Financier | Commitments |
---|---|
Borrower/Recipient | 5.00 |
IDA Credit | 5.00 |
Bilateral Agencies (unidentified) | 33.00 |
P108791
Closed
Adama Ouedraogo
Government of Burkina Faso,Ministry of Economy and Finance
November 16, 2007
(as of board presentation)
June 5, 2008
April 8, 2009
US$ 43.00 million
2iE - International Institute for Water and Environmental Engineering
2008
US$ 38.00 million
B
Not Applicable
November 30, 2015
BANK APPROVED
July 17, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 5.00 |
IDA Credit | 5.00 |
Bilateral Agencies (unidentified) | 33.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 5.00 |
IBRD + IDA Commitment | 5.00 |
Lending Instrument | |
---|---|
Grant Amount | 33.00 |
Total Project Cost** | 43.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 1, 2020 | IDA-44620 | Int Charges | 383.78 |
Apr 1, 2020 | IDA-44620 | Int Charges | 383.78 |
Apr 1, 2020 | IDA-44620 | Loan Repay | 1,763.18 |
Apr 1, 2020 | IDA-44620 | Int Charges | 15,367.57 |
Apr 1, 2020 | IDA-44620 | Int Charges | 15,367.57 |
Apr 1, 2020 | IDA-44620 | Loan Repay | 40,564.89 |
Oct 6, 2020 | IDA-44620 | Int Charges | 30.25 |
Oct 6, 2020 | IDA-44620 | Int Charges | 30.25 |
Oct 6, 2020 | IDA-44620 | Loan Repay | 43,785.48 |
Oct 6, 2020 | IDA-44620 | Int Charges | 15,406.27 |
Oct 6, 2020 | IDA-44620 | Int Charges | 15,406.27 |
Apr 1, 2021 | IDA-44620 | Loan Repay | 42,941.15 |
Apr 1, 2021 | IDA-44620 | Loan Repay | 958.37 |
Apr 1, 2021 | IDA-44620 | Int Charges | 4.58 |
Apr 1, 2021 | IDA-44620 | Int Charges | 4.58 |
Apr 1, 2021 | IDA-44620 | Int Charges | 14,819.32 |
Apr 1, 2021 | IDA-44620 | Int Charges | 14,819.32 |
Apr 1, 2021 | IDA-44620 | Int Charges | 357.47 |
Apr 1, 2021 | IDA-44620 | Int Charges | 357.47 |
Oct 1, 2021 | IDA-44620 | Int Charges | 817.05 |
Apr 6, 2016 | IDA-44620 | Int Charges | 16,145.66 |
Mar 31, 2016 | IDA-H8200 | Loan Disb | 210,683.56 |
Mar 24, 2016 | IDA-H8200 | Loan Disb | 119,133.01 |
Dec 8, 2016 | IDA-H8200 | Loan Cancel | 882,665.20 |
Apr 1, 2016 | IDA-44620 | Int Charges | 193.01 |
Apr 1, 2016 | IDA-44620 | Int Charges | 193.01 |
Oct 1, 2016 | IDA-44620 | Int Charges | 376.99 |
Oct 1, 2016 | IDA-44620 | Int Charges | 376.99 |
Oct 1, 2016 | IDA-44620 | Int Charges | 15,843.52 |
Oct 1, 2016 | IDA-44620 | Int Charges | 15,843.52 |
Oct 3, 2017 | IDA-44620 | Int Charges | 137.86 |
Oct 3, 2017 | IDA-44620 | Int Charges | 137.86 |
Oct 3, 2017 | IDA-44620 | Int Charges | 16,331.65 |
Oct 3, 2017 | IDA-44620 | Int Charges | 16,331.65 |
Apr 6, 2017 | IDA-44620 | Int Charges | 15,621.53 |
Apr 6, 2017 | IDA-44620 | Int Charges | 15,621.53 |
Apr 1, 2017 | IDA-44620 | Int Charges | 14.53 |
Apr 1, 2017 | IDA-44620 | Int Charges | 14.53 |
Apr 1, 2018 | IDA-44620 | Int Charges | 16,762.06 |
Apr 9, 2024 | IDA-44620 | Int Charges | 13,728.40 |
Apr 9, 2024 | IDA-44620 | Int Charges | 13,728.40 |
Oct 1, 2023 | IDA-44620 | Loan Repay | 144.60 |
Oct 4, 2023 | IDA-44620 | Loan Repay | 40,429.51 |
Oct 4, 2023 | IDA-44620 | Int Charges | 0.08 |
Oct 4, 2023 | IDA-44620 | Int Charges | 0.08 |
Oct 4, 2023 | IDA-44620 | Int Charges | 12,535.90 |
Oct 4, 2023 | IDA-44620 | Int Charges | 12,535.90 |
