TA for Capacity Development in Hydropower and Mining Sector

Abstract*

The objective of the Technical Assistance for Capacity Development in Hydropower and Mining Sectors Project for Lao People's Democratic Republic (PDR) is to increase human capacity and improve the performance of Government oversight institutions for the hydropower and mining sectors. There are four components to the project. The first component of the project is joint hydropower and mining learning program. This component aims to building critically...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Development objective is to increase human capacity and improve the performance of Government oversight institutions for the hydropower and mining sectors.

Key Details

Project Details

  • P109736

  • Closed

  • Shinya Nishimura

  • Lao People's Democratic Republic

  • US$ 8.00 million

  • Ministry of Energy and Mines

  • East Asia and Pacific

  • 2010

  • US$ 8.00 million

  • B

  • March 26, 2021

  • September 30, 2020

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 8.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 8.00
IBRD + IDA Commitment 8.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 8.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 15, 2020 IDA-54490 Int Charges 19.63
Jan 30, 2021 IDA-H9470 Loan Cancel 1,502.08
Nov 4, 2021 IDA-54490 Int Charges 30,496.02
Nov 4, 2021 IDA-54490 Int Charges 30,496.02
Oct 15, 2021 IDA-54490 Int Charges 161.10
Oct 15, 2021 IDA-54490 Int Charges 161.10
Apr 21, 2021 IDA-54490 Int Charges 197.46
Apr 21, 2021 IDA-54490 Int Charges 197.46
Apr 21, 2021 IDA-54490 Int Charges 31,176.23
Apr 21, 2021 IDA-54490 Int Charges 31,176.23
Apr 15, 2022 IDA-54490 Int Charges 235.50
Apr 15, 2022 IDA-54490 Int Charges 235.50
Apr 27, 2022 IDA-54490 Int Charges 29,101.13
Apr 27, 2022 IDA-54490 Int Charges 29,101.13
Oct 15, 2022 IDA-54490 Int Charges 1,131.64
Oct 15, 2022 IDA-54490 Int Charges 1,131.64
Oct 15, 2022 IDA-54490 Int Charges 26,632.23
Oct 15, 2022 IDA-54490 Int Charges 26,632.23
Apr 15, 2023 IDA-54490 Int Charges 954.61
Apr 15, 2023 IDA-54490 Int Charges 28,133.41
Apr 15, 2023 IDA-54490 Int Charges 28,133.41
Apr 15, 2023 IDA-54490 Int Charges 954.61
Oct 15, 2023 IDA-54490 Int Charges 28,490.76
Sep 21, 2017 IDA-54490 Loan Disb 309,959.16
Oct 26, 2017 IDA-54490 Loan Disb 685,075.50
Aug 2, 2018 IDA-54490 Loan Disb 270,941.56
Apr 15, 2018 IDA-54490 Int Charges 680.04
Apr 15, 2018 IDA-54490 Int Charges 680.04
Apr 15, 2018 IDA-54490 Int Charges 14,232.29
Apr 15, 2018 IDA-54490 Int Charges 14,232.29
Dec 5, 2017 IDA-54490 Loan Disb 127,129.73
Dec 5, 2017 IDA-54490 Loan Disb 360,013.00
Feb 21, 2018 IDA-54490 Loan Disb 317,544.88
Jan 4, 2018 IDA-54490 Loan Disb 191,195.66
