CO-National Macroproyectos Social Interest Program Project

Abstract*

The objective of the National Macroproyectos Social Interest Program Project for Colombia is to enable access to affordable housing solutions for low-income beneficiaries. There are three components to the project, the first component being low-income land and housing development. The component will finance two sub-components: technical studies and fiduciary management for Macroproyectos; and grants for low income land and housing development. The...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project development objective is to enable access to affordable housing solutions for low-income beneficiaries.

Key Details

Project Details

  • P110671

  • Closed

  • Angelica Nunez del Campo

  • N/A

  • Colombia

  • July 15, 2008

  • (as of board presentation)

    January 11, 2011

  • June 20, 2011

  • US$ 40.00 million

  • Ministerio de Vivienda Ciudades y Territorio

  • Latin America and Caribbean

  • 2011

  • US$ 40.00 million

  • B

  • Not Applicable

  • December 31, 2014

  • BANK APPROVED

  • August 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 40.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 40.00
IDA Commitment N/A
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 40.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 15, 2016 IBRD-79980 Int Charges 3,195.23
Aug 15, 2014 IBRD-79980 Int Charges 2,966.39
Feb 15, 2015 IBRD-79980 Int Charges 3,015.56
Aug 15, 2015 IBRD-79980 Int Charges 2,481.70
Mar 31, 2015 IBRD-79980 Loan Disb -130,394.46
Apr 30, 2015 IBRD-79980 Loan Cancel 5,430,394.50
Aug 15, 2013 IBRD-79980 Int Charges 3,293.19
Feb 15, 2014 IBRD-79980 Int Charges 3,194.44
Feb 15, 2023 IBRD-79980 Int Charges 5,174.46
Aug 15, 2023 IBRD-79980 Int Charges 5,174.46
Aug 15, 2024 IBRD-79980 Int Charges 5,174.46
Feb 15, 2024 IBRD-79980 Int Charges 5,174.46
Jan 11, 2011 IBRD-79980 Loan Commitment 40,000,000.00
Feb 15, 2021 IBRD-79980 Int Charges 5,174.46
Aug 15, 2021 IBRD-79980 Int Charges 5,174.46
Aug 15, 2022 IBRD-79980 Int Charges 5,174.46
Feb 15, 2022 IBRD-79980 Int Charges 5,174.46
Aug 15, 2019 IBRD-79980 Int Charges 6,671.27
Aug 15, 2019 IBRD-79980 Loan Disb -369,605.53
Aug 15, 2019 IBRD-79980 Loan Disb 369,605.53
Feb 15, 2020 IBRD-79980 Int Charges 5,174.46
Aug 15, 2020 IBRD-79980 Int Charges 5,174.46
Aug 15, 2017 IBRD-79980 Int Charges 4,069.65
Feb 15, 2018 IBRD-79980 Int Charges 4,363.82
Aug 15, 2018 IBRD-79980 Int Charges 5,407.63
Feb 15, 2016 IBRD-79980 Int Charges 2,588.06
Apr 29, 2014 IBRD-79980 Loan Cancel 34,200,000.00
Feb 15, 2019 IBRD-79980 Int Charges 6,347.36
Feb 15, 2017 IBRD-79980 Int Charges 3,872.66

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Unsatisfactory 2014-12-23
Overall Implementation Progress (IP) Unsatisfactory 2014-12-23
Overall Safeguards Rating Satisfactory 2014-12-23
Procurement Moderately Satisfactory 2014-12-23
Financial Management Moderately Satisfactory 2014-12-23
Project Management Moderately Unsatisfactory 2014-12-23
Monitoring and Evaluation Moderately Satisfactory 2014-12-23
Progress towards achievement of PDO Unsatisfactory 2014-12-23

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 40,000 low income beneficiaries with access to affordable housing in the project areasValue0.000.0040000.00
    DateOctober 13, 2009December 12, 2014December 31, 2014
    Comment
  • Finance approximately 10,000 supply-side housing grants for land development and secondary infrastructure associated with small andmedium size mixed-use land and housing development SubprojectsValue0.000.0010000.00
    DateOctober 13, 2009December 12, 2014December 31, 2014
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Subproject investments include mix of uses (multi-income residential, commercial and green areas)Value-Yes
    DateDecember 12, 2014December 31, 2014
    Comment
  • 100% of Subprojects include a minimum of 50% social interest housing units (VIS) including 25% of priority interest housing units (VIP)Value0.000.00100.00
    DateDecember 12, 2014December 31, 2014
    Comment
  • 100% of parcels of selected Subproject sites have access to networked water supplyValue0.000.00100.00
    DateDecember 12, 2014December 31, 2014
    Comment
  • 100% of selected Subproject sites have access to adequate sanitation.Value0.000.00100.00
    DateOctober 13, 2009December 12, 2014December 31, 2014
    Comment
  • 100% of parcels of selected Subproject sites with access to an adequate drainage system.Value0.000.00100.00
    DateOctober 13, 2009December 12, 2014December 31, 2014
    Comment
  • 100% of parcels with access to roads with public transport stops at a distance of less than 500 mValue0.000.00100.00
    DateOctober 30, 2009December 12, 2014December 31, 2014
    Comment
  • Development of a land trust instrumentValue-partially completed. The generic model has been deYes
    DateOctober 30, 2009December 12, 2014December 31, 2014
    Comment
  • Development of a real estate development modelValue0Model DevelopedYes
    DateOctober 30, 2009December 12, 2014April 30, 2012
    Comment
  • Bidding processes for Subproject Contracts require an average of 9 months from tender to signing.Value-na
    DateOctober 13, 2009December 12, 2014
    Comment