Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 78.00 |
Borrower/Recipient | 52.00 |
P108443
Closed
Maurizio Guadagni
State of Sao Paulo
October 7, 2008
(as of board presentation)
May 25, 2010
December 22, 2010
US$ 130.00 million
State Secretariat of Agriculture - Sao Paulo,State Secretariat of Environment - Sao Paulo
2010
US$ 78.00 million
B
Not Applicable
September 30, 2018
BANK APPROVED
May 10, 2022
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 78.00 |
Borrower/Recipient | 52.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 78.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 78.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 130.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 9, 2014 | IBRD-79080 | Loan Disb | 1,162,066.90 |
Dec 15, 2014 | IBRD-79080 | Loan Disb | 2,314,100.50 |
Dec 15, 2014 | IBRD-79080 | Loan Disb | 833,076.20 |
Dec 9, 2014 | IBRD-79080 | Loan Disb | 1,385,981.20 |
Sep 10, 2013 | IBRD-79080 | Loan Disb | 257,389.22 |
Jul 30, 2013 | IBRD-79080 | Loan Disb | 444,563.00 |
Oct 18, 2013 | IBRD-79080 | Loan Disb | 481,320.20 |
Dec 15, 2013 | IBRD-79080 | Int Charges | 199.13 |
Dec 17, 2013 | IBRD-79080 | Loan Disb | 1,285,594.90 |
Dec 9, 2013 | IBRD-79080 | Loan Disb | 505,539.88 |
Dec 15, 2013 | IBRD-79080 | Int Charges | 14,009.57 |
Feb 7, 2014 | IBRD-79080 | Loan Disb | 413,667.60 |
Feb 24, 2014 | IBRD-79080 | Loan Disb | 1,459,367.00 |
Jun 15, 2014 | IBRD-79080 | Int Charges | 576.00 |
Jun 15, 2014 | IBRD-79080 | Int Charges | 24,006.21 |
Aug 14, 2014 | IBRD-79080 | Loan Disb | 878,117.30 |
Dec 15, 2014 | IBRD-79080 | Int Charges | 38,463.39 |
Jul 1, 2014 | IBRD-79080 | Loan Disb | 2,716,653.00 |
Jul 31, 2014 | IBRD-79080 | Loan Disb | 1,121,126.50 |
Mar 30, 2015 | IBRD-79080 | Loan Disb | 403,526.88 |
Feb 20, 2015 | IBRD-79080 | Loan Disb | 211,066.94 |
Jun 29, 2015 | IBRD-79080 | Loan Disb | 833,090.20 |
Jun 9, 2015 | IBRD-79080 | Loan Disb | 994,195.20 |
Jun 15, 2015 | IBRD-79080 | Loan Repay | 390,325.84 |
Jun 15, 2015 | IBRD-79080 | Int Charges | 136.29 |
Jun 15, 2015 | IBRD-79080 | Int Charges | 62,141.39 |
Jul 10, 2015 | IBRD-79080 | Loan Disb | 314,406.10 |
Jul 10, 2015 | IBRD-79080 | Loan Disb | 943,218.25 |
Aug 17, 2015 | IBRD-79080 | Loan Disb | 1,033,799.50 |
Oct 14, 2015 | IBRD-79080 | Loan Disb | 1,038,583.40 |
Sep 10, 2015 | IBRD-79080 | Loan Disb | 394,913.50 |
Sep 9, 2015 | IBRD-79080 | Loan Disb | 794,565.20 |
Dec 15, 2015 | IBRD-79080 | Int Charges | 106.05 |
Dec 15, 2015 | IBRD-79080 | Int Charges | 92,505.21 |
Dec 15, 2015 | IBRD-79080 | Loan Repay | 519,799.97 |
Jan 28, 2016 | IBRD-79080 | Loan Disb | 121,961.63 |
Mar 29, 2018 | IBRD-79080 | Loan Disb | 5,328,328.00 |
Jun 22, 2018 | IBRD-79080 | Loan Disb | 73,922.21 |
Sep 17, 2018 | IBRD-79080 | Loan Disb | 3,837,533.00 |
Aug 24, 2018 | IBRD-79080 | Loan Disb | 1,037,873.06 |
Jun 15, 2018 | IBRD-79080 | Int Charges | 11,654.44 |
Oct 9, 2018 | IBRD-79080 | Loan Disb | 419,063.90 |
Dec 15, 2018 | IBRD-79080 | Int Charges | 1,048,580.40 |
Dec 15, 2018 | IBRD-79080 | Loan Repay | 1,675,468.40 |
Jun 15, 2019 | IBRD-79080 | Int Charges | 1,206,797.40 |
Jun 15, 2019 | IBRD-79080 | Loan Repay | 1,675,468.40 |
Jun 15, 2020 | IBRD-79080 | Int Charges | 811,364.56 |
Jun 15, 2020 | IBRD-79080 | Loan Repay | 1,675,468.40 |
Dec 15, 2019 | IBRD-79080 | Int Charges | 985,382.56 |
Dec 15, 2019 | IBRD-79080 | Loan Repay | 1,675,468.40 |
Dec 15, 2020 | IBRD-79080 | Int Charges | 302,477.16 |
Dec 15, 2020 | IBRD-79080 | Loan Repay | 1,372,991.20 |
Dec 15, 2020 | IBRD-79080 | Loan Repay | 302,477.16 |
Jun 15, 2021 | IBRD-79080 | Int Charges | 241,579.30 |
Jun 15, 2021 | IBRD-79080 | Loan Repay | 1,675,468.40 |
Jun 15, 2022 | IBRD-79080 | Int Charges | 253,286.86 |
Jun 15, 2022 | IBRD-79080 | Loan Repay | 1,422,181.50 |
Jun 15, 2022 | IBRD-79080 | Loan Repay | 253,286.86 |
