Power Distribution and Rural Electrification

Development Objective

Restructuring and additional financing was approved by the Board on June 19, '08. The revised PDOs of the restructured project are: (i) Expansion of electricity access in rural areas; (ii) Improve the quality and adequacy of the electricity supply; (iii)Regulatory and institutional reforms in the sector to increase efficiency.

Key Details

Project Details

  • P110202

  • Closed

  • Kyran O'Sullivan

  • N/A

  • Eritrea

  • March 5, 2008

  • (as of board presentation)

    June 26, 2008

  • N/A

  • US$ 17.50 million

  • B

  • January 15, 2013

  • June 30, 2010

  • BANK APPROVED

  • P057929

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 17.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 17.50
IBRD + IDA Commitment 17.50
Lending Instrument
Grant Amount N/A
Total Project Cost** 17.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework