Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 4.80 |
P108144
Closed
Aifa Niane
N/A
August 28, 2008
(as of board presentation)
August 25, 2009
March 5, 2010
US$ 4.80 million
N/A
2010
US$ 4.80 million
B
Not Applicable
December 31, 2012
BANK APPROVED
June 28, 2013
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 4.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 4.80 |
Total Project Cost** | 4.80 |
Name | Review | Date |
---|---|---|
Summary Global Objective Rating | Satisfactory | 2012-12-16 |
Counterpart Funding | Satisfactory | 2012-12-16 |
Monitoring and Evaluation | Satisfactory | 2012-12-16 |
Overall Implementation Progress (IP) | Satisfactory | 2012-12-16 |
Overall Safeguards Rating | Satisfactory | 2012-12-16 |
Procurement | Satisfactory | 2012-12-16 |
Project Management | Satisfactory | 2012-12-16 |
Financial Management | Satisfactory | 2012-12-16 |
Overall Safeguards Rating | Satisfactory | 2012-12-16 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-13-2013 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-30-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
New technologies tested and proven successful by the end of the Project | Value | 0.00 | 2.00 | 3.00 |
Date | August 25, 2009 | April 16, 2012 | December 31, 2012 | |
Comment | The third technology is in test in farmers field and its effect will be evaluated during coming rainy season (June-October) |
SLM activities are integrated into the annual work plan of the Rural Advisory Agency in Rural Councils within the project target area | Value | 0.00 | 8.00 | 8.00 |
Date | August 25, 2009 | October 1, 2012 | December 31, 2012 | |
Comment | The target value is reached with SLM well integrated in agricultural and rural advisers work plan. | The target value is corrected to reflect initial objective of 8 rural councils |
Project proposals submitted by Producer Organizations to implement SLM technologies are implemented | Value | 0.00 | 23.00 | 30.00 |
Date | August 25, 2009 | April 16, 2012 | December 31, 2012 | |
Comment | The 23 sub projects are under implementation and 4 others are identified. | The target will be reached at the project closing. |
SLM Investment Framework (SIF) is approved | Value | SIF non-existent | SIF developped, approved and submitted to Agricult | SIF developed and approved |
Date | August 25, 2009 | October 1, 2012 | December 29, 2012 | |
Comment | Breves and brochures are in editing as requested by the Ministry of Agriculture. |
Increase of organic matter in the soil in target areas | Value | 0.20 | 0.47 | 0.23 |
Date | August 25, 2009 | October 1, 2012 | June 30, 2012 | |
Comment | The baseline at the project approval was defined based on secondary data. Analysis done at the beginning of the project showed abaseline of 1.82. | The soil organic material rose on average by 0.47% at the end of the project. | The project induced an increase by 0.47% of soil organic material. The target of 0.23% is widely exceeded. |
Increase of land with SLM practices in target areas | Value | 0.00 | 0.00 | 20.00 |
Date | August 25, 2009 | November 27, 2012 | November 27, 2012 | |
Comment | Indicator not yet available. Mapping of the area covered by SLM technologies is under going. An increase of 32% found in ruralcommunities mapped. | Indicator under study. Target exceeded in rural community mapped. |
Direct project beneficiaries | Value | 0.00 | 17990.00 | 4100.00 |
Date | August 25, 2009 | October 1, 2012 | June 30, 2012 | |
Comment | The number of direct project beneficiaries is 17990 producers of which 9991 women (55%). A total of 28 producers organizationsbenefited from the project funding for their SLM sub-projects. | Number of farmers targeted not specified but 30 producers organizations were targeted. |
Female beneficiaries | Value | 0.00 | 9991.00 | 50.00 |
Date | August 25, 2009 | October 1, 2012 | June 30, 2012 | |
Comment | Direct project beneficaries understood as 'Producers benefited from the project' |