Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 6.80 |
P109737
Closed
Abimbola Adubi
N/A
October 27, 2009
(as of board presentation)
July 8, 2010
November 25, 2010
US$ 6.80 million
N/A
2011
US$ 6.80 million
B
Not Applicable
December 31, 2013
BANK APPROVED
June 27, 2014
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 6.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 6.80 |
Total Project Cost** | 6.80 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2013-11-19 |
Overall | Low | 2013-11-19 |
Overall Implementation Progress (IP) | Satisfactory | 2013-11-19 |
Procurement | Satisfactory | 2013-11-19 |
Financial Management | Moderately Satisfactory | 2013-11-19 |
Summary Global Objective Rating | Satisfactory | 2013-11-19 |
Project Management | Satisfactory | 2013-11-19 |
Monitoring and Evaluation | Satisfactory | 2013-11-19 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2014 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 10-21-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Unsatisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Stakeholder perception of the enabling environment for sustainable land management | Value | 0.32 | 0.56 | 0.60 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment | This is a composite index ranging from 0 to 1.00 giving expert perception on the extent to which the enabling conditions for SLM(Institutions, Financing, Knowledge, etc) are improving or deteriorating. | An independent tracking of the composite index was conducted May, 2012 to give the national average of 0.563. However, when theoverall mean scores of the states were compared, it was observed that the highest mean score was recorded by Sokoto (6.81) followedby Kwara (6.77), Ebonyi (6.74), Kogi (6.66), Benue (6.53), Ondo (6.44), Taraba (6.32), Osun (6.13), Delta (6.06) and Kaduna (6.05).However, the states with the lowest mean scores were Akwa-Ibom (4.09), Edo (4.59), Kano (4.66) and Jigawa (4.9). |
Direct project beneficiaries (% female - Cumulative) | Value | 0.00 | 33743.00 | 259000.00 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment | This figure which represent 14.98% achievement of the target is made up of 20,622 males (53%) and 18,183 females (47%). |
Participating communities that have selected SLM sub-projects for inclusion in their Local Development Plans (LDPs) (cumulative % of communities) | Value | 0.00 | 24.90 | 10.00 |
Date | May 14, 2010 | April 3, 2013 | December 31, 2013 | |
Comment | The project is not yet effective and communities are just being sensitized to SLM practices. | 1,096 FCAs out of the 4,402 participating FCAs whose LDPs have been approved for implementation have included a total of 3,076 SLMsub-projects in their LDPs. To date, 2,490 SLM sub-projects have been fully implemented across the participating states. | 740 FCAs |
Community Associations reached through training and / or communications on SLM practice / planning (# per year) | Value | 0.00 | 5185.00 | 7400.00 |
Date | May 14, 2010 | April 3, 2013 | December 31, 2013 | |
Comment | All FCAs in the baseline project are being sensitized on SLM practice but 1,096 of them are currently adopting SLM. |
People reached through training and/or communications on SLM practice / planning (# per year) | Value | 0.00 | 5543.00 | 4714.00 |
Date | May 14, 2010 | April 3, 2013 | December 31, 2013 | |
Comment | See details below. | See details below. |
Local Government Areas trained in rural land use planning | Value | 0.00 | 30.00 | 62.00 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment | Training on land use plan mapping software for the selected Local Government Areas was conducted for 30 Local government Areas i.e.for 15 states. Proposal to train the remaining 32 local government is in progress. |
State Governments participating in development of Nigeria's multi-sector SLM Investment Framework (cumulative # of State governments) | Value | Terms of Reference approved by Governement's Natio | About 30 states have reported the formation of the | 20 States + federal goverment |
Date | May 14, 2010 | April 3, 2013 | December 31, 2013 | |
Comment | Project has commenced and progress already being recorded. |
Improved monitoring tools developed to track adoption of SLM practices and changes in land productivity (# tools) | Value | 0.00 | 1.00 | 2.00 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment | Terms of Reference (TOR) for Studies on Monitoring Tool to Track Adoption Rates of Specific Sustainable Land Management (SLM)Practices under Fadama III GEF has been developed; and current evaluation of consultants that would be engaged in the consultancy. |
SLM Information System developed (Yes/No) | Value | No (does not exist) | Yes | |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment | Yes |
Additional Area under Sustainable Land Management | Value | 0.00 | 100091.00 | 0.00 |
Date | August 30, 2013 | |||
Comment | Up to 100,091 ha have been added to SLM management across the 36 states and the FCT. |
Percentage of women beneficiaries | Value | 0.00 | 47.00 | 40.00 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment | This figure should be in percentages and is corrected in the entries. | A total of 18,183 women beneficiaries out of a total of 38,805 beneficiaries, representing 47% are currently implementing SLMsub-projects across the 36 States and the FCT. | The project is targeting 40% female participants out of the total beneficiaries. |
Community facilitators | Value | 0.00 | 1950.00 | 2500.00 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment |
Extension and advisory staff | Value | 0.00 | 479.00 | 814.00 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment |
Local Government Staff | Value | 0.00 | 398.00 | 700.00 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment |
State Government Staff | Value | 0.00 | 1377.00 | 5000.00 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment | This includes all active members of the already formed 30 states SLM Committee. |
Federal Government Staff | Value | 0.00 | 25.00 | 200.00 |
Date | May 14, 2010 | August 30, 2013 | December 31, 2013 | |
Comment | 25 Federal Officers. |
Additional Area under Sustainable Land Management | Value | |||
Date | ||||
Comment |