Abstract*

The development objective of the Environmental and Social Capacity Building for the Energy Sector Project for Cameroon is to improve the management of and the accountability for environmental and social issues related to large infrastructure investments, with an initial focus on the energy sector. The project will initially focus capacity building efforts towards the energy sector, in support of the Energy Sector Development Project. The mobilization...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objective of the project would be to: Improve the management of and the accountability for environmental and social issues related to large infrastructure investments, with an initial focus on the energy sector. The Project would initially focus capacity building efforts towards the energy sector, in support of the Energy Sector Development Project. The mobilization of supplemental resources to more explicitly address issues in the mining and transport sectors would be explored during the project's mid-term review. The expected long-term benefits of the project are to: (i) reduce the negative externalities of large infrastructure projects, and (ii) develop a transparent, stable and fair framework for managing environmental and social risks that should comfort large infrastructure investments, and (iii) institutionalizes information flows between the populations affected by large infrastructure projects and other stakeholders, and political decision-makers.

Key Details

Project Details

  • P109588

  • Closed

  • Dahlia Lotayef

  • N/A

  • Cameroon

  • February 29, 2008

  • (as of board presentation)

    June 24, 2008

  • January 28, 2009

  • US$ 20.00 million

  • B

  • Not Applicable

  • June 27, 2013

  • BANK APPROVED

  • December 20, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 20.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 20.00
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 20.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 6, 2021 IDA-44770 Int Charges 339.04
Sep 6, 2021 IDA-44770 Loan Repay 57,268.07
Sep 6, 2021 IDA-44770 Int Charges 10.30
Sep 6, 2021 IDA-44770 Int Charges 10.30
Sep 6, 2021 IDA-44770 Int Charges 19,421.70
Sep 6, 2021 IDA-44770 Int Charges 19,421.70
Mar 15, 2022 IDA-44770 Int Charges 741.69
Aug 15, 2013 IDA-44770 Int Charges 728.97
Aug 15, 2013 IDA-44770 Int Charges 728.97
Aug 15, 2013 IDA-44770 Int Charges 25,598.12
Aug 15, 2013 IDA-44770 Int Charges 25,598.12
Feb 27, 2014 IDA-44770 Int Charges 23,352.76
Feb 27, 2014 IDA-44770 Int Charges 23,352.76
Aug 30, 2013 IDA-44770 Loan Disb -201,815.39
Aug 30, 2013 IDA-44770 Loan Disb -708,312.20
Sep 1, 2013 IDA-44770 Loan Cancel 11,630,660.00
Feb 15, 2014 IDA-44770 Int Charges 38.48
Feb 15, 2014 IDA-44770 Int Charges 38.48
Mar 25, 2014 IDA-44770 Loan Cancel 928,265.70
Aug 15, 2014 IDA-44770 Int Charges -26,222.57
Aug 15, 2014 IDA-44770 Int Charges 26,222.57
Aug 15, 2014 IDA-44770 Int Charges 154.74
Aug 15, 2014 IDA-44770 Int Charges 154.74
Aug 15, 2014 IDA-44770 Int Charges 22,945.31
Aug 15, 2014 IDA-44770 Int Charges 22,945.31
Feb 15, 2015 IDA-44770 Int Charges 117.36
Feb 15, 2015 IDA-44770 Int Charges 117.36
Feb 15, 2015 IDA-44770 Int Charges 20,252.83
Feb 15, 2015 IDA-44770 Int Charges 20,252.83
Aug 15, 2016 IDA-44770 Int Charges 168.98
Aug 15, 2016 IDA-44770 Int Charges 20,889.00
Aug 15, 2016 IDA-44770 Int Charges 20,889.00
Feb 15, 2017 IDA-44770 Int Charges 20,313.76
Feb 15, 2017 IDA-44770 Int Charges 20,313.76
Feb 15, 2017 IDA-44770 Int Charges 55.25
Feb 15, 2017 IDA-44770 Int Charges 55.25
Aug 15, 2017 IDA-44770 Int Charges 145.44
Aug 15, 2017 IDA-44770 Int Charges 145.44
Aug 15, 2017 IDA-44770 Int Charges 21,090.44
Aug 15, 2017 IDA-44770 Int Charges 21,090.44