Nov 28, 2018 IDA-54490 Loan Disb 193,315.39
May 10, 2018 IDA-54490 Loan Disb 70,987.94
May 10, 2018 IDA-54490 Loan Disb 98,416.83
Jun 28, 2018 IDA-54490 Loan Disb 173,967.90
Oct 15, 2023 IDA-54490 Int Charges 28,490.76
Apr 15, 2024 IDA-54490 Int Charges 28,137.00
Apr 15, 2024 IDA-54490 Int Charges 28,137.00
Apr 15, 2024 IDA-54490 Int Charges 494.05
Apr 15, 2024 IDA-54490 Int Charges 494.05
Oct 15, 2023 IDA-54490 Int Charges 361.97
Oct 15, 2023 IDA-54490 Int Charges 361.97
Jun 3, 2014 IDA-54490 Loan Commitment 8,900,000.00
Jun 3, 2014 IDA-H9470 Loan Commitment 8,900,000.00
Jan 12, 2010 IDA-H5390 Loan Commitment 8,000,000.00
Nov 28, 2016 IDA-H9470 Loan Disb 180,006.52
Dec 15, 2016 IDA-H9470 Loan Disb 236,987.52
Dec 15, 2016 IDA-H9470 Loan Disb 500,000.00
Sep 1, 2016 IDA-H9470 Loan Disb 488,042.30
Jun 15, 2017 IDA-54490 Loan Disb 270,009.75
Mar 29, 2017 IDA-H9470 Loan Disb 116,908.72
Apr 25, 2017 IDA-H9470 Loan Disb 278,400.72
May 15, 2017 IDA-H9470 Loan Disb 402,232.12
Apr 12, 2017 IDA-H9470 Loan Disb 300,333.90
Aug 3, 2017 IDA-54490 Loan Disb 1,000,000.00
Oct 15, 2017 IDA-54490 Int Charges 2,181.96
Oct 15, 2017 IDA-54490 Int Charges 2,181.96
Feb 22, 2017 IDA-H9470 Loan Disb 734,519.70
Sep 21, 2017 IDA-54490 Loan Disb 723,852.50
Sep 21, 2017 IDA-54490 Loan Disb 270,009.75
Jun 28, 2018 IDA-54490 Loan Disb 71,344.61
Aug 22, 2018 IDA-54490 Loan Disb 198,980.67
Jul 11, 2018 IDA-54490 Loan Disb 360,013.00
Sep 5, 2018 IDA-54490 Loan Disb 237,726.75
May 14, 2019 IDA-54490 Loan Disb 246,962.52
Oct 15, 2018 IDA-54490 Int Charges 303.50
Oct 15, 2018 IDA-54490 Int Charges 303.50
Oct 15, 2018 IDA-54490 Int Charges 17,752.63
Oct 15, 2018 IDA-54490 Int Charges 17,752.63
Jan 3, 2019 IDA-54490 Loan Disb 703,663.00
Nov 8, 2018 IDA-54490 Loan Disb 118,009.29
Oct 4, 2018 IDA-54490 Loan Disb 171,129.88
Feb 8, 2019 IDA-54490 Loan Disb 145,491.73
Aug 6, 2019 IDA-54490 Loan Disb 109,658.25
Aug 6, 2019 IDA-54490 Loan Disb 90,462.58
May 20, 2019 IDA-54490 Loan Disb 265,541.44
Apr 15, 2019 IDA-54490 Int Charges 642.92
Apr 15, 2019 IDA-54490 Int Charges 642.92
Apr 15, 2019 IDA-54490 Int Charges 24,384.55
Apr 15, 2019 IDA-54490 Int Charges 24,384.55
Apr 8, 2019 IDA-54490 Loan Disb 110,537.45
Oct 18, 2019 IDA-54490 Int Charges 28,141.08
Oct 18, 2019 IDA-54490 Int Charges 28,141.08
Sep 20, 2019 IDA-54490 Loan Disb 123,186.38
Oct 18, 2019 IDA-54490 Int Charges 86.42
Oct 18, 2019 IDA-54490 Int Charges 86.42
Oct 22, 2019 IDA-54490 Loan Disb 129,714.40
Apr 15, 2020 IDA-54490 Int Charges 116.95
Apr 15, 2020 IDA-54490 Int Charges 116.95
Apr 15, 2020 IDA-54490 Int Charges 29,705.02
Apr 15, 2020 IDA-54490 Int Charges 29,705.02
Oct 22, 2020 IDA-54490 Int Charges 30,640.90
Oct 22, 2020 IDA-54490 Int Charges 30,640.90
Oct 15, 2020 IDA-54490 Int Charges 19.63
