Skip to Main Navigation

Bangladesh DSC IV-Supplemental Financing II

Abstract*

The second additional financing (SF2) of the Fourth Development Support Credit of Bangladesh will help Government of Bangladesh (GOB) continue along the path of reforms needed to accelerate economic growth and poverty reduction. The SF2 credit will help GOB meet the immediate short-term needs by reducing the fiscal pressure on the FY08 budget arising from unforeseen cyclone-related spending, including the need to provide large amounts of cash and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Budget support in response to SIDR Cyclone in order to meet emergency cyclone related expenditures and thus help the government avoid borrowing excessively from the domestic banking system and/or cut priority development and poverty reducing expenditures.

Key Details

Project Details

  • P110110

  • Closed

  • Zahid Hussain

  • N/A

  • Bangladesh

  • January 10, 2008

  • (as of board presentation)

    January 10, 2008

  • N/A

  • US$ 100.00 million

  • N/A

  • South Asia

  • 2008

  • US$ 100.00 million

  • N/A

  • Not Applicable

  • February 13, 2008

  • BANK APPROVED

  • P074801

  • June 7, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-12-2009PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

No data available.