Financier | Commitments |
---|---|
IDA Credit | 6.50 |
P110555
Closed
Imtiaz Hizkil
N/A
May 1, 2008
(as of board presentation)
May 1, 2008
November 26, 2008
US$ 6.50 million
N/A
2008
US$ 6.50 million
B
June 25, 2013
December 31, 2012
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 6.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 6.50 |
IBRD + IDA Commitment | 6.50 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 6.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 1, 2008 | IDA-H3720 | Loan Commitment | 6,500,000.00 |
May 6, 2010 | IDA-H5660 | Loan Commitment | 15,000,000.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2012-12-26 |
Project Management | Moderately Satisfactory | 2012-12-26 |
Monitoring and Evaluation | Moderately Satisfactory | 2012-12-26 |
Counterpart Funding | Satisfactory | 2012-12-26 |
Financial Management | Unsatisfactory | 2012-12-26 |
Progress towards achievement of PDO | Satisfactory | 2012-12-26 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2012-12-26 |
Overall Safeguards Rating | Satisfactory | 2012-12-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2013 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 01-28-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Better Reservoir Management | Value | 36.00 | 0.00 | 0.00 |
Date | April 30, 2008 | December 14, 2012 | December 31, 2012 | |
Comment | Number of days below dead zone in winter 2008 - 36 days | In 2011/12 winter the reservoir level did not fall. The target is achieved. | Reservoir level would not fall below "dead zone". |
Increase in Winter Electricity Availability | Value | 1330.00 | 2241.00 | 1330.00 |
Date | March 31, 2008 | December 14, 2012 | December 31, 2012 | |
Comment | (in GWh) - Winter electricity consumption by households in Tajikistan | 2011/12 winter - 68% increase2010/11 winter - 71% increase 2009/10 winter - 64% increase (2184 GWh)2008/09 winter - 5%increase(1395 GWh) | (in GWh) - Not less than the baseline |
Increase of Winter Electricity in Dushanbe | Value | 442.00 | 1032.00 | 442.00 |
Date | March 31, 2008 | December 14, 2012 | December 31, 2012 | |
Comment | (in GWh) - Winter electricity consumption by households in Dushanbe | 2011/12 winter - 133% increase2010/11 winter - 82% increase2009/10 winter - 68% increase (743 GWh)2008/09 winter - 9% increase(483 GWh) | (in GWh) - Not less than the baseline |
Winter electricity supply to the Northern areas households (hours per day) | Value | 7.80 | 9.30 | 7.80 |
Date | March 31, 2009 | December 14, 2012 | December 31, 2012 | |
Comment | Baseline - 2008/09 winter | 2011/12 winter - 19% increase2010/11 winter - 8% increase2009/10 winter - 1% increase (7.9 hours) | Not less than the baseline |
Winter electricity average household consumption supplied from Sangtuda-1 (hours per day) | Value | 2.40 | 2.90 | 2.40 |
Date | March 31, 2009 | December 14, 2012 | December 31, 2012 | |
Comment | Baseline - 2008/09 winter.Portion of winter power consumption of an average household supplied from Sangtuda-1 power plant(hours/day) | 2011/12 winter - 22% increase2010/11 winter - 13% increaseAdditional increase is due to purchase of electricity from Sangtuda-1,which was not envisaged in the original project. | Not less than the baseline |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
LSRFO tanks are delivered to warehouses and stored safely. An additional indicator is the amount of power generated in case it is necessary to use this back-up reserve | Value | not applicable | Fuel oil (5,000 tons) has been delivered to Dushan | Delivery of 4000-4300 tones |
Date | February 15, 2008 | May 31, 2011 | December 31, 2010 | |
Comment |
Additional winter power from Sangtuda-1 power plant (IPP) (GWh) | Value | 0.00 | 1161.00 | 1226.00 |
Date | November 1, 2011 | December 14, 2012 | December 31, 2012 | |
Comment | This figure shows only the power procured during winter months of 2011/2012.The electricity procured during November and Decemberof 2012 is currently not included. Once this electricity i.e. for the months of November and December, is included the end targetwill be achieved.2010/11 winter - 1071.0 GWh2009/10 winter - 883 GWh |