Oct 18, 2012 | IDA-H8200 | Loan Commitment | 10,000,000.00 |
Jun 5, 2008 | IDA-44620 | Loan Commitment | 5,000,000.00 |
Oct 1, 2021 | IDA-44620 | Int Charges | 817.05 |
Oct 1, 2021 | IDA-44620 | Loan Repay | 15,176.73 |
Oct 1, 2021 | IDA-44620 | Loan Repay | 28,569.71 |
Oct 1, 2021 | IDA-44620 | Int Charges | 14,519.64 |
Oct 1, 2021 | IDA-44620 | Int Charges | 14,519.64 |
Apr 1, 2022 | IDA-44620 | Int Charges | 14,577.67 |
Apr 1, 2022 | IDA-44620 | Int Charges | 14,577.67 |
Apr 1, 2022 | IDA-44620 | Int Charges | 881.01 |
Apr 1, 2022 | IDA-44620 | Int Charges | 881.01 |
Apr 1, 2022 | IDA-44620 | Loan Repay | 14,826.43 |
Apr 1, 2022 | IDA-44620 | Loan Repay | 27,950.06 |
Oct 1, 2022 | IDA-44620 | Int Charges | 315.82 |
Oct 1, 2022 | IDA-44620 | Int Charges | 315.82 |
Oct 1, 2022 | IDA-44620 | Loan Repay | 39,662.10 |
Oct 1, 2022 | IDA-44620 | Int Charges | 12,909.84 |
Oct 1, 2022 | IDA-44620 | Int Charges | 12,909.84 |
Apr 1, 2023 | IDA-44620 | Int Charges | -14,225.81 |
Apr 6, 2023 | IDA-44620 | Int Charges | 14,260.28 |
Apr 6, 2023 | IDA-44620 | Int Charges | 14,260.28 |
Apr 1, 2023 | IDA-44620 | Int Charges | 813.06 |
Apr 1, 2023 | IDA-44620 | Int Charges | 813.06 |
Apr 1, 2023 | IDA-44620 | Loan Repay | 40,979.35 |
Apr 1, 2023 | IDA-44620 | Int Charges | -813.06 |
Apr 1, 2023 | IDA-44620 | Int Charges | -813.06 |
Apr 1, 2023 | IDA-44620 | Loan Repay | -41,687.22 |
Apr 1, 2023 | IDA-44620 | Int Charges | -14,225.81 |
Apr 6, 2023 | IDA-44620 | Loan Repay | 709.59 |
Apr 1, 2023 | IDA-44620 | Int Charges | 813.06 |
Apr 1, 2023 | IDA-44620 | Int Charges | 813.06 |
Apr 1, 2023 | IDA-44620 | Loan Repay | 41,687.22 |
Apr 1, 2023 | IDA-44620 | Int Charges | 14,225.81 |
Apr 1, 2023 | IDA-44620 | Int Charges | 14,225.81 |
Apr 4, 2024 | IDA-44620 | Int Charges | 1,173.17 |
Apr 4, 2024 | IDA-44620 | Int Charges | 1,173.17 |
Apr 4, 2024 | IDA-44620 | Loan Repay | 13,819.04 |
Apr 9, 2024 | IDA-44620 | Int Charges | 2.56 |
Apr 9, 2024 | IDA-44620 | Int Charges | 2.56 |
Apr 9, 2024 | IDA-44620 | Loan Repay | 27,308.89 |
Apr 2, 2019 | IDA-44620 | Int Charges | 84.16 |
Apr 2, 2019 | IDA-44620 | Int Charges | 84.16 |
Apr 2, 2019 | IDA-44620 | Int Charges | 15,084.84 |
Apr 2, 2019 | IDA-44620 | Int Charges | 15,084.84 |
Apr 2, 2019 | IDA-44620 | Loan Repay | 15,935.45 |
Apr 2, 2019 | IDA-44620 | Loan Repay | 27,014.89 |
Oct 1, 2019 | IDA-44620 | Int Charges | 845.60 |
Oct 1, 2019 | IDA-44620 | Int Charges | 845.60 |
Oct 1, 2019 | IDA-44620 | Loan Repay | 42,207.53 |
Oct 1, 2019 | IDA-44620 | Int Charges | 0.87 |
Oct 1, 2019 | IDA-44620 | Int Charges | 0.87 |
Oct 1, 2019 | IDA-44620 | Int Charges | 15,128.57 |
Oct 1, 2019 | IDA-44620 | Int Charges | 15,128.57 |
Apr 1, 2018 | IDA-44620 | Int Charges | 16,762.06 |
Apr 1, 2018 | IDA-44620 | Int Charges | 45.27 |
Apr 1, 2018 | IDA-44620 | Int Charges | 45.27 |
Oct 1, 2018 | IDA-44620 | Int Charges | 127.73 |
Oct 1, 2018 | IDA-44620 | Int Charges | 127.73 |
Oct 1, 2018 | IDA-44620 | Loan Repay | 43,253.71 |
Oct 1, 2018 | IDA-44620 | Int Charges | 16,135.41 |
Oct 1, 2018 | IDA-44620 | Int Charges | 16,135.41 |
Oct 10, 2014 | IDA-44620 | Int Charges | 16,648.91 |
