
20,000 rural students participating in the Quero Ler Program. | Value | 0.00 | 0.00 | 0.00 |
Date | December 31, 2015 | January 21, 2020 | ||
Comment |
Increase access to information and eservices offered by the GoAc in 30% of the target communities (CAPs and COPS) by 2014 | Value | 0.00 | 30.00 | 0.00 |
Date | January 1, 2008 | January 31, 2015 | ||
Comment |
5,300 new students enrolled in secondary education programs | Value | 0.00 | 5300.00 | 0.00 |
Date | December 31, 2008 | January 31, 2015 | ||
Comment |
7,200 new children age 4 and 5 enrolled in ECD programs in urban ZAPs | Value | 0.00 | 12254.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
1,600 youth and adults ages 15 - 35 have attended literacy programs and 3,000 youth and adults living in COPs benefiting from the provision of EJA 1st and 2nd segment programs | Value | 0.00 | 9071.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
Training of at least 80% of staff at the central level of the participating Secretariats in programs for improving managerial capacity | Value | 0.00 | 80.00 | 0.00 |
Date | January 1, 2008 | January 31, 2015 | ||
Comment |
66,900 students of fundamental cycle (grades 1-4), 52,650 students of fundamental cycle (grades 5-8) and 35,000 students of secondary cycle benefiting from the implementation of a quality improvement | Value | 0.00 | 289274.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
Increase in the proportion of live births of mothers with seven or more prenatal consultations from 42.98% in 2015 to 65% in 2021. | Value | 42.98 | 43.00 | 46.00 |
Date | December 31, 2015 | December 31, 2021 | December 31, 2021 | |
Comment |
Reduction of neonatal mortality by place of residence from 11 in 2015 to 9 in 2021. | Value | 11.00 | 3.00 | 0.00 |
Date | December 31, 2015 | November 30, 2020 | ||
Comment |
134 schools benefiting from the implementation of school subprojects | Value | 0.00 | 134.00 | 0.00 |
Date | January 1, 2008 | January 31, 2015 | ||
Comment |
8,500 youth and adults ages 15 - 35 have attended literacy programs and 12,200 youth and adults benefiting from the provision of EJA 1st and 2nd segment programs in urban ZAPs | Value | 0.00 | 25798.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
Adoption of Results Based Management at agreements in education in, at least, 40% of the SMEs by 2014 | Value | 0.00 | 40.00 | 0.00 |
Date | January 1, 2008 | January 31, 2015 | ||
Comment |
Refurbishment of 2 aerodrome runways meeting the standards of the National Civil Aviation Agency of Brazil (ANAC) in the municipalities of Marechal Thaumaturgo and Porto Walter | Value | 0.00 | 2.00 | 0.00 |
Date | December 31, 2015 | December 31, 2021 | ||
Comment |
11,200 students of fundamental cycle (grades 1-4), 7,000 students of fundamental cycle (grades 5-8) and 10,000 students of secondary cycle regularized in terms of age-grade distortion | Value | 0.00 | 27226.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
200 Community Development Plans (CDPs) developed and being implemented | Value | 0.00 | 106.00 | 200.00 |
Date | January 1, 2008 | December 31, 2016 | December 31, 2014 | |
Comment |
Quality Program for the Forestry Sector agreed with and joined by at least 30% of the State’s enterprises | Value | 0.00 | 30.00 | 0.00 |
Date | January 1, 2008 | January 31, 2015 | ||
Comment |
At least 15 Indigenous Land Management Plans developed and being implemented | Value | 0.00 | 15.00 | 0.00 |
Date | January 1, 2008 | January 31, 2015 | ||
Comment |
Indigenous households served with domestic connection for water for human consumption | Value | 0.00 | 59.00 | 0.00 |
Date | December 31, 2013 | December 31, 2021 | ||
Comment |
Increase in the percentage of pregnant women having at least 4 or more prenatal consultations in Rio Branco, Cruzeiro do Sul, and Sena Madureira from 40% in 2007 to 70% in last year of the project | Value | 40.00 | 81.00 | 0.00 |
Date | December 31, 2007 | December 31, 2016 | ||
Comment |
At least 15 indigenous organizations (cooperatives and associations) implementing strategic planning and management | Value | 0.00 | 18.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
Increase in the percentage of PSF coverage in Rio Branco, Cruzeiro do Sul and Sena Madureira from 42% in 2007 to 66% in 2014 | Value | 42.00 | 66.00 | 0.00 |