Feb 15, 2018 IDA-44770 Int Charges 754.91
Feb 15, 2018 IDA-44770 Int Charges 754.91
Feb 15, 2018 IDA-44770 Int Charges 21,253.99
Feb 15, 2018 IDA-44770 Int Charges 21,253.99
Feb 24, 2021 IDA-44770 Int Charges 31.32
Feb 24, 2021 IDA-44770 Int Charges 20,365.35
Feb 24, 2021 IDA-44770 Int Charges 20,365.35
Feb 15, 2021 IDA-44770 Loan Repay 2,363.58
Mar 15, 2022 IDA-44770 Int Charges 741.69
Mar 15, 2022 IDA-44770 Loan Repay 55,501.23
Mar 15, 2022 IDA-44770 Int Charges 18,444.86
Mar 15, 2022 IDA-44770 Int Charges 18,444.86
Mar 15, 2022 IDA-44770 Int Charges 24.28
Mar 15, 2022 IDA-44770 Int Charges 24.28
Aug 29, 2022 IDA-44770 Int Charges 16,246.99
Aug 29, 2022 IDA-44770 Int Charges 16,246.99
Aug 29, 2022 IDA-44770 Int Charges 860.05
Aug 29, 2022 IDA-44770 Int Charges 860.05
Aug 29, 2022 IDA-44770 Loan Repay 52,387.23
Aug 29, 2022 IDA-44770 Int Charges 32.74
Aug 29, 2022 IDA-44770 Int Charges 32.74
Mar 20, 2023 IDA-44770 Int Charges 1,879.66
Mar 20, 2023 IDA-44770 Int Charges 1,879.66
Mar 20, 2023 IDA-44770 Loan Repay 53,909.83
Mar 20, 2023 IDA-44770 Int Charges 15.72
Mar 20, 2023 IDA-44770 Int Charges 15.72
Mar 20, 2023 IDA-44770 Int Charges 18,395.97
Mar 20, 2023 IDA-44770 Int Charges 18,395.97
Aug 15, 2023 IDA-44770 Int Charges 18,093.66
Aug 15, 2023 IDA-44770 Int Charges 18,093.66
Aug 15, 2023 IDA-44770 Loan Repay 53,610.86
Aug 15, 2023 IDA-44770 Int Charges 39.09
Aug 15, 2023 IDA-44770 Int Charges 39.09
Aug 15, 2023 IDA-44770 Int Charges 0.79
Aug 15, 2023 IDA-44770 Int Charges 0.79
Aug 20, 2024 IDA-44770 Int Charges 17,837.11
Aug 20, 2024 IDA-44770 Int Charges 17,837.11
Aug 20, 2024 IDA-44770 Int Charges 572.81
Aug 20, 2024 IDA-44770 Int Charges 572.81
Aug 20, 2024 IDA-44770 Loan Repay 54,051.87
Jun 24, 2008 IDA-44770 Loan Commitment 20,000,000.00
Feb 15, 2024 IDA-44770 Loan Repay 52,508.04
Feb 15, 2024 IDA-44770 Int Charges 17,200.58
Feb 15, 2024 IDA-44770 Int Charges 17,200.58
Feb 15, 2024 IDA-44770 Loan Repay 719.35
Aug 15, 2018 IDA-44770 Loan Repay 495.53
Sep 7, 2018 IDA-44770 Loan Repay 55,830.67
Sep 7, 2018 IDA-44770 Int Charges 21,124.52
Sep 7, 2018 IDA-44770 Int Charges 21,124.52
Feb 15, 2019 IDA-44770 Loan Repay 792.23
Sep 10, 2019 IDA-44770 Int Charges 22.61
Sep 10, 2019 IDA-44770 Int Charges 19,492.18
Sep 10, 2019 IDA-44770 Int Charges 19,492.18
Mar 5, 2019 IDA-44770 Int Charges 20,396.79
Mar 5, 2019 IDA-44770 Int Charges 20,396.79
Mar 5, 2019 IDA-44770 Loan Repay 55,220.87
Mar 5, 2019 IDA-44770 Int Charges 25.45
Mar 5, 2019 IDA-44770 Int Charges 25.45
Sep 10, 2019 IDA-44770 Int Charges 392.77
Sep 10, 2019 IDA-44770 Int Charges 392.77
Sep 10, 2019 IDA-44770 Loan Repay 55,101.27
Sep 10, 2019 IDA-44770 Int Charges 22.61
Mar 12, 2020 IDA-44770 Int Charges 766.89
Mar 12, 2020 IDA-44770 Int Charges 766.89
Mar 12, 2020 IDA-44770 Loan Repay 55,779.68
Mar 12, 2020 IDA-44770 Int Charges 29.04
Mar 12, 2020 IDA-44770 Int Charges 29.04
Mar 12, 2020 IDA-44770 Int Charges 20,289.88
Mar 12, 2020 IDA-44770 Int Charges 20,289.88
Sep 11, 2020 IDA-44770 Loan Repay 56,532.88
Sep 11, 2020 IDA-44770 Int Charges 31.96
Sep 11, 2020 IDA-44770 Int Charges 31.96
Sep 11, 2020 IDA-44770 Int Charges 20,457.46
Sep 11, 2020 IDA-44770 Int Charges 20,457.46
Aug 15, 2020 IDA-44770 Loan Repay 292.85
Feb 24, 2021 IDA-44770 Loan Repay 55,761.91
Feb 24, 2021 IDA-44770 Int Charges 31.32
Aug 15, 2015 IDA-44770 Int Charges 1,096.61
Aug 15, 2015 IDA-44770 Int Charges 1,096.61
Aug 15, 2015 IDA-44770 Int Charges 21,102.39
Aug 15, 2015 IDA-44770 Int Charges 21,102.39
Feb 15, 2016 IDA-44770 Int Charges 77.47
Feb 15, 2016 IDA-44770 Int Charges 77.47
Feb 15, 2016 IDA-44770 Int Charges 21,212.64
Feb 15, 2016 IDA-44770 Int Charges 21,212.64
Aug 15, 2016 IDA-44770 Int Charges 168.98
Sep 6, 2021 IDA-44770 Int Charges 339.04