Dec 23, 2014 IDA-H5390 Loan Disb 52,459.28
Sep 30, 2014 IDA-H5390 Loan Disb 84,872.87
Oct 28, 2014 IDA-H5390 Loan Disb 108,200.61
Oct 3, 2014 IDA-H5390 Loan Disb 229,977.10
Sep 4, 2013 IDA-H5390 Loan Disb 53,778.34
Nov 24, 2014 IDA-H9470 Loan Disb 500,000.00
Nov 25, 2014 IDA-H5390 Loan Disb 160,814.95
Nov 25, 2014 IDA-H5390 Loan Disb 127,069.99
Nov 18, 2014 IDA-H5390 Loan Disb 139,917.50
Feb 13, 2014 IDA-H5390 Loan Disb 207,993.98
Dec 26, 2013 IDA-H5390 Loan Disb 26,983.50
Nov 21, 2013 IDA-H5390 Loan Disb 16,955.68
Oct 2, 2013 IDA-H5390 Loan Disb 124,442.79
Feb 25, 2014 IDA-H5390 Loan Disb 100,900.00
Aug 8, 2013 IDA-H5390 Loan Disb 34,804.90
Nov 5, 2013 IDA-H5390 Loan Disb 81,462.81
Feb 7, 2014 IDA-H5390 Loan Disb 44,626.86
Feb 20, 2014 IDA-H5390 Loan Disb 94,582.57
Apr 11, 2014 IDA-H5390 Loan Disb 211,104.02
Apr 1, 2014 IDA-H5390 Loan Disb 113,524.80
May 6, 2014 IDA-H5390 Loan Disb 135,000.00
May 6, 2014 IDA-H5390 Loan Disb 114,616.96
May 1, 2014 IDA-H5390 Loan Disb 111,429.95
Apr 29, 2014 IDA-H5390 Loan Disb 203,605.38
Mar 12, 2014 IDA-H5390 Loan Disb 244,015.66
Jul 21, 2014 IDA-H5390 Loan Disb 369,629.70
Feb 17, 2015 IDA-H5390 Loan Disb 173,046.86
Feb 17, 2015 IDA-H9470 Loan Disb 63,165.68
Jul 15, 2014 IDA-H5390 Loan Disb 81,798.40
Jun 20, 2014 IDA-H5390 Loan Disb 266,074.53
Jun 18, 2014 IDA-H5390 Loan Disb 168,008.16
May 29, 2014 IDA-H5390 Loan Disb 60,501.90
Aug 13, 2014 IDA-H5390 Loan Disb 139,917.48
Aug 13, 2014 IDA-H5390 Loan Disb 137,039.73
Jan 28, 2015 IDA-H5390 Loan Disb 58,355.12
Jan 28, 2015 IDA-H9470 Loan Disb 7,136.00
Jan 26, 2015 IDA-H5390 Loan Disb 105,861.06
Aug 5, 2014 IDA-H5390 Loan Disb 157,065.89
Sep 16, 2014 IDA-H5390 Loan Disb 132,532.80
Apr 1, 2015 IDA-H9470 Loan Disb 98,477.58
Apr 1, 2015 IDA-H5390 Loan Disb 101,773.82
May 5, 2015 IDA-H5390 Loan Disb 25,515.23
May 5, 2015 IDA-H9470 Loan Disb 87,028.41
Jun 9, 2015 IDA-H5390 Loan Disb 5,974.00
Jun 9, 2015 IDA-H9470 Loan Disb 71,975.44
Jun 30, 2015 IDA-H9470 Loan Disb 119,466.40
Jun 30, 2015 IDA-H5390 Loan Disb 137,179.62
Oct 1, 2015 IDA-H9470 Loan Disb 325,529.60
Jan 19, 2016 IDA-H9470 Loan Disb 304,018.25
Nov 17, 2015 IDA-H9470 Loan Disb 114,639.50
Sep 15, 2015 IDA-H5390 Loan Disb 61,219.24
Sep 16, 2015 IDA-H9470 Loan Disb 410,961.78
Mar 16, 2016 IDA-H9470 Loan Disb 205,124.48
Feb 16, 2016 IDA-H9470 Loan Disb 239,952.40
Apr 6, 2016 IDA-H9470 Loan Disb 314,298.53
Aug 9, 2016 IDA-H9470 Loan Disb 229,195.67
Jun 7, 2016 IDA-H9470 Loan Disb 208,916.52
Feb 1, 2017 IDA-H9470 Loan Disb 31,361.13
Dec 7, 2016 IDA-H9470 Loan Disb 273,407.60
May 24, 2016 IDA-H9470 Loan Disb 279,375.75
Jun 28, 2016 IDA-H9470 Loan Disb 216,482.48
Oct 11, 2016 IDA-H9470 Loan Disb 285,410.94
Jun 10, 2016 IDA-H9470 Loan Disb 246,381.67
Sep 21, 2016 IDA-H9470 Loan Disb 157,999.62