Date | December 31, 2007 | December 31, 2015 | ||
Comment |
Urban households served with domestic connection for treated water | Value | 0.00 | 3800.00 | 4503.00 |
Date | December 31, 2013 | March 31, 2020 | December 31, 2021 | |
Comment |
Implemented accountable and effective management system for project that tracks disbursements and results | Value | No | Yes | |
Date | January 1, 2008 | December 31, 2021 | ||
Comment |
Number of households with piped sanitation connections | Value | 0.00 | 3310.00 | 3101.00 |
Date | December 31, 2013 | March 31, 2020 | December 31, 2021 | |
Comment |
25,000 families registered and cared for by the Social Assistance Reference Centers and other social and assistance services (housing, sanitation, health, education, job and income) | Value | 0.00 | 25000.00 | 0.00 |
Date | January 1, 2008 | January 31, 2015 | ||
Comment |
Established social communication strategy with program participants, affected peoples and civil society | Value | No | Yes | |
Date | January 1, 2008 | June 15, 2021 | ||
Comment |
Extension of public roads with underground rainwater networks or channels (microdrainage) | Value | 0.00 | 7.95 | 0.00 |
Date | December 31, 2013 | December 31, 2021 | ||
Comment |
4,000 skilled and capable people to work in the services sectors (IT, business management, etc.), civil works, industry (clothing and food), commerce, arts and handcrafts and others | Value | 0.00 | 4440.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
At least 70% of project implementation by governmental institutions in compliance with planned activities, budget and timeline, as verified by SIM (Integrated Management System) | Value | 0.00 | 70.00 | 0.00 |
Date | January 1, 2008 | January 31, 2015 | ||
Comment |
Increase in the net enrollment ratio of fundamental education in urban areas from 93.1% in 2011 to 95% in 2017 from the implementation of a quality improvement package | Value | 93.10 | 95.00 | 0.00 |
Date | December 31, 2011 | December 31, 2017 | ||
Comment |
Number of maternal deaths adequately administered by place of residence | Value | 11.00 | 12.00 | 10.00 |
Date | December 31, 2015 | December 31, 2021 | December 31, 2021 | |
Comment |
At least 80% of the 34 IP communities receiving Project support receiving capacity building for strategic subproject planning and management | Value | 0.00 | 80.00 | 0.00 |
Date | January 1, 2014 | December 31, 2020 | ||
Comment |
Number of rural schools benefitting from the implementation of school subprojects | Value | 0.00 | 839.00 | 259.00 |
Date | December 31, 2013 | December 31, 2021 | December 31, 2021 | |
Comment |
15,000 new children age 4 and 5 enrolled in ECD programs in rural areas and 30,000 new students in fundamental schools (grades 1-4)have received basic education through Escola Ativa Program | Value | 0.00 | 104643.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
14,400 new students in fundamental schools (grades 5-8) and 9,600 new students enrolled in secondary education have received basic education through Asas da Florestania Program | Value | 0.00 | 25915.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
4,500 youth and adult ages 15 to 35 living in rural areas have attended literacy programs and 5,000 youth and adult benefiting fromthe provision of EJA 1st and 2nd segment programs | Value | 0.00 | 11686.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
Increase in percentage of medical consultations for pregnant women from excluded populations (CAU, CAP) per year from 5% to 50% | Value | 5.00 | 96.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |
Increase the percentage of people registered in PACS from 0 to 80% | Value | 0.00 | 80.00 | 0.00 |
Date | January 1, 2008 | January 31, 2015 | ||
Comment |
17,000 water filters (with chlorine treatment) distributed | Value | 0.00 | 17000.00 | 8550.00 |
Date | January 1, 2008 | December 31, 2014 | December 31, 2010 | |
Comment |
200 sustainable family farming Demonstration Units (DUs) operational | Value | 0.00 | 209.00 | 200.00 |
Date | January 1, 2008 | December 31, 2018 | March 31, 2020 | |
Comment |
100 Community Development Agents (CDAs) trained and on duty | Value | 0.00 | 54.00 | 0.00 |
Date | January 1, 2008 | December 31, 2016 | ||
Comment |