Oct 10, 2014 | IDA-44620 | Int Charges | 16,648.91 |
Oct 1, 2014 | IDA-44620 | Int Charges | 176.05 |
Oct 1, 2014 | IDA-44620 | Int Charges | 176.05 |
Feb 12, 2014 | IDA-44620 | Loan Cancel | 1,701.19 |
Oct 1, 2013 | IDA-44620 | Int Charges | 596.62 |
Oct 1, 2013 | IDA-44620 | Int Charges | 596.62 |
Oct 1, 2013 | IDA-44620 | Int Charges | 17,611.92 |
Oct 1, 2013 | IDA-44620 | Int Charges | 17,611.92 |
Apr 1, 2014 | IDA-44620 | Int Charges | 112.22 |
Apr 1, 2014 | IDA-44620 | Int Charges | 112.22 |
Apr 1, 2014 | IDA-44620 | Int Charges | 17,844.79 |
Apr 1, 2014 | IDA-44620 | Int Charges | 17,844.79 |
Mar 26, 2014 | IDA-H8200 | Loan Disb | 1,913,382.20 |
Jul 3, 2014 | IDA-H8200 | Loan Disb | 3,225,871.00 |
Mar 19, 2015 | IDA-H8200 | Loan Disb | 3,434,883.80 |
Apr 1, 2015 | IDA-44620 | Int Charges | 415.91 |
Apr 1, 2015 | IDA-44620 | Int Charges | 415.91 |
Apr 1, 2015 | IDA-44620 | Int Charges | 15,532.88 |
Apr 1, 2015 | IDA-44620 | Int Charges | 15,532.88 |
Oct 1, 2015 | IDA-44620 | Int Charges | 16,272.81 |
Oct 1, 2015 | IDA-44620 | Int Charges | 16,272.81 |
Oct 1, 2015 | IDA-44620 | Int Charges | 508.58 |
Oct 1, 2015 | IDA-44620 | Int Charges | 508.58 |
Apr 6, 2016 | IDA-44620 | Int Charges | 16,145.66 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2015-11-30 |
Procurement | Moderately Satisfactory | 2015-11-30 |
Project Management | Moderately Satisfactory | 2015-11-30 |
Financial Management | Satisfactory | 2015-11-30 |
Monitoring and Evaluation | Satisfactory | 2015-11-30 |
Overall Safeguards Rating | Moderately Satisfactory | 2015-11-30 |
Overall | Low | 2015-11-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2015-11-30 |
Counterpart Funding | Satisfactory | 2015-11-30 |
Overall Safeguards Rating | Moderately Satisfactory | 2015-11-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-31-2016 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 11-14-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Modest | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Project beneficiaries: Number of new (additional) students, of which female | Value | 0.00 | 817.00 | 720.00 |
Date | July 16, 2012 | October 30, 2015 | November 30, 2015 | |
Comment |
The percentage of graduates employed in the field in which they are qualified, six months after graduation | Value | 90.00 | 90.00 | 90.00 |
Date | November 14, 2007 | October 30, 2015 | November 30, 2015 | |
Comment |
The number of 2IE students | Value | 520 | 2240 | 2200 |
Date | October 16, 2007 | October 30, 2015 | November 30, 2015 | |
Comment |
Percentage of girls/women among new strudents | Value | 0.00 | 23.00 | 23.00 |
Date | July 16, 2012 | October 30, 2015 | November 30, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of square meters rehabilitated | Value | 0.00 | 12000.00 | 12000.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Training and research facilities capacity in m² | Value | 4741.00 | 6770.00 | 6770.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
The seven governing Committees set up tables of indicators and report annually to the General Assembly | Value | No | Yes | Yes |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of non francophone students | Value | 0.00 | 18.00 | 22.00 |