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2020-04-15
Procurement Satisfactory 2020-04-15
Financial Management Satisfactory 2020-04-15
Monitoring and Evaluation Satisfactory 2020-04-15
Overall Implementation Progress (IP) Satisfactory 2020-04-15
Project Management Satisfactory 2020-04-15

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-26-2021
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-07-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of trained GOL staff report medium to intensive use of knowledge and lessons learned from capacity building measures.Value0.0080.0080.00
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Number of River Basins, where all Hydropower Projects are monitored for CA compliance.Value0.0011.005.00
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Direct project beneficiariesValue1500.007600.000.00
    DateDecember 11, 2009September 30, 2020
    Comment
  • Percentage of on-the-ground inspections of exploration/mining operations performed using improved systems and procedures in line with international practice.Value0.0072.0050.00
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Female beneficiariesValue0.001525.000.00
    DateDecember 11, 2009March 2, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Approved Standard Operation Procedures (SOP) for IPP process.ValueNo SOPFully achieved: All 26 SOPs were endorsed by MEM iSOP endorsed by MEM
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Geoscience infrastructure mapping (Geophysics & Geology) in two selected areasValueNo geodataAchieved: Field mapping in two selected areas finaFinal deliverables & by-products (100%)
    DateAugust 26, 2016September 30, 2020September 30, 2018
    Comment
  • Annual report on the implementation of the Policy on Sustainable Hydropower Development (PSHD).ValueOriginal NPSH in placeFully achieved: 2017-2019 Annual Status Report AvaAnnual Status Report
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Number of GoL female and male personnel trained on technical aspects, such as contract management, financial analysis, accounting, environmental and social management.Value0.00880.00750.00
    DateAugust 31, 2010September 30, 2020September 30, 2020
    Comment
  • Percentage of New Hydropower Power Purchasing Agreement (PPA) that are subject to the avoided costs methodologyValue0.00100.00100.00
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Model Mining Development Agreement approved by MEMValueNon standardized terms and conditions for mining cAchieved and exceeded: The MDA has been adjusted tDraft MDA approved by MEM
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Completed and operationalized the performance evaluation (KPI) system for MEM and PDEMsValueNo KPI system in placeFully achieved: the operationalization of the systAssessment of overall results
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Completed power trade strategy and action plan.ValueNo power trade strategy and action planAchieved: The “Vision 2030, Strategic Development White Paper issued by MEM
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Number of approved mining regulations.Value0.0013.0012.00
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Percentage of new hydropower IPP applying the standard CA requirements.Value0.00100.00100.00
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment
  • Completed mining sector strategy and action plan.ValueNo strategy and action plan for mining sectorAchieved: The MEM sector strategies (required by tSector Strategy approved by MEM
    DateAugust 31, 2010September 30, 2020September 30, 2018
    Comment