Dec 15, 2021 | IBRD-79080 | Int Charges | 214,443.84 |
Dec 15, 2021 | IBRD-79080 | Loan Repay | 1,461,024.50 |
Dec 15, 2021 | IBRD-79080 | Loan Repay | 214,443.84 |
Dec 15, 2022 | IBRD-79080 | Int Charges | 1,028,914.70 |
Dec 15, 2022 | IBRD-79080 | Loan Repay | 646,553.70 |
Dec 15, 2022 | IBRD-79080 | Loan Repay | 1,028,914.70 |
Jun 15, 2023 | IBRD-79080 | Int Charges | 75,084.64 |
Jun 15, 2023 | IBRD-79080 | Int Charges | 1,490,412.10 |
Jun 15, 2023 | IBRD-79080 | Loan Repay | 109,971.62 |
Jun 15, 2023 | IBRD-79080 | Loan Repay | 1,565,496.80 |
Dec 15, 2023 | IBRD-79080 | Loan Repay | 1,675,468.40 |
Dec 15, 2023 | IBRD-79080 | Int Charges | 30,318.69 |
Dec 15, 2023 | IBRD-79080 | Int Charges | 21,229.28 |
Dec 15, 2023 | IBRD-79080 | Int Charges | 1,645,149.60 |
May 25, 2010 | IBRD-79080 | Loan Commitment | 78,000,000.00 |
Jun 15, 2024 | IBRD-79080 | Int Charges | 11,002.64 |
Jun 15, 2024 | IBRD-79080 | Int Charges | 1,716,852.90 |
Jun 15, 2024 | IBRD-79080 | Loan Repay | 1,675,468.40 |
Feb 11, 2016 | IBRD-79080 | Loan Disb | 853,827.40 |
Dec 3, 2015 | IBRD-79080 | Loan Disb | 883,059.56 |
Dec 4, 2015 | IBRD-79080 | Loan Disb | 1,012,921.25 |
Mar 29, 2016 | IBRD-79080 | Loan Disb | 342,203.25 |
Apr 5, 2016 | IBRD-79080 | Loan Disb | 660,372.06 |
Apr 26, 2016 | IBRD-79080 | Loan Disb | 2,112,676.00 |
Mar 3, 2016 | IBRD-79080 | Loan Disb | 917,246.75 |
Jan 23, 2017 | IBRD-79080 | Loan Disb | 1,479,889.10 |
Jun 15, 2016 | IBRD-79080 | Int Charges | 464.97 |
Jun 15, 2016 | IBRD-79080 | Int Charges | 159,072.39 |
Jun 15, 2016 | IBRD-79080 | Loan Repay | 619,465.06 |
Jul 26, 2016 | IBRD-79080 | Loan Disb | 2,148,425.50 |
Dec 1, 2016 | IBRD-79080 | Loan Disb | 117,671.29 |
Feb 1, 2017 | IBRD-79080 | Loan Disb | 63,658.79 |
Nov 8, 2016 | IBRD-79080 | Loan Disb | 1,578,605.20 |
Dec 19, 2016 | IBRD-79080 | Loan Disb | 135,951.66 |
Dec 22, 2016 | IBRD-79080 | Loan Disb | 401,989.10 |
Dec 15, 2016 | IBRD-79080 | Int Charges | 3,227.69 |
Dec 15, 2016 | IBRD-79080 | Int Charges | 219,118.73 |
Dec 15, 2016 | IBRD-79080 | Loan Repay | 710,226.50 |
Mar 30, 2017 | IBRD-79080 | Loan Disb | 5,119,508.50 |
May 11, 2017 | IBRD-79080 | Loan Disb | 626,272.10 |
Mar 10, 2017 | IBRD-79080 | Loan Disb | 2,020,396.40 |
Feb 16, 2017 | IBRD-79080 | Loan Disb | 322,570.25 |
Jul 19, 2017 | IBRD-79080 | Loan Disb | 2,194,632.50 |
Oct 10, 2017 | IBRD-79080 | Loan Disb | 3,513,030.20 |
Jun 15, 2017 | IBRD-79080 | Int Charges | 2,185.36 |
Jun 15, 2017 | IBRD-79080 | Int Charges | 341,953.06 |
Jun 15, 2017 | IBRD-79080 | Loan Repay | 954,139.75 |
Nov 20, 2017 | IBRD-79080 | Loan Disb | 8,974,542.00 |
Feb 9, 2018 | IBRD-79080 | Loan Disb | 2,146,580.80 |
Dec 15, 2017 | IBRD-79080 | Int Charges | 460,819.40 |
Dec 15, 2017 | IBRD-79080 | Loan Repay | 1,165,095.20 |
Dec 15, 2017 | IBRD-79080 | Int Charges | 1,041.17 |
Feb 14, 2018 | IBRD-79080 | Loan Disb | 523,656.97 |
Aug 31, 2017 | IBRD-79080 | Loan Disb | 3,168,567.80 |
Jun 15, 2018 | IBRD-79080 | Int Charges | 722,690.60 |
Jun 15, 2018 | IBRD-79080 | Loan Repay | 1,550,384.90 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2018-06-26 |
Counterpart Funding | Satisfactory | 2018-06-26 |
Monitoring and Evaluation | Satisfactory | 2018-06-26 |
Overall Implementation Progress (IP) | Satisfactory | 2018-06-26 |
Project Management | Satisfactory | 2018-06-26 |
Procurement | Moderately Satisfactory | 2018-06-26 |
Financial Management | Moderately Satisfactory | 2018-06-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-29-2019 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-28-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in total sales value for participating organizations, by end of project | Value | 0.00 | 8.00 | 87.00 |
Date | January 1, 2011 | September 30, 2015 | September 28, 2018 | |
Comment |