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Moderately Unsatisfactory 2013-11-18
Financial Management Moderately Satisfactory 2013-11-18
Monitoring and Evaluation Moderately Satisfactory 2013-11-18
Progress towards achievement of PDO Moderately Unsatisfactory 2013-11-18
Procurement Moderately Satisfactory 2013-11-18
Overall Implementation Progress (IP) Moderately Unsatisfactory 2013-11-18
Project Management Moderately Satisfactory 2013-11-18

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-31-2014
Outcomes
Risk to Development OutcomeUnsatisfactory
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-24-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Infrastructure projects in the energy sector approved that comply with int standards for environmental & social issues (KPI)Value5.00100.0080.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    Commentpercentage per annumAll large Energy Projects submitted to the Interministerial Committee received an Environmental Conformity Certificates.
  • Energy sector facilities (existing) for which all enviromental & social impacts have been addressed (KPI)Value5.0050.0080.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentField missions to project sites were suspended since February 2012
  • Facilities for which annual environmental performance report certified as compliant by MinEP with EMP (KPI)Value10.0030.3070.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    Comment24 facilities (21,87%) have implemented their ESMPs in a satisfactory manner;50 facilities (45,45%) have implemented the ESMP inamoderate way; while 15 facilities (13,63%) has an unsatisfactory performance.
  • Domestic stakeholders with satisfactory understanding of norms and standards in matters of env & social diligence of large projects(KPI)Value1.0020.0030.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentNo data available beyond May 2012

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Legislation on land management and compensation systems for involuntary resettlement adoptedValueN0noYes
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentThe procurement process stopped due to the cancellation request.
  • EAs for new investments reviewed by Inter-Ministerial Committee (yearly)Value54.0080.0045.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentNo data available beyond March 2012.
  • Energy sector facilities (existing) for which all environmental and social impacts have been identified through an audit processValue0.0013.0080.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentNo data available beyond March 2012.
  • Sector guidelines on standards and procedural issues that integrate international best practices publishedValue0.002.006.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentOnly two guidelines were prepared. The remaining one is still under preparation.
  • Pollution permits and licences issuedValue0.000.000.00
    DateMay 29, 2008October 24, 2014March 31, 2014
    CommentThe legislation doesn't cover pollution permits and licenses. This indicator was not be able to be reviewed at the MTR process,due to the early cancellation request.
  • Non-compliance cases for which legal actions have been takenValue0.0050.0080.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentBased on results of the consolidated report of the inspection missions conducted in May 2012, it appears that 174 facilities havebeen inspected, and legal actions have been taken against 46 cases of non-compliance
  • Policy to protecting and promoting the rights of marginal populations adoptedValueNoYes
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentThe hiring process of the consultant to prepare the draft policy stopped as a result of the project's cancellation.Indicator not met as a result of the cancellation.
  • Reference health database developed (for selected reference sites)Value
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentReference data for the three main sites (Lom Pangar, Mem vele and Kribi) still not shared by the Ministry of Health (consideredconfidential).
  • Legal framework on cultural patrimony updatedValueNoYes
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentActivity stopped following Project's cancellation
  • Feedback comments/ questions about env/ social diligence provided monthly on the project websiteValue0.0030.0050.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentThe website design has been completed and operational .
  • Audits (security, social, environmental) undertaken for existing infrastructure (annual)Value0.0026.00100.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentIndicator not updated by the team.
  • EMPs for large electricity infrastructure satisfactorily implementedValue5.0080.0080.00
    DateMay 29, 2008October 24, 2013March 31, 2014
    CommentNo major change .
  • SESA for the energy sector completed and disseminatedValueNoYes
    DateOctober 24, 2013March 31, 2014
    CommentStudy is being prepared in the context of another Bank project (PDSEN) following cancellation of PRECESS.
  • approvedValue0.0024.000.00
    DateMay 29, 2008October 24, 2013
    CommentIndicator not updated by the team.
  • submittedValue0.0026.000.00
    DateMay 29, 2008October 24, 2013
    CommentNo major change.