Energy Emergency Project

Development Objective

The development objective of the project is urgently increase the volume and reliability of the national energy supply, especially in the winter season by supporting the implementation of the Recipient's Energy Emergency Mitigation Plan (EEMAP).

Key Details

Project Details

  • P110555

  • Closed

  • Imtiaz Hizkil

  • N/A

  • Tajikistan

  • May 1, 2008

  • (as of board presentation)

    May 1, 2008

  • November 26, 2008

  • US$ 6.50 million

  • B

  • June 25, 2013

  • December 31, 2012

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 6.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 6.50
IBRD + IDA Commitment 6.50
Lending Instrument
Grant Amount N/A
Total Project Cost** 6.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 1, 2008 IDA-H3720 Loan Commitment 6,500,000.00
May 6, 2010 IDA-H5660 Loan Commitment 15,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2012-12-26
Project Management Moderately Satisfactory 2012-12-26
Monitoring and Evaluation Moderately Satisfactory 2012-12-26
Counterpart Funding Satisfactory 2012-12-26
Financial Management Unsatisfactory 2012-12-26
Progress towards achievement of PDO Satisfactory 2012-12-26
Overall Implementation Progress (IP) Moderately Satisfactory 2012-12-26
Overall Safeguards Rating Satisfactory 2012-12-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2013
Outcomes
Risk to Development OutcomeSubstantial
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-28-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Better Reservoir ManagementValue36.000.000.00
    DateApril 30, 2008December 14, 2012December 31, 2012
    CommentNumber of days below dead zone in winter 2008 - 36 daysIn 2011/12 winter the reservoir level did not fall. The target is achieved.Reservoir level would not fall below "dead zone".
  • Increase in Winter Electricity AvailabilityValue1330.002241.001330.00
    DateMarch 31, 2008December 14, 2012December 31, 2012
    Comment(in GWh) - Winter electricity consumption by households in Tajikistan2011/12 winter - 68% increase2010/11 winter - 71% increase 2009/10 winter - 64% increase (2184 GWh)2008/09 winter - 5%increase(1395 GWh)(in GWh) - Not less than the baseline
  • Increase of Winter Electricity in DushanbeValue442.001032.00442.00
    DateMarch 31, 2008December 14, 2012December 31, 2012
    Comment(in GWh) - Winter electricity consumption by households in Dushanbe2011/12 winter - 133% increase2010/11 winter - 82% increase2009/10 winter - 68% increase (743 GWh)2008/09 winter - 9% increase(483 GWh)(in GWh) - Not less than the baseline
  • Winter electricity supply to the Northern areas households (hours per day)Value7.809.307.80
    DateMarch 31, 2009December 14, 2012December 31, 2012
    CommentBaseline - 2008/09 winter2011/12 winter - 19% increase2010/11 winter - 8% increase2009/10 winter - 1% increase (7.9 hours)Not less than the baseline
  • Winter electricity average household consumption supplied from Sangtuda-1 (hours per day)Value2.402.902.40
    DateMarch 31, 2009December 14, 2012December 31, 2012
    CommentBaseline - 2008/09 winter.Portion of winter power consumption of an average household supplied from Sangtuda-1 power plant(hours/day)2011/12 winter - 22% increase2010/11 winter - 13% increaseAdditional increase is due to purchase of electricity from Sangtuda-1,which was not envisaged in the original project.Not less than the baseline

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • LSRFO tanks are delivered to warehouses and stored safely. An additional indicator is the amount of power generated in case it is necessary to use this back-up reserveValuenot applicableFuel oil (5,000 tons) has been delivered to DushanDelivery of 4000-4300 tones
    DateFebruary 15, 2008May 31, 2011December 31, 2010
    Comment
  • Additional winter power from Sangtuda-1 power plant (IPP) (GWh)Value0.001161.001226.00
    DateNovember 1, 2011December 14, 2012December 31, 2012
    CommentThis figure shows only the power procured during winter months of 2011/2012.The electricity procured during November and Decemberof 2012 is currently not included. Once this electricity i.e. for the months of November and December, is included the end targetwill be achieved.2010/11 winter - 1071.0 GWh2009/10 winter - 883 GWh