Number of environmental policies and instruments developed, measured by (a) CAR approved and made available to producers and (b) 3 PES programs developed and adopted by rural producers | Value | 0.00 | 4.00 | 4.00 |
Date | September 15, 2015 | September 30, 2017 | September 28, 2018 | |
Comment |
CAR approved and made available | Value | 0.00 | 1.00 | 1.00 |
Date | September 15, 2015 | September 30, 2017 | September 28, 2018 | |
Comment |
3 PES projects developed and adopted by rural producers | Value | 0.00 | 3.00 | 3.00 |
Date | September 15, 2015 | September 30, 2017 | September 28, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of business initiatives with market viability identified and financed by the project | Value | 0.00 | 267.00 | 287.00 |
Date | May 25, 2010 | September 29, 2017 | September 28, 2018 | |
Comment |
Number of producer organizations trained in management and accounting | Value | 0.00 | 831.00 | 676.00 |
Date | May 25, 2010 | September 29, 2017 | September 28, 2018 | |
Comment |
CATI staff trained in management and value-chains | Value | 0.00 | 500.00 | 599.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
System for payment for water or carbon services piloted | Value | No | Yes | Yes |
Date | May 25, 2010 | September 30, 2015 | September 28, 2018 | |
Comment |
Length of rural roads with year-round usability following rehabilitation (critical spot improvement) | Value | 0.00 | 660.00 | 672.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
System for developing, selecting, supporting and monitoring business proposals, operational | Value | No | Yes | Yes |
Date | May 25, 2010 | September 30, 2015 | September 28, 2018 | |
Comment |
Continued implementation of socio-environmental management plan | Value | No | Yes | Yes |
Date | May 25, 2010 | September 30, 2015 | September 28, 2018 | |
Comment |
Number of subprojects of traditional communities with market viability identified and financed by the project | Value | 0.00 | 49.00 | 87.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of value-chain studies carried out | Value | 0.00 | 4.00 | 4.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of families directly benefiting from the project (Subcomponent 1.1) | Value | 0.00 | 7108.00 | 16622.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of producer organizations trained on the operation of their business initiative | Value | 0.00 | 609.00 | 833.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of beneficiaries of business initiatives registered in the CAR | Value | 0.00 | 4265.00 | 13505.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of ethno-development plans elaborated | Value | 0.00 | 49.00 | 46.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of environmental subprojects implemented | Value | 0.00 | 24.00 | 25.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Rural roads with year-round usability following maintenance | Value | 0.00 | 950.00 | 605.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Municipalities adopting new system for rural roads management | Value | 0.00 | 25.00 | 6.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of beneficiaries of environmental subprojects | Value | 0.00 | 682.00 | 697.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of rural producers trained (environment) | Value | 0.00 | 800.00 | 1690.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of technical staff trained (environment) | Value | 0.00 | 1100.00 | 1135.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Number of beneficiaries of environmental subprojects and PES programs registered in CAR | Value | 0.00 | 1300.00 | 821.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |
Surveys realized for baseline, second survey (mid-term) and third survey (final) | Value | 0.00 | 3.00 | 2.00 |
Date | May 25, 2010 | September 30, 2017 | September 28, 2018 | |
Comment |