Date | October 30, 2015 | November 30, 2015 | ||
Comment |
The percentage of non targeted subsidies in total 2IE resources | Value | 20.00 | 0.00 | 0.00 |
Date | February 25, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of students in distance education | Value | 40.00 | 1036.00 | 1750.00 |
Date | October 16, 2007 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of permanent teaching staff | Value | 38.00 | 115.00 | 100.00 |
Date | July 15, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Percentage of teaching staff with PhD | Value | 30.00 | 61.00 | 60.00 |
Date | July 15, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
General Assembly takes place regularly (annually) | Value | Yes | Yes | Yes |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
The number of doctoral students | Value | 8.00 | 59.00 | 50.00 |
Date | November 15, 2007 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of square meters built | Value | 12000.00 | 62086.00 | 62086.00 |
Date | July 15, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Boarding capacity | Value | 650.00 | 1860.00 | 2100.00 |
Date | November 14, 2007 | October 30, 2015 | November 30, 2015 | |
Comment |
Activities contracts funded by donors as a percentage of 2iE resources | Value | 40.00 | 7.00 | 10.00 |
Date | October 15, 2009 | October 30, 2015 | November 30, 2015 | |
Comment |
Contracted services and e-learning as a percentage of 2iE resources | Value | 20.00 | 37.20 | 34.00 |
Date | October 15, 2009 | October 30, 2015 | November 30, 2015 | |
Comment |
Fees as a percentage of 2iE resources | Value | 30.00 | 55.80 | 56.00 |
Date | October 15, 2009 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of 2iE Board meetings per year | Value | 1.00 | 2.00 | 2.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of students in business incubator and other entrepreneurship programs | Value | 0.00 | 634.00 | 300.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of students financed by enterprises | Value | 12.00 | 53.00 | 50.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of scientific papers published and disseminated internationally | Value | 5.00 | 34.00 | 50.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Percentage of teaching hours from contracted professors from world class institutions | Value | 25.00 | 22.00 | 25.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of sports and cultural facilities | Value | 5.00 | 11.00 | 11.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of laboratories fully equipped | Value | 8.00 | 12.00 | 12.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of Master’s degree programs internationally certified (outside of Africa) | Value | 1.00 | 15.00 | 15.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of countries of origin of 2iE students | Value | 20.00 | 28.00 | 30.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |
Number of enterprises participating in “2iE’s enterprise days” | Value | 90.00 | 100.00 | 110.00 |
Date | November 12, 2008 | October 30, 2015 | November 30, 2015 | |
Comment |