Financier | Commitments |
---|---|
Education for All - Fast Track Initiative | 76.10 |
P110576
Closed
Yacinthe Gbaye
N/A
March 28, 2008
(as of board presentation)
May 23, 2007
April 18, 2008
US$ 76.10 million
N/A
2007
US$ 76.10 million
B
Not Applicable
June 15, 2012
BANK APPROVED
July 17, 2024
Financier | Commitments |
---|---|
Education for All - Fast Track Initiative | 76.10 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 76.10 |
Total Project Cost** | 76.10 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2012-06-15 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2012-06-15 |
Counterpart Funding | Satisfactory | 2012-06-15 |
Monitoring and Evaluation | Moderately Satisfactory | 2012-06-15 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2012-06-15 |
Project Management | Moderately Satisfactory | 2012-06-15 |
Financial Management | Satisfactory | 2012-06-15 |
Overall Safeguards Rating | Satisfactory | 2012-06-15 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-18-2012 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 07-08-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Primary education completion rate - (%) total/girls | Value | Total: 65%; Girls: 54% (school year 2005/06) | Total 64.3%; Girls 57.5% | Total: 68%; Girls: 60% (school year 2011/2012) |
Date | June 24, 2008 | April 6, 2012 | June 15, 2012 | |
Comment | Compared to school year 09/10 there was not any significant improvement. The boys' PCR is 71%. The target will not be met at theclosing date due to high level of repetition and drop outs. Actions are ongoing and will be completed by other adequate actionstoimprove this situation in the medium term. | Based on the difficulties encountered in terms of completion rate , the end-of-project target has been adjusted downward from t72percent to 68 percent total, and from 65 percent to 60 percent for girls during the second restructuring of the program |
Gross enrolment rate (GER) in pre-school | Value | 4.50 | 11.30 | 10.00 |
Date | July 31, 2008 | April 6, 2012 | June 15, 2012 | |
Comment | SY 2005/06 |
Gross enrolment rate (GER) in primary school | Value | 93.00 | 111.50 | 112.00 |
Date | July 30, 2008 | April 6, 2012 | June 15, 2012 | |
Comment | SY 2005/06 | SY 2010/11 | SY 2011/12 |
Repetition rate | Value | 7.50 | 16.40 | 10.00 |
Date | June 17, 2006 | April 6, 2012 | June 15, 2012 | |
Comment | SY 2005/06. The base line is atypical because in this SY, almost all the students in grade 6 successfully passed the final examofprimary education: the repetition rate in grade 6 was 5 per cent | SY 2011/12. This target will not be met by the closing date but actions are underway to improve this indicator. | SY 2010/2011 |
Female students (%) | Value | 44.40 | 46.50 | 47.50 |
Date | June 17, 2006 | April 6, 2012 | June 15, 2012 | |
Comment | SY 2010/11. There was a grow in the number of female students ; but this indicator didn't register significant improvement in2011. The target can not be met in spite of the intensive sensitization that was carried out at the beginning of SY 2011/12 |
People to pass a test in initial literacy or post-literacy training (number) | Value | 23618.00 | 107401.00 | 51000.00 |
Date | June 17, 2006 | June 2, 2012 | June 15, 2012 | |
Comment | SY 2005/06 | 73522 persons financed by the government passed successively the initial test considering the data available in May 2012 . Thetraining of about 51000 persons through the project has just ended. The provisional data indicate that 33879 has passedsuccessively the final test. | SY 2011/12 |
Direct project beneficiaries | Value | 1606946.00 | 1684587.00 | 1730401.00 |
Date | June 7, 2010 | April 6, 2012 | June 15, 2012 | |
Comment | Data for SY 2008/9 | Data for SY 2010/11. The target will likely be met at the end of the project. However, the part of the female beneficiaries didnotregister improvement since SY 2009/10 |
Female beneficiaries | Value | 46.00 | 46.30 | 48.00 |
Date | June 7, 2010 | April 6, 2012 | June 15, 2012 | |
Comment | SY 2008/09 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Implementation of a computerization framework for the information management system | Value | Computerization framework set up | ||
Date | April 6, 2012 | June 15, 2012 | ||
