GEF Huai River Basin Marine Pollution Reduction Project

Abstract*

Demonstrate innovative and cost-effective water pollution control practices in Guangli river catchment of Dongying Municipality, contributing to pollution reduction in the Bohai Sea. There are four components to the project. The first component of the project is wetland construction and sluice gate operation optimization. The second component of the project is agricultural pollution control and rural waste management. The third component of the project...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To demonstrate innovative and cost-effective water pollution control practices in the Guangli River catchment of Dongying Municipality, contributing to pollution reduction in the Bohai Sea

Key Details

Project Details

  • P108592

  • Closed

  • Xiaokai Li

  • N/A

  • China

  • June 30, 2010

  • (as of board presentation)

    February 23, 2012

  • June 22, 2012

  • US$ 37.83 million

  • Shandong Provincial Water Resources Department

  • East Asia and Pacific

  • 2012

  • US$ 5.00 million

  • B

  • July 16, 2024

  • December 31, 2015

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 5.00
Borrower/Recipient 32.83

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 5.00
Total Project Cost** 37.83

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Summary Global Objective Rating Unsatisfactory 2015-12-17
Monitoring and Evaluation Unsatisfactory 2015-12-17
Project Management Unsatisfactory 2015-12-17
Financial Management Moderately Satisfactory 2015-12-17
Procurement Moderately Satisfactory 2015-12-17
Overall Satisfactory 2015-12-17
Overall Implementation Progress (IP) Unsatisfactory 2015-12-17
Counterpart Funding Moderately Satisfactory 2015-12-17

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2016
OutcomesUnsatisfactory
Risk to Development OutcomeHigh
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceUnsatisfactory
Government PerformanceUnsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-02-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualityHighN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Project-induced reduction in pollutant/nutrient loads entering Bohai Sea from Guangli River Watershed (BOD) (T/a)Value0.0026.00215.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Project-induced reduction in pollutant/nutrient loads entering Bohai Sea from Guangli River Watershed (NH3N) (T/a)Value0.0016.95134.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Project-induced reduction in pollutant/nutrient loads entering Bohai Sea from Guangli River Watershed (TP) (T/a)Value0.007.1812.90
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Reduction in pollutants/nutrients through constructed wetlands at Dongbalu (COD) (T/a)Value0.000.00430.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Reduction in pollutants/nutrients through constructed wetlands at Dongbalu (NH3-N) (T/a)Value0.000.00129.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Reduction in pollutants/nutrients through constructed wetlands at Dongbalu (BOD) (T/a)Value0.000.00215.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Livestock waste pollution reduction in participating villages (COD) (T/a)Value0.0092.2978.30
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Livestock waste pollution reduction in participating villages (TN) (T/a)Value0.0017.160.74
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Agricultural pollution/nutrient load reduction in participating villages (TP) (T/a)Value0.000.130.12
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Number of people trainedValue0.004603.004500.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Reduction in pollutants/nutrients through constructed wetlands at Dongbalu (TP) (T/a)Value0.000.0012.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Annual volume of treated wastewater at wetlands (millions of m3 annually)Value0.0021.5021.50
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Rural wastewater pollution load reduction in participating villages (COD) (T/a)Value0.004.079.30
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Rural wastewater pollution load reduction in participating villages (SS) (T/a)Value0.002.214.60
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Livestock waste pollution reduction in participating villages (TP) (T/a)Value0.007.055.88
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Agricultural pollution/nutrient load reduction in participating villages (NH3-N) (T/a)Value0.001.455.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Proportion of farmers adopting integrated and balanced fertilizer application technology in participating villagesValue0.0048.0080.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Farmers' environmental protection associations operationalValue0.0010.0010.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Study of the impact on pollution reduction through constructing wetlands in Guangli RiverValueNot startedStudy completedStudy completed
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Evaluation study and management planning for Ag. and Rural Pollution Reduction in Guangli River CatchmentValueNot startedStudy completedStudy completed
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Development and dissemination of Huai River basin-wide replication strategyValueNot startedStrategy (strategic plan) developedCompleted and disseminated
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Voume(mass) of COD pollution load reduction achieved under the projectValue0.00371.36517.60
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Direct project beneficiariesValue0.000.000.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Client days of training provided - Female (number)Value0.002200.002000.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Female beneficiariesValue0.000.000.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Client days of training provided (number)Value0.004603.004500.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Project-induced reduction in pollutant/nutrient loads entering Bohai Sea from Guangli River Watershed (COD) (T/a)Value0.00371.36517.60
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment
  • Nutrient load reduction (Nitrogen(N)) achieved under the projectValue0.0016.95134.00
    DateDecember 31, 2011December 7, 2015December 31, 2015
    Comment