Comment | There is a significant delay in the implementation of this activity. The consultant has just been recruited. The activity will notbe completed by the closing date. |
Number of Central ministry staff trained in project management (e.g. procurement, financial management, planning etc) | Value | not available | 103 | 100 |
Date | June 6, 2006 | April 6, 2012 | June 15, 2012 | |
Comment | Training in procurement, planning, monitoring and evaluation, data base. The implementation of the training action plan isunderway. The target will be met. |
System for learning assessment at the primary level | Value | No | Yes | Yes |
Date | July 15, 2006 | April 6, 2012 | June 15, 2012 | |
Comment | The learning assessment has been carried out in May 2011 and the report released in April 2012 | Learning assessment: final test completed and report available |
Pre-school and primary students receiving at least one meal per day | Value | 0.00 | 125000.00 | 110000.00 |
Date | April 18, 2008 | June 1, 2012 | June 15, 2012 | |
Comment | This is a provisional data for the SY 2011/12. | SY 2011/12 |
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions. | Value | 0.00 | 1941.00 | 1926.00 |
Date | April 18, 2008 | April 6, 2012 | June 15, 2012 | |
Comment | The construction of 260 classrooms is underway. |
Number of additional qualified primary teachers resulting from project interventions. | Value | 0.00 | 7971.00 | 8000.00 |
Date | April 18, 2008 | April 6, 2012 | June 15, 2012 | |
Comment | 7971 out of 9970 community teachers who received the three-years in-service training passed successively the written exam ofCEAP.The final exam will be held by June 2012. | Number of teachers who successfully passed the first exam of CEAP and will have to be presented to the final exam that iseducational application in June 2012. |
Utility of the learning assessment system | Value | 0.00 | 1.00 | 1.00 |
Date | July 15, 2006 | April 6, 2012 | June 15, 2012 | |
Comment | The learning assessment is planned for the school year 2010-2011 | Learning assessment: final test completed and report available |
Canteens receiving food supply financed by the program | Value | 0.00 | 501.00 | 501.00 |
Date | April 18, 2008 | June 1, 2012 | June 15, 2012 | |
Comment | 501 schools has been selected for the food supply financed by the program since January 2011 |
School having received learning material (number) | Value | 0.00 | 8059.00 | 5763.00 |
Date | April 18, 2008 | June 1, 2012 | June 15, 2012 | |
Comment | Direct financing for 8059 schools which purchased learning material according to their needs. | Direct financing for 5763 schools to purchase learning material according to their needs. |
Classes visited each year by the inspectors and the educational advisers (Percentage) | Value | 6.00 | 65.90 | 40.00 |
Date | December 31, 2009 | June 1, 2012 | June 15, 2012 | |
Comment | Data for the SY 2010/11. The data for 2011/12 is not yet available. |
Latrines constructed | Value | 0.00 | 375.00 | 324.00 |
Date | April 18, 2008 | June 1, 2012 | June 15, 2012 | |
Comment | 313 blocks of 4 latrines and 62 blocks of 2latrines |
Number of community teachers benefiting from training to obtain a CEAP | Value | 9979 | 10000 | |
Date | April 6, 2012 | June 15, 2012 | ||
Comment | This activity is financed by the program FTI-FCB, UNICEF and the Government. Two years training has been completed and theteachers passed the written exam of CEAP.The final exam will be held by June 2012. | 3 years training for 10000 community teachers |
Teachers trained in service (number) (Core AFR) | Value | 0 | 52255 | 16000 (school year 2010/11) |
Date | June 26, 2008 | April 6, 2012 | June 15, 2012 | |
Comment | (i) 20 days in-service training of 3253 teachers in 2009 for the preparation of the CEAP exam(ii) 10 days in-service trainingfor2806 preschool teachers in 2011;(iii) 6 days in-service training of 46196 primary teachers in 2011 |
Number of girls and women literates in national language | Value | 0 | 28940 | |
Date | June 24, 2008 | April 6, 2012 | June 15, 2012 | |
Comment | 29200 girls and women are enrolled in the training through the ''faire faire" approach which has just ended. The breakdown bygender of the provisional data of the number who passed successively the test is not yet available . However, the Governmentachieved on its own resources the training of 37301 girls and women in 2009 , 2010 and 2011. |